Measures for the administration of public welfare water conservancy infrastructure construction in Hubei Province
Chapter I General Provisions Article 1 In order to establish and improve the management system and operation mechanism of public welfare water conservancy infrastructure construction and ensure the quality of the project, these measures are formulated in accordance with the relevant laws and regulations of the state and combined with the actual situation of this province. Article 2 These Measures shall apply to the construction and management activities of public water conservancy infrastructure within the jurisdiction of this province.

The term "public welfare water conservancy infrastructure" as mentioned in these Measures refers to key projects such as flood control and waterlogging elimination, farmland irrigation and drainage, soil and water conservation and water resources protection. Third public water conservancy infrastructure construction to implement the project legal person responsibility system, bidding system, construction supervision system, contract management system and other management systems. Article 4 The provincial people's government or the provincial people's government authorizes the provincial water administrative department to set up and appoint the legal representative as the project legal person of the public welfare water conservancy infrastructure project in this province, which is mainly invested by the central government and the province.

The project legal person of public welfare water conservancy infrastructure projects mainly invested by cities (including prefectures, the same below) and counties (including cities and districts, the same below) shall be established and appointed by the people's governments of cities and counties.

The project legal person of the public welfare water conservancy infrastructure project is the responsible subject of the project construction, is fully responsible for the project construction, and accepts the centralized management of the relevant water administrative departments. Fifth water administrative departments at all levels shall be responsible for the organization and management of the whole process of planning, survey, design, bidding, construction, supervision, completion acceptance and delivery of public welfare water conservancy infrastructure construction projects.

The administrative departments of development planning at all levels shall be responsible for the supervision and management of the declaration, examination and approval, planning and implementation of public welfare water conservancy infrastructure projects in accordance with the requirements of the management of capital construction procedures.

The financial administrative departments at all levels shall, in accordance with the requirements of financial management of capital construction, supervise and manage the financial activities of public welfare water conservancy infrastructure construction.

Audit administrative departments at all levels shall, in accordance with audit laws and regulations, conduct special audits and follow-up audits on major projects of public welfare water conservancy infrastructure construction.

The competent departments of development planning, finance, auditing and water administration at all levels shall establish and improve the relevant rules and regulations for the construction of public welfare water conservancy infrastructure. Sixth public water conservancy infrastructure construction projects, according to the provisions of the state should be subject to tender, tender according to the provisions of the Ministry of Water Resources on the management of water conservancy construction projects. The provincial development plan and other relevant departments shall exercise administrative supervision over the bidding activities according to law. If the state has other provisions on the above matters, those provisions shall prevail. Chapter II Plan Management Article 7 The public welfare water conservancy infrastructure construction shall strictly implement the national investment plan and capital construction procedures, and strengthen the plan management. Eighth provincial development planning administrative departments of the main responsibilities of public water conservancy infrastructure construction plan management:

(a) in accordance with the management authority and infrastructure procedures, examine and approve the relevant capital construction projects, review and prepare the relevant capital construction plans, and strive for the central investment plan;

(two) in conjunction with the water administrative department to do a good job in the implementation of the annual plan for water conservancy capital construction and the organization and coordination of major projects;

(three) in conjunction with the water administrative department to organize and guide the preparation of long-term investment plans for water conservancy construction;

(four) comprehensive use of direct investment, foreign exchange, foreign loans, national and provincial reserves and other economic means to ensure the implementation of water conservancy planning, planning and water conservancy industrial policies;

(five) to supervise and inspect the investment, construction progress and construction period. In the implementation of key water conservancy construction plans, timely put forward opinions to solve problems;

(six) in accordance with the authority of infrastructure management, examine and approve or report the feasibility study report, preliminary design, commencement report and completion acceptance report of water conservancy capital construction projects. The main responsibilities of the ninth provincial water conservancy administrative department of public infrastructure construction plan management:

(a) to organize the preparation of comprehensive management plans for provincial river basins or regions;

(two) according to the comprehensive river basin management plan approved by the state and the province, organize the preparation of the province's water conservancy project construction plan and long-term water conservancy project construction plan;

(three) according to the management authority to organize the project feasibility study report, preliminary design and commencement report review, submission and approval;

(four) to organize the preparation of the annual investment proposal plan for water conservancy projects in the province, according to the plan of the national and provincial development planning commission, to prepare and issue specific annual implementation plans, to examine and approve the annual construction budget of the project, and to supervise and inspect the implementation of the annual plan;

(five) to preside over or participate in the completion acceptance of relevant construction projects. Tenth city and county development plans and water administrative departments shall, in accordance with their respective division of labor, do a good job in the planning and management of public welfare water conservancy infrastructure construction. Eleventh public water conservancy infrastructure construction must follow the following procedures, and it is strictly forbidden to merge or surpass without authorization:

(1) Project proposal;

(2) Feasibility study report;

(3) Preliminary design;

(4) Bidding for construction;

(5) Preparation before construction (including technical design);

(6) Commencement report;

(7) Construction and implementation;

(8) Trial operation (trial operation);

(9) Completion acceptance;

(10) Post-evaluation. Chapter III Fund Management Article 12 The fund management of public welfare water conservancy infrastructure construction adheres to the principles of graded management, graded responsibility, earmarking and stressing efficiency.