How to write the inverted construction schedule?
Question 1: What is the inverted duration of the project plan? It means to finish something within the specified time, such as a project on May 30th. Aim to finish the project on May 30th, push it forward day by day, and do what work every day until the moment when you are filming the plan.

Through this push, we can find out whether the conditions I have now can meet the requirements of the project. If it matches, it can be completed. If it doesn't match, we can continue to push forward and get the total time.

Question 2: How to make an inverted construction schedule? Is there any standard? Are there any related cases? It is best to use the inverted construction schedule related to the construction project. Valves start with all the construction tasks that must be completed at the time of completion acceptance, and divide the construction progress and construction period of construction tasks in stages, thus dividing the main construction period and emergency work.

Question 3: How to arrange the construction period? If the time limit for a project is reversed, the construction progress and time limit for the construction task shall be arranged in stages starting from all the construction tasks that must be completed at the time of completion acceptance, and the main construction time limit and emergency work shall be divided.

(1) design conditions

1. Project overview: A unit project is a three-story full cast-in-place frame structure (see the construction drawing).

2. Construction conditions

1) construction period: the construction period of this project is 2 10 days. Commencement date: May+May 5, 65438.

2) Meteorological conditions: the prevailing wind direction during the construction period is easterly, the rainy season is August, and the winter is165438+1mid-October to February of the following year.

3) Construction conditions and engineering characteristics: This project is the first building in the factory, and the rest buildings are follow-up projects, and the site can be used at will.

4) Technical and economic conditions:

The location and terrain of the project are not too complicated. See the general plan for details.

Building materials used in construction can be directly transported to the construction site by highway;

The types of mechanical equipment used in the construction are not limited, and they can be selected at will;

Construction water and electricity can be connected to the site from nearby existing circuits and water pipe networks;

The labor force required for construction meets the requirements.

According to the proposed construction plan, draw the construction schedule (cross schedule and network schedule).

(1). The form of Shi Chang's comprehensive progress plan is uniformly expressed by "time scale network plan";

(2) The process name and duration shall be marked on the process, and the time scale shall be expressed in calendar coordinates (including year and month);

(3) The control date of the key working procedure of civil engineering should be an important milestone and key node, which should be highlighted in the network plan;

(4) Drawing by indirect drawing method according to the network plan of early time scale; Key lines should be placed in a prominent central position and represented by thick lines or colored lines;

(5) It is required to draw on square paper or EXCEL with appropriate specifications (the results must be printed), with neat drawings, reasonable layout, appropriate line thickness, font and symbol size;

(6) The arrangement of each working procedure shall conform to the technological process, and the commencement and completion dates of the main project and auxiliary projects shall be arranged to ensure the formation of a complete production capacity, and other provisions of the comprehensive construction schedule shall be followed. I have a better answer.

Question 4: The total duration is 244 days. How to arrange the schedule with the construction period upside down? Inverted duration is to determine the completion date according to the total duration, and then make arrangements according to the completion date. This means that your plan cannot exceed the specified completion date.

Question 5: What does the reverse construction period mean? Simply put, the construction arrangement is arranged in the reverse order of the project construction process. For example, it is required to be completed on 20 12 and 1, and the time of each work is calculated from the last work of the project, provided that the previous work is successfully completed on time.

Question 6: How to arrange the "inverted schedule" of the next municipal project? According to the completion time of each subproject arranged by the owner, subtract the current time to get your available time, and then allocate the number of completed projects in each cycle (which can be days, weeks or months) according to the available time.

Question 7: How to use project 2007 to make the construction schedule Basic steps: Set the working time and the start (or end) date of the project, and set the new task as "automatic task" (easy to adjust automatically); In the resource sheet, list the details of the resources used in the project; Type the task name, resource name, and duration. Organize with summary tasks (see WBS code for details); Set the relationship between tasks (mainly predecessor tasks); If necessary, set schedule restrictions for some tasks; Finally, adjust and optimize the project plan.

Question 8: How to refine the time node, reverse the construction period, and implement the responsibility layer by layer is to complete one thing within the specified time, such as completing a project on May 30. Aim to finish the project on May 30th, push it forward day by day, and do what work every day until the moment when you are filming the plan. Through this push, we can find out whether the conditions I have now can meet the needs of the project to return to the present ...

Question 9: How to arrange your question according to the three-day cycle in the inverted project schedule is a bit vague. What kind of project is it? See if each process can be arranged. If you can rank it, it will be no problem. As a building project, the standard floor has the following working procedures: setting out, binding reinforcement, scaffolding, supporting wallboard and platform formwork, binding reinforcement of beam and slab, and pouring concrete. Among them, the binding and setting-out of wall column reinforcement can basically be carried out at the same time, and the erection and binding of wall column reinforcement can also be carried out at the same time. However, after the completion of concrete pouring, according to the specification, it must reach 1.2MPa before people can enter here, so there is an intermittent time, about one night, depending on the temperature of course. If it is applied in winter, I suggest you close the floor and raise the temperature. You can work overtime at other times, and you should be able to arrive in three days. We used to work faster. But some measures should be taken to ensure the quality.