Supervision diary recording method:
I. Construction activities
1, construction site, content: work on key lines, work on important parts or nodes, and other work that needs to be recorded by the project supervision team.
2, engineering, materials, machine dynamics
Workers: the number of workers in the main types of work on site (such as steel workers, carpenters, masons, scaffolders, etc.). ), and the availability of the main management personnel of the project department (project manager, builder, quality engineer, safety officer, etc.). ).
Materials: main materials (including components) entering and leaving the site that day.
Machinery: refers to the quantity and operation of the main machinery and equipment on the construction site (whether there are faults, troubleshooting time, etc.). ), as well as the main mechanical equipment in and out.
II. Supervisory activities
1, patrol: patrol time or frequency, and optionally record important information during patrol according to actual conditions;
2. Acceptance: the place, content, result and receiver of acceptance;
3. Witness: witness content, time and witness;
4. Site: content, location, site owner and site record number;
5. Parallel inspection: location, content, inspector and parallel inspection record number;
6. Engineering measurement: complete the measurement of engineering quantity and change the measurement of contact content (required);
7. Examination and approval: examination and approval of relevant schemes and inspection lots (specialty, technology, etc.). ), raw materials, schedule, etc. (Only record the relevant audit number and approval form)
Three. Existing problems and solutions
In the past day, through a series of supervision work, what problems have been found in project quality, progress and investment, and how did the supervision team deal with these problems? * What is the treatment result? Detailed records should be made. Some major quality and safety accidents should be handled according to the prescribed procedures, and relevant information should be recorded, saved and sorted out according to regulations, and the records in the diary should be concise and to the point.
Fourth, other things.
1, supervision instruction (supervision notice, memorandum, rectification notice, change notice, etc. );
2. Meetings and meeting minutes;
3. communication;
4. Safe working conditions;
5. Rationalization suggestions;
6, construction leading departments or construction administrative departments to check the situation;
Five, the duty record
Signature of the supervisor on duty that day.