The preparer, reviewer and technical director in the completion stamp shall be signed by the relevant personnel of the project team of the construction unit. Compiler is documenter or builder, reviewer is project builder (project manager), and technical director is project engineer. Date Fill in the date of completion acceptance (comprehensive acceptance).
The design change notice is the basis for modifying the drawings after modification, which is equivalent to the effect of the drawings and should be attached to the modified drawings (as-built drawings) of the page.
The as-built drawings shall be arranged in the same order as the original design drawings.