Model river dredging contract 1
Party A: (hereinafter referred to as Party A)
Party B: (hereinafter referred to as Party B)
In accordance with relevant laws, regulations and rules such as "People's Republic of China (PRC) Construction Law" and "People's Republic of China (PRC) Safety Production Law", the legal rights, obligations and economic responsibilities of all parties in the construction shall be defined. According to the specific conditions of the project, based on the principle of equality and mutual benefit, the two parties reached an agreement on the resources related to the project construction and signed the following contract terms.
I. Project Overview and Contracting Method
1, Project Name: Subitem Project of River Dredging for Reconstruction Project of West Section of Third Ring Street in zhuanghe city.
2. Project Location: Third Ring Road, zhuanghe city.
3. Project contracting method: contracting for work and materials.
4. Project Overview: The project is located in Sanhuan Street, zhuanghe city. Because the river is open for a long time, the domestic garbage in the river is cleaned up. The main engineering quantities are as follows: according to the drawings, the open channel length 1089.7m, the dredging depth of 0.6m, the same width as the river course, and the dredging earthwork volume of 2530m3. According to the drawings, the culvert length is 609.06m, the dredging depth is 0.6m, the same width as the culvert, and the dredging earthwork volume is 1739.5438+0m3.
Second, the content of the journey.
Clean up river silt and domestic garbage, and the engineering quantity is about 3620 cubic meters.
Third, the project cost
The project cost is one hundred and fifty thousand yuan only (¥150,000.00 yuan). This project is a lump sum price, and the cost overrun will not be compensated.
Fourth, the project cycle
Project start date:
Verb (abbreviation of verb) quality requirements
Engineering quality standard: Party B shall clean up all silt and domestic garbage in the river according to Party A's requirements, and it shall be qualified only after reaching the handover requirements, and carry out the construction according to the bidding drawings.
Terms of payment for intransitive verbs
After the project is completed and accepted by the construction unit and relevant departments, Party A shall pay Party B 100% of the total project cost.
Seven. Responsibility of both parties
1. Party A is responsible for providing the use and design requirements of the whole project; Sampling inspection of Party B's construction quality and progress anytime and anywhere; Party A shall ensure that Party B's construction will not be affected. Party A is responsible for coordinating and solving the group disputes arising in the construction process, which will not affect Party B's construction in principle; Party A shall communicate with the supervisor and the construction unit every day to verify the earthwork quantity. Party A shall provide Party B with a specific construction plan, and Party B shall strictly abide by the detailed rules of the plan. If the construction is not carried out in a barbaric manner according to the operation flow, all consequences shall be borne by Party B..
2. Party B: The garbage spilled by Party B on the road surface during sludge transportation shall be cleaned up in time, and if it causes adverse effects, Party B shall coordinate and solve it by itself; In the process of dredging culverts, Party B shall do a good job of ventilation, and resolutely put an end to personal safety accidents caused by lack of oxygen of staff due to poor ventilation. If it happens, all consequences shall be borne by Party B: during the culvert construction, workers must wear anti-virus equipment, and no open flames are allowed in the culvert. If the gas in the culvert explodes and burns due to smoking and other factors, resulting in personal safety accidents, all consequences shall be borne by Party B: in the process of culvert cleaning, it is necessary to dig holes at the top of the culvert, slot and lay asphalt pavement, and make warning signs at the entrance to avoid personal safety accidents caused by non-working personnel approaching. If it happens, all consequences shall be borne by Party B, and it shall be restored immediately after the construction is completed, so as to reduce the impact on road traffic.
Toxic and harmful gases in culverts are measured every half hour, and the values are recorded in real time. If the toxic and harmful gases in the culvert are not measured due to Party B's reasons, Party B shall bear all consequences. The power supply in the culvert must be below 12V (including 12V). It is forbidden to pull the power supply without permission. If Party B connects the power supply privately and exceeds 12V, all consequences shall be borne by Party B.. During the construction period, all workers are forbidden to drink alcohol. If personal injury or death is caused by drinking, all consequences shall be borne by Party B; Other unfinished matters shall be implemented with reference to the specific construction plan.
Eight. Other matters:
Party A and Party B agree to reach the following agreement:
1. If the construction cannot be carried out due to special circumstances or force majeure, the construction period can be postponed; All losses caused by breach of contract shall be borne by the breaching party.
2. If Party A or Party B breaches the contract and fails to perform the contract, they may appeal to the superior competent department or arbitration institution.
3. Party B shall carefully and strictly carry out safe construction in accordance with the laws and industry regulations that define construction safety in foreign countries. If the construction project causes personal and property damage within the reasonable service period due to Party B's reasons, Party B shall be liable for damages.
4. Other matters not covered shall be settled by both parties through negotiation.
5. This contract is made in duplicate, which shall come into effect after being signed by both parties, and each party holds one copy, with the same legal effect.
Representative of Party A: Representative of Party B:
(Signature and seal) (Signature and seal)
Date, month, 20
Demonstration Contract for River Dredging II
Party A: (Employer)
Party B: (Contractor)
When the rainy season comes, the drainage plugging point of the pipe trench should be dredged immediately to meet the drainage safety requirements of enterprises and roads in the park and avoid losses. According to the actual situation of this project, through friendly negotiation between both parties, Party A contracted out the dredging and replacement of damaged cover plates of sewage ditches on Zhuguan Road and Wei Ba Road to Party B for construction. In order to clarify the responsibilities, rights and obligations of both parties, this contract is specially formulated and both parties shall abide by it:
I. Overview of the Project:
1, project name and quantity: dredging, dredging and cover replacement works for Zhuguan Road (Weijiulugou 104 to 950m) and Wei Ba Road (920m from Zhuguan Road to the north wall of the sewage treatment plant).
2. Project Location: Zhuguan Road and Wei Ba Road.
3, project contracting content:
Sewage pipes and ditches along the line shall be dredged, wells shall be inspected and cover plates shall be replaced.
4. Project contracting form: general contracting.
Second, the project period:
The project duration is 30 days. When the construction site has the construction conditions, Party A shall notify Party B three days in advance. Party B must enter the site on the second day after receiving the notice (that is, calculate the construction period), and complete the project within the specified time limit and hand it over to Party A for use.
Three. Total project cost and payment method:
1. This project is contracted out to Party B in the form of contract work and materials, and the tax-included cost is _ _ _ _ _ yuan per meter.
2. After signing the contract, Party A shall pay 30% of the project price to Party B, and after the project is completed and accepted by Party A, Party A shall pay the remaining 70% of the project price to Party B..
3. Party A pays the project payment by transfer, and Party B issues an official invoice of the same amount to Party A when receiving the payment.
Four. Responsibilities, rights and obligations of both parties:
1. Party A shall provide Party B with necessary construction conditions and supervise and inspect the quality, safety and construction period of this project. If it does not meet the specified requirements, Party A has the right to require Party B to rectify immediately;
2. Party A shall pay the project payment to Party B according to Article 3 of this contract;
3. Party B must carry out the construction according to the design requirements and relevant standards and specifications, and undertake the repair and maintenance of the pipe network;
4. Party B shall be responsible for technical liability accidents and safety accidents during construction;
5. When the project meets the acceptance conditions, Party B shall notify Party A for acceptance three days in advance.
Verb (abbreviation of verb) liability for breach of contract:
Disputes arising from the performance of this contract shall be settled by both parties through consultation.
Supplementary clauses of intransitive verbs:
1. This contract shall come into effect after being signed and sealed by both parties, and shall serve as the basis for both parties to perform the contract and the final accounts of the project.
2. This contract is made in quadruplicate, with Party A and Party B holding two copies respectively.
Party A: Party B:
Legal representative: legal representative: company seal: company seal: bank:
Account number:
Time: Bank: Account Number: Time:
Demonstration Contract for River Dredging 3
Party A:
Party B:
As Party B voluntarily undertakes part of the dredging works in this bid section and part of the subcontracting works, in order to ensure that all the contents stipulated in the contract are completed on time and with high quality, and to clarify the rights, responsibilities and obligations assumed by both parties, this contract is hereby signed for the information of * * *.
I. Project name:
Second, the project site selection:
Third, the price:
Four. Acceptance method: Party A and Party B shall measure the silt top, silt bottom and geometric dimension elevation.
Verb (abbreviation of verb) stacking requirements: stacking in the place designated by Party A.
VI. Number of projects:
7. Payment method: 50% of monthly measurement shall be paid according to the completed quantity, and 80% shall be paid after completion.
Eight. Construction period: according to the requirements of Party A and the project department.
Nine. Settlement method: provide the official invoice, and handle the invoice for Party B if Party A fails to deduct 3% of Party B's payment. ..
X. contents of the contract:
(1) Party A's responsibilities:
1. Party A must provide sludge storage site;
2. Party A must provide the construction drawings in time and make technical disclosure to Party B;
3. Party A is responsible for providing technical guidance to Party B, and performing the duties of guidance, inspection and assessment on Party B's quality, progress, safe production and civilized construction during the project implementation;
4. Party A must pay the project payment in time as agreed;
5. Party A must organize personnel for acceptance and settlement in time.
(II) Party B's responsibilities:
1. Party B is equipped with sufficient personnel and machinery to meet the needs of construction progress;
2. Party B must have full-time production and safety management personnel to manage production and safety;
3. Party B must obey the management and supervision of Party A and the unified arrangement of Party A;
4. Party B shall not subcontract the project in any form. If this happens, all consequences shall be borne by Party B;
5. Party B shall not do anything that damages the interests and reputation of Party A;
6. Party B's machinery must have a certificate;
7. Party B must handle work-related injury insurance for construction personnel; Party A's project department collects copies of Party B's personnel's ID cards and submits them to the company office for accident insurance. The expenses shall be borne by Party B..
8. Party B must ensure safe and civilized construction, and take full responsibility for all safety problems during construction;
XI。 Settlement of disputes
(1). All disputes related to the company arising from the performance of this contract shall be settled by both parties through consultation; If negotiation fails, it shall be submitted to the judicial department for handling;
(2) For matters not covered in this contract, supplementary terms shall be negotiated (supplementary terms have the same legal effect as this contract).
Matters not mentioned above shall be implemented in accordance with national laws and relevant regulations. This contract shall come into effect after being signed by both parties in triplicate, with Party A holding two copies and Party B holding one copy.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Sample of River Dredging Contract 4
Party A:
Party B:
I. Project name:
Second, the project site selection:
3. Project content: (including the main earthwork construction of the river channel and the auxiliary work of completing the main earthwork, including dam building, dam demolition, flood control embankment and embankment filling with drainage, etc.). ).
Four, engineering standards:
1. River standard: bottom width meter, bottom height meter and slope ratio. According to the river construction specification, the maximum error of the center line is about 20 cm, the error of the river bottom elevation is not greater than +3.0 cm-20 cm, and the average value is not higher than the design elevation; The bottom width is 30 cm, and the average value is not less than the design bottom width; The local slope ratio is 1:n( 1 5%), and the overall slope is not steeper than the design value (1:n). Others shall be implemented in accordance with relevant technical specifications and standards.
2. Other requirements:
5. Civilized construction and engineering safety: Party B shall conscientiously do a good job in civilized construction and safety, and Party B shall be responsible for the economic compensation and safety accidents that do occur due to Party B's responsibility during the construction.
Construction time of intransitive verbs: this project will be completed from, to, with a construction period of days.
Seven. Contract price and payment method: the total earthwork quantity of this project is tentatively set as m3, the comprehensive unit price is RMB /m3, and the total contract price is tentatively set as RMB (in figures). Payment by installment is. The final calculation of the project shall be subject to the quantities approved by the supervisor.
Eight. Responsibilities of both parties:
Party A's responsibilities:
1. Before starting work, Party A shall define the relevant tasks and requirements of the project construction according to relevant documents and specifications.
2. Party A shall organize examination and approval in time after receiving the commencement application or commencement report submitted by Party B..
3. Party A shall provide relevant items for Party B to organize the construction according to the contents of the bidding documents or consensus.
4. Party A shall pay on time according to the payment method stipulated in this contract.
5. Party A shall timely coordinate the contradictions in the construction process.
Party B's responsibilities:
1. Party B guarantees to complete the project tasks with good quality on schedule according to the contract contents (including the bidding documents and written documents agreed by both parties), and will be fined RMB/day if it is completed beyond the time limit.
2. Before the start of construction, Party B must go through all the formalities related to the construction according to the regulations, including: paying duplicate deposit RMB before signing the contract; Provide Party A with the construction plan; Commencement report, etc. Otherwise, Party B shall not start work. If Party B fails to go through the above procedures within three days, Party A will disqualify Party B from winning the bid.
3. In the process of project construction, if Party B terminates the project construction without justifiable reasons, Party A will not settle the expenses of the construction department and deduct the performance bond. The consequences arising therefrom shall be borne by Party B. ..
4. Party B shall actively coordinate and handle contradictions.
Nine. Others:
X. Matters not covered in this contract shall be settled by both parties through consultation.
XI。 This contract shall come into effect after being signed by the legal representatives or entrusted agents of the two methods and stamped with the official seal of the unit respectively.
12. This contract is made in sextuplicate, including two originals and four copies, with each party holding one original and two copies.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Model River Dredging Contract 5
Party A:
Party B:
Due to the construction needs of the project department, Party B voluntarily undertakes part of the dredging works in this bid section through on-site reconnaissance and friendly negotiation between both parties. In order to ensure the timely and high-quality completion of all the contents stipulated in the contract and clarify the responsibilities and obligations assumed by both parties, this contract is hereby signed for compliance.
1. Project name: huixian city Shimen Reservoir reinforcement project 1 contract.
II. Price: RMB/meter (including tax and electricity)
Three. Acceptance method: the sand egg layer and working face width required by the project construction shall prevail.
Four. Stacking requirements: the location shall be designated by Party A. ..
Verb (abbreviation of verb) engineering quantity: based on the actual engineering quantity measurement.
Payment by intransitive verbs: When Party B completes the mobilization of machinery and equipment within three days after the signing of the contract, and the project progress reaches 70%, Party A shall pay Party B 300,000 yuan within 30 days after the completion of the project, that is, 80% of the total project price, and the remaining 20% of the project price shall be paid according to the measurement allocation of the construction unit.
Seven. Project duration: from MM DD YY-MM DD YY, with a duration of * * * days.
Eight. Contract content:
(1) Party A's responsibilities:
1. Party A must provide a sludge storage site.
2. Party A must provide Party B with the construction drawings for technical disclosure in time. ..
3. Party A is responsible for providing technical guidance to Party B, and performing the duties of guidance, inspection and assessment on Party B's quality, progress, safe production and civilized construction during the project implementation.
4. Party A must organize personnel for acceptance and settlement in time. The project payment must be paid in time as agreed.
(II) Party B's responsibilities:
1. Party B shall provide sufficient personnel and machinery to meet the needs of construction progress, strictly implement the construction period requirements of Party A, and complete the contract work on time.
2. Party B must have full-time production and safety management personnel to manage production and safety; Responsible for the education of laws and regulations, safety production education and technical training of subordinates, do a good job in environmental protection and civilized construction, and bear the responsibility and extra expenses for violating the above. In case of personal injury or major equipment accident due to Party B's own reasons, Party B shall bear all responsibilities and handling expenses except compensation from the insurance company.
3. Party B must obey the management and business plan of Party A.. Violation of regulations or disobedience to Party A's personnel management will be punished according to the seriousness of the case.
4. Party B shall not do anything that damages the interests and reputation of Party A; The project shall not be subcontracted in any form; If this happens, Party B shall be responsible for all the consequences.
5. Party B must apply for work-related injury insurance for construction personnel, provide Party A's project department with a copy of Party B's personnel ID card, and submit it to the company office for accident insurance.
X. Settlement of disputes
1. All disputes related to the Company arising from the performance of this Contract shall be settled by both parties through consultation; If negotiation fails, it shall be handed over to the judicial department for handling.
2. Matters not covered in this contract shall be supplemented by both parties through consultation, and the supplementary terms shall have the same legal effect as this contract.
3. Matters not mentioned above shall be handled in accordance with national laws and relevant regulations.
XI。 This contract shall come into effect after being signed by both parties. Both parties must abide by this contract. If one party breaches the contract, it shall compensate the other party for 200,000 yuan. After the project is completed and accepted, both parties fulfill their obligations under the contract and the contract is terminated.
Twelve, due to serious natural disasters and force majeure factors, the construction period can be postponed.
Thirteen. This contract was signed in huixian city on, in duplicate, one for Party A and one for Party B, all of which have the same effect.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Articles related to five model river dredging contracts (2022);
★ Model Agreement on River Dredging Contract 2022(5 articles)
★ 5 classic contract 2022 styles.
★ In 2022, five new special contracting contracts will be added.
★ 5 demonstration articles on individual fish pond contracting in 2022.
★ Five templates for simple contracts in 2022
★ 5 copies of formal contract agreement in 2022
★ Five classic model contracts in 2022
★ Paint 5 contract templates, the latest 2022.
★ Five standard samples of construction contract in 2022.
★ The latest version of 2022 is 5 pieces of paint construction contract template.