Supervision weekly is the style of construction project supervision weekly. For your convenience, here are some samples of weekly supervision reports. Welcome to refer to them!
Project supervision week model 1 1. Image of project progress in progress
1. Time span of this period: March 22nd, 2008? 2008.3.28。
2. The work completed in the renovation project of the computer room includes: shifting the fire control box, connecting the fire control system with the building property control center, and adjusting the air conditioning equipment.
What will be completed on Saturday or next week. The work includes: laying anti-static floor; Lighting system threading; The upper part of the west wall is closed; Installation of gas fire extinguishing system; Unified adjustment of fire fighting system and air conditioning system.
3. The completed work of the five-story decoration project includes: demolition; 6, 7, 8, 9, 10 room ground dust removal; Laying of strong and weak grounding pipes (boxes).
Projects under construction include: dismantling the original air conditioning system; The ground is covered with dust.
In addition, the transformation of the power supply system on the fifth floor has been completed.
Second, the construction quality
1. There are hidden quality problems during the installation of the battery cabinet in the machine room: ○ 1 The equipment rack is not welded with special grounding screws; ○2 The equipment is not completely placed on the beam. After the supervision engineer pointed out, the construction unit completed the rectification.
2. There are some quality problems in the construction process, such as poor heat preservation of air-conditioning condensate pipes and uneven application of fire retardant coatings on fire-fighting pipes. The supervision engineer has issued a rectification instruction.
No quality accidents occurred during this period.
3. The supervision engineer has made physical acceptance of the wires, boxes, pipes, anti-static floors, fire-retardant coatings, light steel keels, bridges and other materials and equipment, and taken photos for archiving. The quality certification documents of various materials and equipment are complete and effective. No materials that do not meet the requirements of environmental protection were found to enter the site.
Third, the construction safety
When the supervision engineer inspected the site, no smokers were found. The number and location of fire extinguishers should be placed according to the requirements of the owner.
No safety accidents occurred during this period.
Fourth, the existing problems
1. The air-conditioning construction personnel on the fifth floor encountered difficulties when entering the site. After the coordination between the owner and the building property, the problem was solved. On the 27th, air-conditioning personnel went through the construction procedures.
2. During the renovation of the sixth floor computer room, due to the insufficient supply of building materials and other factors (see 3.25 Coordination Meeting Minutes for specific reasons), the renovation project was postponed for one week.
Verb (abbreviation for verb) supervises the work.
3.25 Hold on-site coordination meeting and form meeting minutes. Establish the guiding ideology that the decoration project is mainly based on SZ architectural decoration company, with Levin as the general manager. Other construction units are required to obey management and strengthen mutual cooperation.
Issue work contact sheet 1 copy, and put forward specific requirements for grounding of anti-static floor.
18 kinds (batches) of building materials and equipment enter the site for acceptance. The quality of five kinds of materials (batches) such as 1.5mm2 flame retardant wire, light steel keel, bridge frame and electric tube for fire fighting was tested, and no unqualified products were found.
For example, the construction progress of anti-static floor is lagging behind, and the installation of bridge and fan pipeline conflicts for 4 times.
Put forward five requirements for construction quality rectification. It has been implemented.
Examination and approval of project payment for computer room: 66,500 yuan.
Model of Engineering Supervision Weekly 2 I. Project Construction Progress
As of June 3, 2065, the site construction of Songpan drainage system reconstruction project is summarized as follows:
1, Xinsongpan Pumping Station Project
Last week, it was planned to complete the excavation of the first layer of soil in the pumping station and the erection of the second layer of steel support; Actually completed the first layer of earthwork excavation * * * 4000m3, and the second layer of steel support is under construction;
Last week, it was planned to complete the steel binding construction of the bottom plate of the culvert in the second section of the outlet pool, and the pouring of the bottom plate of the culvert in the second section of the outlet pool was completed as planned.
2. Drainage and outlet culverts
Last week, it was planned to complete the steel binding construction of the bottom plate of the culvert in the second section of the outlet pool, and the pouring of the bottom plate of the culvert in the second section of the outlet pool was completed as planned.
Second, this week's material acceptance and testing:
This week * * * comes into play to use concrete 130m? Make two groups of compressive test blocks, and impermeability test block 1 group.
Third, the construction quality
1, check and accept the installation quality of reinforcement binding on the bottom plate of culvert in the outlet tank, which meets the requirements of design drawings and construction specifications.
2. There is a lot of rain in the near future, so the surface water in the foundation pit should be eliminated in time, and no water can be accumulated in the foundation pit, so as to reduce the unfavorable factors to the foundation pit and avoid affecting the next construction.
3. This week, witness and sample the steel bar to enter the site for inspection.
Four, safety and civilized construction situation
1. After the excavation of the foundation pit on the first floor of the pumping station, the surrounding buildings, flood control walls and outlet culverts were monitored, and the monitoring data has no alarm value for the time being;
2. The retaining wall at the gap of the pump station body has been completed, and the temporary enclosure is being installed;
3, safety inspection every week, the construction site fire equipment and distribution box safety inspection records are complete.
Verb (abbreviation for verb) Work plan for next week
1. Safety inspection during foundation pit excavation of pumping station and quality monitoring during steel purlin support installation.
2. Quality inspection of steel binding of the second section wallboard of outlet box culvert and installation quality inspection of bent frame and formwork.
3. During the dewatering process, inspect the well point of the pumping station to check whether the dewatering work is normal, and check the water level before the secondary excavation.
4. Participate in witness sampling inspection and supervision parallel inspection of raw materials.
5, urge the construction unit to do a good job of safety education and self-inspection on the construction site.
The supervision of intransitive verbs
1, supervision committee1;
2. 1 supervision safety inspection record;
;