Old building renovation procedures and guidelines
1.
Preparations for adding an elevator
1.
Survey on the intention to install elevators in existing residences
Conduct an intention survey on the owners of the building to install elevators, and compile a signature form for adding elevators.
2.
Collect copies of the property certificate and ID card (in duplicate) from the owner who agrees to install an elevator, and sign the copies. (When applying for planning and construction in Yuexiu District, you need to provide the original real estate certificate or purchase a real estate certificate search form from the Housing Authority)
3.
Entrust a design institute to do the planning and construction design for adding an elevator
1) When planning and submitting construction drawings, the original floor plans, sections, elevations, foundation drawings and other drawings of the building must be provided.
2) Two 1:500 terrain blueprints and one electronic file need to be purchased from the Guangzhou Urban Planning, Survey and Design Institute (it takes 3 working days)
3) Design Institute It takes time to complete the planning and construction application drawings (one week)
4.
Submit planning and construction application materials
The owner’s representative brings his or her ID card and a copy to the district planning office The construction project management section of the bureau applied for review of the construction plan for adding an elevator. The following information is required:
1)
A signature form agreeing to install an elevator and a letter of authorization from the owner’s representative;
2)
Original real estate certificate (or search form purchased by the housing authority) and copy, copy of ID card with owner's signature;
3)
Planning and construction drawings, structural safety instructions and other information (provided by the design institute)
5.
Review of the architectural design plan for adding an elevator (reviewed by the District Planning Bureau, which takes one month)
6.< /p>
Pre-approval announcement for adding an elevator (10 days)
1)
Entrust the district notary office to notarize
2)
The Planning Bureau produces a formal sign
7.
Planning permit for additional elevators
The "Additional Elevator Planning Permit" will be issued 10 working days after the pre-approval announcement is completed. Elevator Planning Permit".
8.
The design institute completed the construction drawing design of the additional elevator (one week)
9.
Submit the application to the local government with the planning permit The power supply station applies for electricity.
10.
The owner shall invite bids from the construction team that plans to participate in the elevator construction project based on the elevator construction drawings and determine the construction team.
11.
The construction team enters the site for construction
The civil construction will take about 2 to 3 months (the steel structure stairwell will be completed in 2 months), and the elevator installation and commissioning 1 month.