Current location - Quotes Website - Personality signature - Experts pointed out that what should the hydropower installation administrator do specifically?
Experts pointed out that what should the hydropower installation administrator do specifically?
Indoor drainage system

Installation of drain pipes and fittings

One to five floors

five

titular

Installation of rainwater pipes and fittings

One to five floors

1

titular

Sanitary ware installation

Sanitary ware installation

One to five floors

five

titular

Installation of water supply fittings for sanitary ware

One to five floors

five

titular

Installation of sanitary ware drainage pipeline

One to five floors

five

titular

1

three

six

27

titular

architecture electric

Install power mains

Installation of cable tray and laying of cable in the tray

One to five floors

five

titular

Electric lighting device

Installation of lighting distribution box

One to five floors

six

titular

Wire conduit laying

One to five floors

five

titular

Installation of electric wire through pipe

First to second floors

five

titular

Cable head manufacturing, wiring and line insulation test

One to five floors

five

titular

Installation of special lamps and lanterns

One to five floors

five

titular

Installation of ordinary lamps and lanterns

One to five floors

five

titular

Installation of switches and sockets

One to five floors

five

titular

Installation of lightning protection and grounding device

Power-on trial operation of building lighting

One to five floors

five

titular

Installation of grounding device

Artificial grounding device

1

titular

Local equipotential bonding in bathroom

One to five floors

five

titular

Lightning protection downlead laying

1

titular

Installation of lightning arrester

Roof covering method

1

titular

1

four

54

titular

Construction data: serial number

Material name

number of pages

Reserve bill

1

Design disclosure and joint review of construction drawings

three

2

Special construction organization design scheme for hydropower installation

30

three

Engineering (design) change contact list

four

four

Main equipment and materials, factory certificate and test report

48

five

Acceptance record of concealed works

17

six

Installation record of power and lighting distribution cabinet (box)

seven

seven

Cable tray installation inspection record

1

eight

Cable laying and insulation resistance test records

2

nine

Test record of insulation resistance of distribution line

4 1

10

Electrical insulation resistance test record

2

1 1

Wiring inspection records of lines, sockets and switches

10

12

Simulation test record of leakage protection device

five

13

Lighting full-load power-on commissioning record

five

14

Hidden record of grounding device construction

1

15

Grounding resistance test record

1

16

Installation record of lightning rod and lightning belt

1

17

Pipeline (equipment) strength test record

10

18

Flushing record of pipeline system

1

19

Water supply pipeline water test record

three

20

Drainage pipe irrigation test record

1

2 1

Drainage pipeline water test record

2

22

Drainage pipe ball test record

2

23

Rainwater pipeline water test record

2

24

Test record of rainwater pipeline passing ball

1

25

Sanitary ware full water and water test records

five

Inspection and acceptance record number of concealed works for grounding device installation: (01-18/03-02/04-02/05-16)/06-17/(08-20/09-0/.

Division (sub-division) project name

Installation of lightning protection and grounding device

Project manager

construction organization

Receiving position

basis

Construction drawing number

Dianshi -02

Name and number of construction execution standard

GB50303-2002 Standard Drawing of Lightning Protection and Grounding Construction Organization Design for Civil Buildings < 97 Zhejiang D2 >

Name of subdivisional work/inspection lot number

06070 1

Contact phone number or date

inspection item

Check the situation

Description or schematic diagram: Carry out construction according to electrical drawing -02, and install lightning protection and grounding devices as required. The two main bars in the lower floor of the ground beam of the building foundation are welded around and welded with the two main bars in the pile foundation at each lightning protection downlead as a grounding device. Lightning protection grounding, protective grounding and equipment grounding share a grounding body. The lightning protection downlead is welded with the foundation grounding device by two φ 16 main bars in the pile, and crosses 1, 6, 10, 12, 16, 20 and 1 axis on the A and H axes. Set the main equipotential grounding bus at the electrical shaft, and lead out the standby grounding according to the electrical drawing -02. The construction quality meets the design requirements and construction acceptance specifications. See electrical drawing -02 for details:

Welding of foundation reinforcement and grounding grid

comply with the requirements

Grounding bus laying -40*4 galvanized flat iron

comply with the requirements

Welding of lightning protection downlead and column reinforcement

comply with the requirements

Inspection and acceptance opinions

Professional quality inspector of the construction unit (signature): professional technical person in charge of the project (signature): July 2, 2007

Professional supervision engineer (signature): (professional and technical person in charge of the project of the construction unit) year month day.

Inspection and acceptance record number of concealed works for laying electric wires and conduits: (01-18/03-02/04-02/05-16)/06-17/(08-20/09-0/.

Division (sub-division) project name

Electric lighting device

Project manager

construction organization

Receiving position

Single roof

Construction drawing number

Electric Power Application -03, 04

Name and number of construction execution standard

Atlas of construction organization design of installation engineering and construction and installation engineering (3) Electrical engineering

Name of subdivisional work/inspection lot number

060502

Contact phone number or date

inspection item

Check the situation

Description or schematic diagram: (1 ~ 1 1) The lighting of the shaft on the first floor and the laying of the wire and conduit of the socket on the second floor shall be carried out according to the minutes of blue prints.the design, the design contact sheet and the electrical drawings -03 and 04. Wires and conduits are laid with PVC pipes, and the joints are tight and firm. The conduit is laid between two layers of steel bars, and the protective layer meets the requirements of concrete. The conduit and lamp holder box are firmly bound and fixed in the concrete slab, and the position is accurate. Before laying the conduit, check that there is no sundries and blockage in the conduit, the conduit incision is smooth and burr-free, and the junction box is connected with a special terminal. The bending half-warpage of the pipe is ≥ 10D, the bending straightness is < < 0. 1D, and the pipe has no cracking and wrinkling. All materials and specifications meet the requirements, and the construction quality meets the design requirements and construction acceptance specifications. See electrical drawings -03 ~ 04 for details.

Laying PVC20 in conduit

comply with the requirements

Installation of lamp holder box

comply with the requirements

Inspection and acceptance opinions

Professional quality inspector of Hege construction unit (signature): professional technical person in charge of the project (signature): August 2007 16.

Professional supervision engineer (signature): (professional and technical person in charge of the project of the construction unit) year month day.

Inspection and acceptance record number of rigid waterproof casing embedded concealed works passing through the floor slab: (01-18/03-02/04-02)/05-16/(06-17/08-20/09-)

Division (sub-division) project name

Installation of indoor drainage pipes and fittings

Project manager

construction organization

Receiving position

Single roof

Construction drawing number

Shi Shui -03

Name and number of construction execution standard

Installation project construction organization design and building drainage rigid PVC pipe installation 96S406

Name of subdivisional work/inspection lot number

05020 1

Contact phone number or date

inspection item

Check the situation

Description or schematic diagram: (1 ~ 1 1) The rigid waterproof casing of the first floor roof of the shaft shall be constructed according to 03 water drawings and drawings minutes, and the water supply and drainage pipes shall be embedded with rigid waterproof casing, with accurate position and firm fixation. The casing specification shall be equal to or higher than that of the pipeline passing through the floor, and the casing wall thickness and wing ring shall meet the requirements. All materials and specifications meet the requirements. The construction quality meets the design requirements and construction acceptance specifications. See Water Application Diagram -03 for details.

The water supply and drainage pipeline crosses the rigid floor slab in waterproof casing DN50 ~ 100.

comply with the requirements

Inspection and acceptance opinions

Professional quality inspector of Hege construction unit (signature): professional technical person in charge of the project (signature): August 2007 16.

Professional supervision engineer (signature): (professional and technical person in charge of the project of the construction unit) year month day.

Package the divisional works of each monomer into a volume, including cover, list, division, sub-item, material quality assurance (if there are more monomers, the materials will be in another volume), concealed works records (according to time), test records (according to the numerical order in the upper corner of the table), sub-items and inspection lots (according to the specified numerical order, because the files do not accept sub-items, it is convenient to take them down later).

Hydropower installation mainly includes building electricity, water supply and drainage, intelligent building division, and sprinklers are listed as a division in some places. Generally, divisions, sub-divisions and sub-items can be determined according to GB50300.

Concealed records can be carried out according to actual concealed works, and inspections can be carried out according to local forms and actual conditions. (In fact, these tests are stipulated in the construction and acceptance specifications). For more information, please visit/