Management regulations for project shutdown and resumption of work?
1. According to the provisions of the supervision contract and the scope of supervision work, the supervision unit has the right to issue a notice of suspension of construction when it encounters major safety and quality problems in engineering supervision, and the authority to issue a notice of suspension of construction belongs to the chief supervision engineer.

2. When the notice of suspension of work is issued, the chief supervision engineer shall determine the scope of suspension of work according to the scope and degree of influence of the suspended project and the stipulations of the supervision contract and the construction contract. When one of the following conditions is met, a shutdown notice can be issued:

2. 1 The construction unit requests to suspend the construction, and the project needs to suspend the construction;

2.2 When the safety and quality problems of Xie Wei are found in the engineering construction or installation, the work must be stopped to ensure the engineering quality and safe and civilized construction;

2.3 In case of emergency, the construction or installation of the project must be suspended;

2.4 The construction contractor carries out construction and installation without applying for permission to start construction, or refuses to be managed by the supervision unit;

2.5 The construction contractor uses building materials that have not been inspected or tested in the project, or uses building materials that have not been inspected and signed by the supervision engineer;

2.6 After the suspension notice is issued and before the application form for resumption of work is issued, the construction contractor continues the construction or installation without authorization.

3. If the construction contractor carries out construction or installation without authorization after issuing the shutdown notice and before issuing the application form for resumption of work, the supervision unit shall issue the shutdown notice again after discovering it, and require the construction contractor to take further measures to ensure the normal construction and supervision order of the project.

4. When a major project or event needs to be stopped, but it will affect the progress of the project milestone or the time limit for the critical path, the supervision unit shall reach an agreement with the construction unit in advance before issuing a project stop order and reporting it to the construction unit for approval.

5. Due to reasons other than those of the construction contractor and the reasons in Articles 2.2 ~ 2.6, the supervision unit shall negotiate with the construction contractor about the construction period and expenses before issuing the suspension notice.

6. When the project is shut down due to the reasons of the construction unit or other reasons other than the construction contractor, the supervision unit shall truthfully record the actual situation, and sign the application form for resumption of work submitted by the construction contractor in time when the shutdown factors are eliminated and the conditions for resumption of work are met, and continue the construction with the consent of the construction unit.

7. If the project is stopped due to the reasons of the construction contractor, the construction contractor may submit the application form for resumption of work, rectification report and other related materials when the conditions for resumption of work or installation are met. After the approval of the supervision engineer, the chief supervision engineer signs the application form for resumption of work, agrees to the construction contractor to continue the construction, and reports it to the construction unit for approval.

8. Within three months after the application form for resumption of work is approved by the construction unit, the supervision unit shall, in conjunction with the relevant parties, deal with the time limit for a project related problems caused by shutdown according to the contract.