Current location - Quotes Website - Personality signature - How to write a construction project introduction in a construction project contract?
How to write a construction project introduction in a construction project contract?
So how to write the construction contract? The following information about how to write a construction contract was brought by Zhong Da Consulting. The specific content is for your reference.

Party A (Employer):

Party B (contractor):

In accordance with the Contract Law of People's Republic of China (PRC) and relevant laws and regulations, in line with the principles of voluntariness, equality and consensus, combined with the actual situation of the project, and in order to ensure the interests of all parties, the following agreement is reached through consultation:

I. Contents of the Project

Second, the project site selection

Third, the project cycle

1. The total duration of this contract starts from and ends at.

2. In case of the following circumstances, the construction period shall be postponed accordingly.

(1) The construction site does not conform to the safety construction;

(2) Major design changes within the design scope;

(3) Force majeure natural disasters (such as typhoons, earthquakes, wars, etc.) affect the project progress;

(4) Party A cannot pay the project payment as stipulated in the contract.

Party B shall report the contents of the delay and the economic expenses arising therefrom to Party A within ten days after the above situation occurs. Party A's representative shall confirm and reply within ten days after receiving the report. If Party A fails to reply to the document channel of China Education Universal Network within the time limit, Party B may regard this request as confirmed.

Four. Project price Total project price: RMB only (¥).

Verb (abbreviation of verb) payment terms

1. After the contract comes into effect, Party A shall pay Party B 50% of the total project price as an advance payment, that is, RMB ×××× Yuan only (¥);

2. After the project is completed, Party A shall pay 40% of the total project price to Party B within one week, that is, RMB ×× Yuan only (¥);

3. After the acceptance of the project, Party A shall pay all the balance to Party B within one week, that is, RMB ×× Yuan only.

VI. Project Acceptance

1. After the project is completed, Party B shall submit a written application for completion acceptance to Party A. Party A shall arrange the acceptance within 7 days and notify Party B to participate in the acceptance. If Party B fails to arrange acceptance due to Party A's reasons 7 days after submitting the application acceptance report, it shall be deemed that the project meets the requirements of the design and construction plan, operates normally and is qualified for acceptance.

2. If Party A needs to start construction without acceptance, it must consult with Party B before it can be used. If construction is started without Party B's consent, it shall be deemed as qualified.

3. If the whole project is accepted, the completion acceptance date is the completion date.

4, the project failed to pass the acceptance, causing controversy, request a third party acceptance.

Seven, acceptance criteria

This project is accepted according to national standards according to relevant design schemes and drawings; If there is no national standard, it shall be accepted according to the industry standard.

Eight. Rights and obligations of both parties

1. Party A's rights and obligations are designated as on-site representatives to coordinate Party A's related matters. During the execution of the project, the signatures of all designated personnel shall be regarded as the behavior of Party A..

(1) is responsible for the supervision of this project and actively coordinates the construction cooperation.

(2) Be responsible for supervising Party B's progress, installation quality, safety protection and comprehensive management.

(3) Provide favorable site conditions for construction.

(4) Review the project progress.

(5) Be responsible for the review and confirmation of drawings and schemes, and supervise and inspect the project progress, project quality, concealed works, supporting works and contract implementation, design drawings change visas, intermediate acceptance of projects and other necessary visas.

(6) Be responsible for the completion acceptance, and organize the acceptance within one week after receiving all the completion data submitted by Party B. ..

(7) Pay the price stipulated in this contract to Party B according to the contract.

2. Rights and obligations of Party B

(1) The construction shall be carried out in strict accordance with the design drawings, and the quality and technical indicators shall meet the requirements of various standards and specifications of the project.

(2) Report the problems found in the construction to Party A in time and propose solutions.

(3) Prepare the construction organization plan, general construction schedule plan, material mobilization plan and completion notice, and send them to Party A in time.

(4) Provide technical data for completion acceptance, prepare technical drawings for completion, handle project completion settlement and participate in completion acceptance. The completion data shall meet the requirements of Party A..

(5) Organize a construction team with technical level, and define the on-site technical and construction leaders and main management personnel. Technicians are not allowed to change at will.

9. No terms of service.

X. liability for breach of contract

1. If the completion of the project is delayed due to Party A's reasons, it shall be regarded as Party A's breach of contract, and Party A shall pay liquidated damages to Party B. The liquidated damages shall be calculated as 0.5% of the total contract price, and the total amount of liquidated damages shall not exceed 10% of the total contract price.

2. If the completion of the project is delayed due to Party B's reasons, it shall be deemed as Party B's breach of contract, and Party A shall be paid liquidated damages ... The liquidated damages shall be calculated according to the total contract price ×0.5% of the delayed days, and the total amount of liquidated damages shall not exceed 10% of the total contract price.

3. As Party A fails to pay Party B as agreed in the contract, it shall be regarded as a breach of contract, and Party A shall pay Party B liquidated damages. The liquidated damages shall be calculated according to the total contract price ×0.5%× days of delay, and the total liquidated damages shall not exceed 10% of the total contract price.

4. During the execution of the contract, if either party unilaterally terminates the contract without reason, it will be regarded as breach of contract, and the breaching party shall pay 65,438+00% of the total contract price to the observant party as liquidated damages.

XI。 Alteration and termination of the contract

1. After this contract comes into effect, except for force majeure (war, serious flood, fire, typhoon, earthquake, accidents agreed by both parties as force majeure), Party A and Party B shall not change or terminate this contract without reason.

2. During the performance of the contract, in case of force majeure, both parties shall take effective measures to reduce the losses and prevent the losses from expanding. If it is really necessary to change or terminate the contract, the party requesting the change shall notify the other party in time, and the other party shall give a reply within 3 days after receiving the notice. If no reply is made within the time limit, it shall be deemed as consent.

3. If Party A fails to pay according to this contract, and the deferred payment period of any sum reaches 60 days, Party B has the right to suspend the performance of its obligations under this contract; If Party A's deferred payment period reaches 120 days, Party B has the right to terminate this contract and demand Party A to pay corresponding compensation.

4. If Party B fails to complete the project as scheduled and the extension period reaches 60 days, Party A has the right to suspend its obligations under this contract; If the extension period of the whole project reaches 120 days, Party A has the right to terminate this contract and demand Party B to pay corresponding compensation.

5. If this contract is modified or terminated, the losses caused thereby shall be settled by both parties through consultation.

Twelve. Dispute resolution method

Any dispute arising from or related to the signing, performance, dissolution and termination of this contract shall be settled by both parties through friendly negotiation. If negotiation fails, both parties agree to bring a lawsuit to the people's court where the contract is signed.

Thirteen. other terms

During the performance of this contract, both parties can determine the matters not covered in this contract through consultation according to the actual situation.

Place of signing the contract: ××

Fourteen Text and effect of contract

This contract is made in duplicate, one for each party, and shall come into effect after being signed and sealed by the representatives of both parties. The annex is an integral part of this contract and has the same legal effect as the text of the contract.

There is no text on this page. Party A:

Address:

Postal code:

Contact telephone number:

Bank of deposit:

Account number:

For more information about bid writing and improving the winning rate, click on the bottom customer service for free consultation.