Generally, the project handover certificate (on behalf of the project completion certificate) is issued after the contract acceptance, and the defect liability period termination certificate is issued after the expiration of the defect liability period.
The completion certificate of water conservancy project should be signed and sealed by several companies.
The contract acceptance certificate shall be signed and sealed by the construction, design, supervision and construction unit.
The project completion certificate can be issued by the construction (or supervision) unit.
The certificate of termination of the defect liability period shall be issued by the construction unit.
How to write the house completion certificate?
Hello!
Filing-13 Construction Project Completion Acceptance Certificate
Project Name Project Location Building Area (m2) Structure, Floor Height, Span Start Time Completion Time Construction Drawing Review DocumentNo. Construction PermitNo. Project Quality Evaluation Grade and Acceptance Conclusion: Participating in the acceptance unit Construction unit: project leader: legal representative (official seal) Survey unit: project leader: legal representative (official seal) Design unit: project leader: legal representative (official seal) Construction unit: (official seal) Person in charge: legal representative: (official seal) year month supervision unit: project leader: legal representative: (official seal) year month Japan form in sextuplicate, one for quality supervision station and one for acceptance unit.
Filing-13 Completion Acceptance Certificate of Continued Construction Project
Project name Project location Building area (m2) Structure, storey height and span Start time Completion time Construction drawing review documentNo. Construction permitNo. Comprehensive disaster prevention and acceptance: Acceptance unit Earthquake department: Project leader: legal representative: (official seal) Water conservancy department: Project leader: legal representative: (official seal) Meteorological department: Project leader: legal representative: (official seal) ...>
How to write an application report for the commencement of water conservancy projects
CB 14 Application Form for Commencement of Contract Works
CB 14 Application Form for Commencement of Contract Works
(Contract [] Joint Work Number)
Name of Contract: ContractNo.:
To: (supervision organization)
The contract project undertaken by us has completed all preparatory work and has the conditions for commencement. We are applying to start construction, please approve it.
Attachment: 1 Construction application report.
2. Documentary proof of existing construction conditions.
3.
Contractor: (full name and seal)
Project Manager: (signature)
Date: Year Month Day
After examination and approval, the contract project commencement order will be issued separately.
Supervisory organ: (full name and seal)
Supervision Engineer: (signature)
Date: Year Month Day
Note: This form is made in duplicate and should be filled in by the contractor. After the supervision institution signs the contract, the contractor, the supervision institution, the employer and the agency together with the "Contract Works Commencement Order" shall be 1 copy.
How to complete the data of 20 15 water conservancy project?
A, supervision data management
1. Supervision data must be timely sorted, true and complete, and classified in an orderly manner.
2. The chief supervision engineer shall be responsible for the management of supervision data, and assign special personnel to implement it.
3. After the supervision work in each stage, the supervision data shall be timely filed.
4. The preparation and preservation of supervision files shall be carried out in accordance with relevant regulations.
Two. Scope of monitoring data
The basic information of construction projects and technical and management documents signed and sealed by supervisors are generally collected and filed by project supervision institutions for future reference.
Three. Supervise the contents of the materials
1. According to the Code for Supervision of Water Conservancy Projects, the supervision data at the construction stage shall include the following contents:
(1). Construction contract documents and entrusted supervision contracts;
(2) Survey and design documents;
(3). Supervision planning;
(4) Supervise the detailed rules for implementation;
(5). Subcontractor qualification report;
(6). Design disclosure and minutes of the meeting of the blue prints.the design;
(7). Construction organization design (scheme) to submit for approval;
(8). The project starts to submit for approval, resumes to submit for approval and suspends the project;
(9). The main construction machinery and equipment to submit for approval data;
(10). Metrological verification data;
(1 1). Application form for selection of building materials, building components and main engineering equipment;
(12). Check the test data;
(13). Engineering change data;
(14). Concealed and inspection batch acceptance records
(15). Project schedule;
(16). List of engineering measurement and payment certificate of project funds;
(17). Supervision engineer's notice;
(18). supervision project contact list, supervision memorandum and special report;
(19). Meeting minutes;
(20). Communication;
(2 1). Supervision log;
(22). Supervision monthly report;
(23). Documents for handling quality defects and quality accidents;
(24). The unit engineering quality acceptance records, division of engineering quality acceptance records;
(25). Claim documents;
(26). Completion settlement audit opinion;
(27). Special reports such as quality evaluation report in the construction stage of the project;
(28). Supervision work summary.
2. According to the Code for Filing and Arrangement of Construction Project Documents and the relevant provisions of the state, the project supervision institution shall also file the following information:
(1) supervision bidding bidding documents for the project;
(2) the organizational form and personnel composition of the project supervision organization, the written appointment information of the chief supervision engineer, and the written notice information of the adjustment of the chief supervision engineer and professional supervision engineer;
(3) Witness inspection data of engineering materials by the project supervision institution;
(4) Station supervision records;
(5) The list of office, transportation, communication, living facilities, routine testing equipment and tools provided by the construction unit as stipulated in the entrusted supervision contract, and the handover list data after the supervision work is completed.
3. Special projects shall be filed according to the confidentiality requirements of the construction unit and the agreed data.
Four. Filing of supervision data
Project supervision institutions should generally classify, catalog, file and archive the supervision data according to the time sequence of the unit project and construction. Documents and accessories should be placed in a unified acid-free paper roll box (there should be a data catalogue in the box). Supervision data should be classified into papers according to the following requirements (in principle, they should be grouped according to the unit project and merged appropriately according to the actual project):
1. Volume I Basic Information of Construction Projects
(1). Entrusted supervision contract;
(2) Construction contracts (including all kinds of contracts, such as subcontracts and supply contracts);
(3). Construction project supervision report;
(4). Construction permit;
(5) The organizational form, personnel composition, written appointment materials of the chief supervision engineer and personnel change materials of the project supervision institution;
(6) Survey and design documents (photos); (Note: Please indicate whether the data stamp is valid or invalid);
(7). Design disclosure and minutes of the meeting of the blue prints.the design;
(8). Design supervision audit report;
(9). The project starts to submit for approval form;
(10). engineering suspension order;
(1 1). Resume report;
(12). The construction organization design (scheme) is submitted for approval;
(13). supervision bidding document;
(14). Construction bidding documents;
(15). Engineering negotiation documents;
(16). Work Evaluation Manual of Sichuan Construction Engineering Supervision Organization.
2. The second volume "project supervision agency work data"
(1). Supervision planning;
(2). Supervise the implementation details;
(3) monthly report of construction supervision;
(4). Supervision work summary (special topic, stage and completion summary);
(5). Construction supervision log;
(6). Station supervision records;
(7). Supervision memorandum;
(8). Supervision engineer's notice;
(9). Meeting Minutes and Contacts ... >>
How to find out that you or your partner have emotional cleanliness?
Emotional feelings over time:
If people love a person and really love each other, a person's heart is pure because love itself is selfish.
Single-minded people can do this by asking their partners to be single-minded, loyal and love life.
It is meaningful and interesting for people to fall in love. I still stick to my love view and miss my feelings.
Love is pure and quality, and everyone who knows how to love knows that time is the best answer.
Water conservancy project division appraisal, unit appraisal and completion appraisal. Did the construction unit do it or did the construction unit do it?
The construction unit has the most complete information.
What are the bidding documents for water conservancy projects? It is best to have detailed instructions or templates, thank you!
This should be written in strict accordance with the requirements of the tender documents, and how you are asked to write it is clearly defined in the structure and composition of the tender documents.
Is there any regulation on the size of water conservancy completion drawing?
Requirements and explanations for the compilation of completion drawings of water conservancy projects;
(a) according to the construction drawing construction without change, and stamped with the completion stamp on the construction drawing;
(two) the general drawing changes and meet the requirements of the bar change or cross change, can be changed in the original construction drawing, indicate the basis for the change in the description column, affix and sign the completion stamp;
(3) When major changes such as structural form, technology and layout are involved, or the number of columns in the drawing exceeds 1/3, the as-built drawing shall be redrawn (no stamp is required). Repainting should be based on the original drawing number, indicating the basis of change in the description column, and indicating the "completion stage" and the time, unit and person in charge of drawing the as-built drawing in the icon column. Hope to adopt! ! !
Examples of approval opinions of water conservancy project supervision
Provisions of Code for Reply of Water Conservancy Project Supervision (please refer to)
"After review, the contractor's preparatory work before construction has been completed and meets the construction conditions. It was agreed to start construction on.
Terms of examination and approval opinions:
A) agree
"After review, the problems mentioned in the shutdown order have been handled and meet the requirements of engineering quality (process flow). Both parties agree to resume work on the following projects: ×××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××
1. The project management implementation plan (construction organization design) is compiled by the project department of the construction contractor, reviewed by the company-level technical management department, and approved by the company's chief engineer. The preparation and approval procedures of the documents shall conform to the provisions of the contractor's system documents, and the signature on the cover of the documents shall be the contractor's company name and stamped with the company seal.
2. The project supervision department should consider whether the contents of the document are complete, whether the total construction schedule meets the contract period, and whether it can ensure the continuity, compactness and balance of the construction; Whether the overall construction scheme is technically feasible, economically reasonable, whether the construction technology is advanced, whether it can meet the requirements of the overall construction progress, and whether the safety and civilized construction and environmental protection measures are appropriate; Whether the layout of the construction site is reasonable, whether it conforms to the overall planning of safe and civilized construction, whether it is compatible with the overall construction progress, and whether the coordination of construction machines, materials and equipment in space and time is considered; Review whether the resource supply plan is consistent with the overall construction progress and construction plan, and put forward supervision opinions.
3. Supervision specification terms:
Terms of examination and approval opinions:
A) The construction organization design declared by the contractor meets the requirements, and its construction method will not cause the increase of the cost outside the contract. It is suggested that the conclusion of the supervisor's examination and approval is: "After examination, the construction organization design declared by you meets the construction requirements, and you agree to guide the construction according to this construction organization design".
B) The construction organization design declared by the contractor meets the requirements, and its construction method will cause an increase in the cost outside the contract, but the reason is that the increased cost shall be borne by the contractor. It is suggested that the conclusion of supervision and approval is: "After examination, the construction organization design declared by you meets the construction requirements, and you agree to guide the construction according to this construction organization design; However, according to this construction organization, the supervision of the increased cost of design and construction will not be recognized. "
C) The construction organization design declared by the contractor does not meet the requirements. It is suggested that the conclusion of the supervisor's examination and approval is: "After examination, the contents of the construction organization design declared by you are not perfect and cannot meet the construction requirements, and you do not agree to guide the construction according to this construction organization design; Please modify it according to the requirements of the supervisor (with written comments) and re-declare it before ××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××××
Precautions:
A) The construction organization design/scheme submitted by the contractor for examination and approval shall be signed by the preparer, reviewer and approver, and stamped with the official seal of the unit, with a complete date (the construction organization design, important scheme and new technical scheme shall be signed by the technical director of the contractor).
B) Carefully review whether the quality assurance measures, construction progress and resource preparation in the construction organization design meet the construction requirements and contract provisions. In particular, the construction methods and measures that will increase the cost, the use of new technologies and the safety of construction machinery should be taken as key audits.
C) When the project supervision organization examines and approves, it must have the examination opinions of supervision engineers of various disciplines. For complex/special/new technology-related construction schemes, the chief supervision engineer should suggest that the construction unit organize experts to demonstrate.
4, supervision standard terms:
Terms of examination and approval opinions:
A) The management organization is sound and the personnel qualification meets the requirements. Supervisor's comment: "The management system is sound, please follow the established management system".
3. The project supervision department review points:
A) Whether the contents of the document are complete and conform to the overall planning scheme of safe and civilized construction, and put forward evaluation opinions on the quality of document preparation;
B) Whether the management objectives of safe and civilized construction meet the project construction objectives;
C) Whether a safe and civilized construction management organization has been established and whether the responsibility system has been implemented;
D) Whether the management rules and regulations for safe and civilized construction are sound;
E) Whether the general layout of the construction site is reasonable;
F) Whether the safe and civilized construction facilities and safety signs are complete, standardized and effective, and whether the setting is reasonable;
G) Whether the safety and civilized construction measures and environmental protection measures are effective.
1. Supervision specification clauses:
Terms of examination and approval opinions:
A) "The contents of the document are complete and meet the requirements of the overall planning of safe and civilized construction".
B) "If it does not meet the requirements of the overall planning of safe and civilized construction, please make up for the measures or systems within XXX time."
3. Supervision specification terms:
Terms of examination and approval opinions:
A) "The detailed rules for the implementation of excellence are complete and meet the requirements of excellence planning".
B) "excellent implementation" > >