Question 1: What does the fire protection acceptance of construction projects include? 1] Project document list
This document list includes the acceptance from the beginning of the project bidding to the completion of the project. The list of documents is as follows:
1. Bidding documents 35. Flow indicator installation and inspection records
2. Project contract 36. Fire hydrant box installation and inspection records
3. Project overview sheet 37. Concealed acceptance record of fire distribution lines
4. Project negotiation record 38. Detector installation inspection record
5. Commencement report 39. Roof water discharge test record
6. Contracting unit qualification application 40, equipment handover order
7. Construction organization design application 41, construction log
8. Equipment/materials/ Components and accessories come in for review 42. Safety information
9. Equipment/materials/component parts list details and summary of all inspection records
10. Concealed project acceptance records (stratified) < /p>
11. Inspection batch acceptance record for indoor pipe and trunking laying
12. Application for pre-embedded inspection of fire protection engineering (stratified)
13. Sprinkler Pressure test records
14. Fire protection pressure test records
15. Pipe system, strength and tightness test records (layered)
16. Pipe insulation, Anti-corrosion (stratification)
17. Pipe network flushing record files
18. Water pump installation record files
19. Water and heating equipment stand-alone test operation records< /p>
20. Inspection and trial operation records of sprinklers and fire pumps
21. Debugging and trial operation records of water and electricity systems
22. Unpacking of main equipment Inspection report and debugging and trial operation records
23. Electrical equipment grounding resistance, insulation resistance, integrated wiring test records
24. Wiring project review documents
25. Project change record document
26. Project completion summary document
27. Project completion final account document
28. Project self-inspection results document
29. System voltage stabilizing device installation and inspection records
30. Terminal water testing device installation and inspection records
31. Linkage debugging and inspection records
32. Valve sampling inspection and test records
33. Pipe support production and installation inspection records
34. Water pump adapter installation inspection records
Question 2: House fire protection acceptance includes What contents should be reviewed by the public security and fire department, usually the Construction Approval Office of the Municipal Fire Brigade or the District Fire Brigade according to different authority, and issue the "Construction Project Fire Acceptance Opinion". It is recommended that it be handled at the city fire brigade. Even if it is handled at the district fire brigade, it must be reported to the city fire brigade. It is one more procedure and is too troublesome.
Fire protection project acceptance procedures Before submitting the application form, the construction unit should organize the construction unit, design unit, and supervision unit to compare the "Fire Protection Acceptance Requirements for Construction Projects" with the design drawings and relevant information reviewed and approved by the public security fire protection agency. "Basic conditions must be met", conduct a comprehensive self-examination and self-inspection, and fill in the self-inspection opinions in the "Construction Project Fire Protection Acceptance Application Form".
□ Units applying for fire protection acceptance must carefully fill in the "Construction Project Fire Protection Acceptance Application Form" in duplicate (and stamp it with the official seal as required).
□ "Construction Project Fire Protection Design Review Opinion" issued by the public security fire protection agency (the original must be produced at the same time).
□Special article on fire prevention.
□ Completion drawing of the outdoor fire water supply pipe network, with a completion seal from the pipe network construction unit or a confirmation seal from the Water Supply Development Department of Tianjin Water Group Corporation regarding the fire water source (projects with fire pools should Submit the completion data of the fire pool and its water replenishment, with the official seals of Party A, the supervisor and the construction unit); the completion data of the fire power supply mainly include the power supply plan issued by the power supply department and the completion seal of the power construction unit.
□ "Building Fire Protection Facilities Quality Supervision Report" issued by a legally qualified supervision unit.
□ Projects equipped with automatic fire protection facility systems should submit a "Building Fire Protection Facilities Test Report" issued by a legally qualified testing unit.
□ Qualification certificates for main building fireproof materials, components and fire protection products (type approval certificate, certification certificate or test report, etc.).
□ Report materials from the main person in charge of the construction unit on the project overview, and the official seal of the unit shall be stamped on the report materials;
self-inspection status and unit signature of the "Declaration Form"
p>
This column must be stamped with the official seal of the relevant unit, and the person in charge must sign the opinion and confirm it with his signature.
□ For flammable and explosive factories, the site should provide static electricity and lightning protection test reports.
□ The unit applying for acceptance should bind the submitted drawings and materials (A4 size) into a volume.
The above procedures are in Tianjin and are basically the same in all regions.
In addition, if you feel that fire protection acceptance is difficult, you can also entrust the fire protection company under the fire department to handle it, which saves money and trouble.
Question 3: How many steps are required for fire protection acceptance? First of all, let me answer your question. The following functions are generally tested during the acceptance of the sprinkler system: 1. The starting function of the water pump includes manual starting of the water pump control cabinet and remote multi-line starting of the fire control host. The requirement is that the water pump can be started within 30 seconds. Normal operation can be achieved within 2. Linkage function, the process is as follows: discharge water at the end (usually the end of the most unfavorable layer or the end of the most unfavorable point), the water flow indicator alarms (the fire control host alarms), the wet alarm valve alarms (hydraulic alarm The bell rings), along with the pressure switch action and alarm (fire control host alarm), the pressure switch action starts the spray pump. The entire process needs to be completed within 5 minutes. The prerequisite for this process to proceed smoothly is that the voltage stabilizing system must be able to work properly. This process is the focus of the fire brigade’s acceptance and must be tried. I think this is also the focus of your question. 3. Installation conditions, including the installation of wet alarm valves, nozzles, etc., the settings of the water pump room, etc. You can ask me again for details. I don’t want to type anymore because there is too much content. Secondly, you must understand that fire protection acceptance is for fire protection facilities (including automatic fire alarm systems, automatic sprinkler systems, fire hydrant water supply systems, smoke prevention and exhaust systems, water spray fire extinguishing systems, foam fire extinguishing systems, gas fire extinguishing systems, fire doors, fire protection Rolling shutters, fire protection functions of elevators, fire emergency broadcasting or alarm devices, emergency lighting evacuation instructions, dedicated fire telephones, fire water supply and fire lanes), civil engineering (including fire sealing), electrical (implemented since May 2009, in some places This piece has been inspected during on-site acceptance) for overall acceptance. Let me tell you, I do fire inspection, so I know the fire acceptance process very well.
Is this okay?
Question 4: What does a fire protection acceptance include? Fire protection acceptance refers to the fire department’s qualified investigation of fire protection inspections when enterprises and institutions are completed and operated. When construction units conduct fire protection acceptance, they need the fire bureau to conduct safety inspections and inspections. At the same time, It is necessary to issue certification documents for electrical fire protection inspection. Electrical fire protection inspection has been included in the mandatory inspection items for fire protection acceptance by the Ministry of Public Security.
For construction projects that apply for fire protection acceptance, the fire protection agency of the public security organ shall organize fire protection acceptance for the content that has passed the fire protection design review in accordance with the fire protection acceptance assessment standards for construction projects. For a construction project whose comprehensive assessment conclusion is qualified, the fire protection department of the public security organ shall issue a fire protection acceptance qualification opinion; for a comprehensive assessment conclusion that is unqualified, it shall issue a fire protection acceptance failure opinion and explain the reasons.
Main content:
1. The general layout and the fire spacing, fire lanes, fire water sources, etc. related to fire safety in the layout;
2. Building Fire hazard category and fire resistance level;
3. Building fire and smoke prevention zoning and building structure;
4. Safety evacuation and fire elevator;
5 , fire water supply and automatic fire extinguishing system;
6. Smoke prevention, smoke exhaust and ventilation, air conditioning system;
7. Fire power supply and power distribution;
8. Fire emergency passages, emergency lighting, emergency broadcasts and evacuation signs;
9. Automatic fire alarm system and fire control room;
10. Building interior decoration;
p>
11. Configuration of building fire extinguishers;
12. Other contents related to fire safety in national engineering construction standards;
13. Inspection of valid documents and supply certificates for fire protection products .
Question 5: What materials should be prepared for fire protection acceptance (1) Construction project fire protection acceptance declaration form;
(2) Project completion acceptance report;
(3) ) Documents proving the quality of fire protection products;
(4) Documents proving that building components, building materials, and interior decoration materials with fire protection performance requirements meet national standards or industry standards, and factory certificates;
(5) Documents proving that tripod protection facilities and electrical fire protection technology have passed the test;
(6) Documents proving the legal identity and qualification level of construction, project supervision, and testing units;
(7) Other materials required to be provided by law.
Question 6: The fire protection site acceptance inspection is mainly divided into several parts. 1. In terms of civil engineering, the civil engineering mainly accepts fire doors and windows, roller shutters, evacuation channels, and fire separation distances. 2. Water fire protection part. 3. Electrical and automatic alarm, 4. Overall fire protection linkage, 5. Fire protection product information, etc.
Question 7: Which construction projects must undergo fire protection acceptance by the public security fire protection agency upon completion? Answer: When a construction project that requires fire protection design in accordance with the national engineering construction fire protection technical standards is completed, it must be inspected by the public security fire protection agency for fire protection acceptance. If it has not been inspected or failed to pass the acceptance inspection, it shall not be put into use. Fire inspection is mainly to inspect the fire protection design review content and conduct necessary system performance tests.
Question 8: What are the regulations related to fire protection? GB, including design, construction and acceptance. The building owner can refer to the "Design Instructions" of the construction drawings or "Refer to the National Standard Atlas". Common specifications related to fire protection systems in civil buildings are
I currently collect The relevant specifications obtained are roughly as follows, I hope they can help the original poster.
"Code for Construction and Acceptance of Automatic Sprinkler Systems" GB50261-2005
"Code for Design of Automatic Sprinkler Systems" GB50084-2001 Partially revised provisions (October 1, 2005 )
"Code for Construction and Acceptance of Gas Fire-Extinguishing Systems" GB50263-2007
"Code for Design of Gas Fire-Extinguishing Systems" GB50370-2005
"Construction and Acceptance of Automatic Fire Alarm Systems" Acceptance Specifications" GB50166-2007
"Design Specifications for Automatic Fire Alarm Systems" GB50116-98
"Construction Quality Acceptance Specifications for Building Water Supply, Drainage and Heating Projects" GB50242-2002
"Building Water Supply and Drainage Design Code for Valve GB50015-2003 (2009 Edition)"
"Code for Construction Quality Acceptance of Ventilation and Air Conditioning Projects" GB-50243
"Code for Design of Building Fire Extinguishers" GB50140-2005
Question 9: What are the houses that must undergo fire protection acceptance? For densely populated places with one of the following circumstances, the construction unit shall apply to the fire protection department of the public security organ for fire protection design review, and shall apply for fire protection design review after the construction project is completed. Then apply for fire protection acceptance to the fire protection agency of the public security organ that issued the fire protection design review opinion:
(1) Displays in sports venues, auditoriums, public exhibition halls, and museums with a total construction area of ??more than 20,000 square meters
(2) Civil airport terminals, passenger station waiting rooms, and passenger terminal waiting rooms with a total construction area of ??more than 15,000 square meters;
(3) Hotels, restaurants, shopping malls, and markets with a total construction area of ??more than 10,000 square meters;
(4) Theaters with a total construction area of ??more than 2,500 square meters, and reading rooms of public libraries, Commercial indoor fitness and leisure venues, hospital outpatient buildings, university teaching buildings, libraries, canteens, production and processing workshops of labor-intensive enterprises, temples and churches;
(5) The total building area is greater than One thousand square meters of children's rooms in nurseries and kindergartens, children's play halls and other indoor children's activity places, nursing homes, welfare homes, ward buildings in hospitals and nursing homes, teaching buildings, libraries, canteens in primary and secondary schools, and school dormitories, Employee dormitories of labor-intensive enterprises;
(6) Song and dance halls, video halls, projection halls, karaoke halls, nightclubs, Danyi halls, saunas, etc. with a total construction area of ??more than 500 square meters. Internet cafes, bars, restaurants, teahouses, and coffee shops with entertainment functions.
For special construction projects with one of the following circumstances, the construction unit shall apply to the fire protection agency of the public security agency for fire protection design review, and after the completion of the construction project, apply to the fire protection agency of the public security agency that issued the fire protection design review opinion. Acceptance:
(1) Construction projects with densely populated places listed in Article 13 of these regulations;
(2) State agency office buildings, power dispatching buildings, telecommunications buildings building, postal building, disaster prevention command and dispatch building, radio and television building, archives building;
(3) The single building area other than those specified in paragraphs 1 and 2 of this article is greater than 40,000 square meters or the building Other public buildings with a height exceeding fifty meters;
(4) Urban rail transit, tunnel projects, large-scale power generation, power transformation and distribution projects;
(5) Production, Factories, warehouses, special stations and docks for storing, loading and unloading flammable and explosive dangerous goods, filling stations, supply stations and pressure regulating stations for flammable and explosive gases and liquids.
Question 10: What versions of fire protection acceptance specifications are there, the complete GB50016-2014 "Code for Fire Protection Design of Buildings"
GB50898-2013 "Technical Specification for Water Mist Fire Extinguishing System"
p>
GB50084-2005 "Code for Design of Automatic Sprinkler Systems"
GB50116-2013 "Code for Design of Automatic Fire Alarm"
GB25506-2010 "General Technology for Fire Control Rooms" Requirements"
GB50140-2005 "Design Code for Building Fire Extinguisher Configuration"
GB50338-2003 "Design Code for Fixed Fire Cannon Fire Extinguishing System"
GB25204-2010 "Automatic Tracking and positioning jet fire extinguishing system"
GB50222-2015 "Code for fire protection design of interior decoration of buildings"
GB50370-2005 "Code for design of gas fire extinguishing system"
GB12955- 2008 "Fire Door Specification"
GB14287.4-2014 "Electrical Fire Monitoring System"
GB16280-2014 "Linear Temperature Fire Detector"
GB50067-2014 "Code for Fire Protection Design of Garages, Garages, and Parking Lots"
GB50098-2009 "Code for Fire Protection Design of Civil Air Defense Projects"
GB50303-2011 "Construction of Building Electrical Engineering Quality Acceptance Specifications"
GB50242-2002 "Construction Quality Acceptance Specifications for Building Water Supply, Drainage and Heating Engineering"
GB50261-2005 "Construction and Acceptance Specifications for Automatic Sprinkler Fire Extinguishing Systems"
GB50166-2007 "Code for Construction and Acceptance of Automatic Fire Alarm Systems"
GB50339-2013 "Code for Quality Acceptance of Intelligent Building Projects"
GB50281-2006 "Construction and Acceptance of Foam Fire Extinguishing Systems" and Acceptance Specifications"
GB50354-2005 "Code for Fire Protection Construction and Acceptance of Internal Building Decoration"
GB50263-2007 "Code for Construction and Acceptance of Gas Fire Extinguishing Systems"
GB50169-2006 "Code for Construction and Acceptance of Grounding Devices in Electrical Installation Engineering"
GB17945-2010 "Fire Emergency Lighting and Evacuation Instruction System"
GB50877-2014 "Fire-proof Roller Shutter Fire Door Specifications for the construction and collection of fireproof windows"
CECS154-2003 "Technical Regulations for the Application of Fireproof Sealing in Buildings"
GA98-2005 "Fireproof Coatings for Concrete Structures"
GB50235 -2010 "Code for Construction and Acceptance of Industrial Metal Pipe Engineering"
GB50184-2011 "Code for Construction Quality Acceptance of Industrial Metal Pipe Project"
GB50236-2011 "Construction of Industrial Pipe Welding Project of Field Equipment and acceptance specifications"
GB50300-2013 "Unified Standard for Construction Quality Acceptance of Construction Projects"