ID number: Tel:
Party B: Name (or name): Address:
ID number: Tel:
Through negotiation between both parties, Party A contracts the construction project of self-occupied house to Party B, and both parties reach the following agreement on the construction contract of the construction project:
1. The contracting method for the building construction of this house is Party B's contracting for labor and materials. Party B shall be responsible for the construction and solve all the equipment needed for the construction and all the raw materials used for the construction by itself. The water and electricity expenses required in the construction process shall be paid by Party B, and the accommodation of the construction personnel shall be borne by Party B. During the construction process, Party B shall pay attention to the construction safety and take full responsibility for the construction safety. Party B shall bear all the responsibilities for the casualties caused by the operation errors of construction equipment and Party B's personnel. If personal and property damage is caused to a third party other than the construction personnel due to Party B's negligence in the management of the construction site, Party B shall take full responsibility. The construction drawings shall be signed by both parties and shall not be changed casually. If changes are needed, they should be agreed by both parties through consultation.
2. The building area of the house to be built is square meters, and Party A will contract all the house construction projects including ground beams to Party B (including interior and exterior wall tiles, indoor floor tiles, stairs and their ancillary facilities, bathroom floor tiles, kitchen console, carpentry, water and electricity pipeline installation, etc.). ). The unit price of Party B's construction contract is RMB per square meter, and the total project price is RMB.
Third, the construction requirements
① Geotechnical foundation: 70 cm deep, 60 cm wide and 40 cm wide inside.
(2) Wall, external wall, internal wall, internal wall, and internal and external staggered joints of masonry are generally made of cement mortar, and the strength should reach (150). There are constructional columns at the four corners and internal sample changing places generally need 80 gongs with two 6mm mortar with tie rods, and the fullness must reach the trinity masonry method (one quick brick, one shovel and one squeeze) and the bricks must be soaked before use.
③ Ring beam: the height of ring beam is not less than 12 cm, the diameter of reinforcement is not less than 10 mm, the diameter of rigid hoop is not less than 6 mm, the maximum spacing is not more than 250 mm, and the height of ring beam is not less than 200 mm. ..
(4) The roof should be hemmed first, and the reinforcement should not be 12mm, and the spacing should be 16cm. 150 level roof, the height of mixed mortar before ash is 25cm, and the height of post ash is 15cm. 5cm and 2cm mortar plastering with mixed mortar on the ash 1/3.
⑤ The price of black and white floor tile is 6060 10 yuan, which shall be selected by Party A.. If it is made by 10 yuan, Party A will pay for it, and Party A will choose the black and white bathroom wall tiles, which shall not be less than 1.8 yuan. The interior of the wall is painted with room pool paint, with 4 square meters of copper core wire in each room, a hot lamp socket and a switch.
6 doors and windows: interior doors, solid wood doors and windows. Party B shall ensure the quality of plastic steel conch brand external doors and security doors during construction. During the construction, Party A and Party B negotiated.
⑦ Party B is responsible for indoor tap water and sewer pipes. Duration: Year Month Day (Gregorian calendar/lunar calendar)? Year, month and day (solar calendar/lunar calendar), calculated by calendar duration. Party B shall carry out the construction on time. If the construction period is delayed due to Party B's reasons, the salary will be deducted by RMB per square meter for each day of delay. Except for delays caused by irresistible objective reasons such as heavy rain.
⑦ Party B shall ensure the construction quality according to Party A's housing quality requirements. After the house is completed and delivered, Party A shall conduct acceptance inspection according to the construction requirements. In case of building quality problems in the house, Party B shall repair it again until it meets the quality requirements of Party A, and compensate all losses caused to Party A due to the building quality problems. All maintenance costs (including materials used for maintenance) shall be borne by Party B. ..
Four. mode of payment
One-time payment starts 40%, masonry 40%, painting 40% and completion 70%. Also reputation% one-year maintenance clearance.
5. This agreement shall come into effect as of the date when both parties sign (seal) the text of this agreement. This agreement is made in triplicate. Party A and Party B each hold one copy, and the witness holds one copy.
By mutual agreement, the details are as follows:
Signature of Party A: Signature of Party B:
Signature of witness (signature):
Signing time: year, month and day (Gregorian calendar/lunar calendar)
Signing place:
Model Letter of Commitment for Villagers Building Part II Party A: (Owner) Name, gender, birth and current address.
Party B: (Neighbor) Name, Gender, Birth and Current Address.
(The order of east, west, north, south and neighbors is the same as above).
In order to correctly handle the adjacent relationship, according to the provisions of Article 83 of the General Principles of the Civil Law, the following agreement is hereby signed:
1. Four boundaries, length, width and area of the building. 2. Ventilation, lighting and drainage methods. 3. The construction method of neighbors will not be affected during the construction period. 4. Transportation of materials. 5. The path of weddings, funerals and happy events. 6. Other matters
Signature fingerprint of the client
Date of signing
Model Letter of Commitment for Building by Villagers Part III Party A: Name:
Party B: Name:
Party A will contract the construction project located in Group 1, Liuduhu Village, Hanjia Town, Pengshui County (small place name: Fengshenbao) to Party B, and both parties reach the following agreement on the construction contract of this construction project through consultation:
1. The contracting method of housing construction is Party B's contracting and Party A's contracting. Party B shall be responsible for the construction and solve all the equipment required for the construction by itself; Party A shall be responsible for all the raw materials used for the construction; the water and electricity expenses required for the construction shall be paid by Party A; and Party B shall be responsible for the accommodation and living of the construction personnel. During the construction process, Party B shall pay attention to the construction safety and be responsible for the whole process of construction safety. All the mistakes caused by the operation of construction equipment and Party B's personnel shall be borne by Party B, which has nothing to do with Party A. If Party B's negligence in the management of the construction site causes personal and property losses to a third party other than the construction personnel, Party B shall bear all the responsibilities.
2. Party A will contract out all housing construction projects including ground beams to Party B, and the unit price of the main building contracted by Party B is 65,438+050 yuan per square meter (in words: one hundred and fifty yuan).
Three. Payment terms:
Pay RMB 2,000 Yuan only (in words: RMB 2,000 Yuan only).
Payment will be made after the first floor is completed (in words: RMB). Payment will be made after the second floor is completed (in words: RMB).
Pay off the balance after completion (the remaining 5,000 yuan will be used as the quality guarantee, and the remaining 5,000 yuan will be paid after one month without quality problems).
Four. Special requirements and instructions:
1. The depth and width of foundation excavation shall be determined on site according to Party A's requirements and geological conditions. Foundation construction includes foundation trench excavation, earthwork backfilling and compaction.
2. The floor should be cast-in-place by layers (including stairs, doors and windows, lintels).
3. All interior walls shall be plastered, and the facade of exterior wall shall be plastered with ceramic tiles.
Five, the engineering quality level:
To meet the acceptance criteria stipulated in the construction code, the internal angle of the roof shall not exceed cm, the internal angle of the wall shall not exceed cm, the four corners of the brick body shall not exceed cm, and the wall surface of the stone wall shall not exceed cm. If individual parts do not meet the quality requirements during construction, they should be reworked. All the materials and labor losses caused by this shall be compensated by Party B. If the rectification still fails to meet the quality requirements, Party A has the right to unilaterally terminate the contract, sign another contract, and clear the site according to 50% of the labor cost of the completed project. ..
This agreement shall come into effect as of the date when Party A and Party B sign (seal) the text of the agreement, and shall have legal effect. This agreement is made in duplicate. Party A and Party B each hold one copy.
Seven. Signature of Party A: Signature of Party B:
Signature of witness (signature):
Signing time: year month day
Model Letter of Commitment for Building by Villagers Part IV Party A: Name, Gender, Age, National Phone Number
Address:
Party B: Name, gender, age and national telephone number.
Address:
Party A needs to build a new house because the child is about to get married, and it needs to occupy a little business road of Party B because of the sunshine degree of Party A's original homestead. Through negotiation, Party A and Party B have reached the following construction agreement.
1. Party B agrees that Party A's building will occupy Party B's official roads: Beimi, Nanmi and Simi (see the attached schematic diagram for details).
2. Party A agrees to compensate Party B for the inconvenience caused by occupying public roads.
3. Party A and Party B agree that part of the ownership of Party A's building occupied by Party B's road will always belong to Party B, and the right to use it will always belong to Party A. ..
4. Party A and Party B agree that Party A's building occupies part of Party B's business road, and after Party A demolishes it by itself, the ownership belongs to Party B, but Party B shall not ask Party A to demolish the building.
5. Both parties agree that Party A's building occupies part of Party B's business road. In case of government expropriation or planning and other related matters, the house compensation fee shall be owned by Party A and the land compensation fee shall be owned by Party B. ..
6. This agreement is printed in duplicate by computer, and each party holds one copy, which has the same effect.
7. If there are any deficiencies in this agreement, both parties can supplement it separately.
Party A: (signature and seal)
Party B: (signature and seal)
Person: (signature and seal) xx.
-
Party A: _ _ _ _ _ _ _ _ _ (name, ID number)
Party B: _ _ _ _ _ _ _ _ _ (name, ID number)
Party A plans to build a house in _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
I. Rights and obligations of both parties
1. Party A is responsible for providing building materials such as lime, bricks, cement, sand, water and steel. According to the construction progress, Party B shall notify Party A to purchase the required materials _ _ days in advance.
2. Party B has mature experience in rural housing construction and is responsible for the construction and delivery of housing achievements. Both parties made it clear that there was no employment relationship between them.
3. All construction machinery, such as mixers and vibrators, and all labor tools, such as templates and scaffolding, shall be brought by Party B, and the expenses shall be borne by Party B. ..
4. The construction period starts from _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ In case of force majeure such as rain, power failure and earthquake, the construction period can be postponed.
5. Party B shall strengthen the safety education for its personnel, strictly manage, abide by national laws and regulations, and carry out safe construction. Safety accidents caused by intentional or negligent behavior of Party B's personnel shall be borne by Party B itself, and have nothing to do with Party A.. ..
6. The wages and remuneration of Party B's employees shall be paid by Party B, which has nothing to do with Party A. ..
Second, the quality requirements
1. Party B shall carry out construction according to the principle of quality and quantity of drawings, and strengthen quality management.
3. Important construction procedures: The foundation and pouring must be accepted by Party A before the next procedure can be carried out.
3. Party A has the right to ask Party B to stop work or make rectification when it finds that Party B has cut corners during the construction and is irresponsible for the work that affects the quality of the house.
2. If Party A finds quality problems within one year after the house is completed, Party B must carry out free maintenance.
Three. terms of payment
1. Payment method: calculated according to the construction area, RMB per square meter.
1. Payment time: the first payment shall be made within _ _ days after the commencement of construction, the second payment within _ _ years, the third payment within _ _ years, and the fourth payment within _ _ days after the house is completed and accepted by Party A. ..
Fourth, the liability for breach of contract
1. If the project quality does not meet the requirements, Party B shall repair and redo it; If losses are caused, Party B shall make compensation. If the Contract cannot be performed due to Party B's reasons, Party B shall bear the liquidated damages of RMB Yuan and compensate all losses caused to Party A due to its breach of contract.
2. If Party B ignores Party A's reasonable requirements, or embarrasses Party A by taking measures such as slacking off and delaying the construction period, it will be regarded as Party B's fundamental breach of contract, and Party A has the right to terminate this contract. Party B shall bear the penalty of RMB yuan.