Current location - Quotes Website - Personality signature - Annual filing flow chart
Annual filing flow chart
How to handle the charging pile filing certificate?

(1) Application Process of Household Charging Piles for New Energy Vehicles

Declaration conditions

(a) whether the construction filing procedures are complete;

(two) according to the procedures to complete the project completion and acceptance;

(three) completed and put into operation before the specified date of the year and did not receive construction subsidies;

(4) Unconditionally access the monitoring platform of electric vehicles and charging facilities in Chongqing (hereinafter referred to as the "city monitoring platform") and exchange data;

(five) the real-time online rate of charging infrastructure is not less than 90%;

(six) full-time technical personnel to ensure the safe and stable operation of the equipment and a sound operation management system;

(7) No major safety accident has occurred;

(eight) in line with the National Energy Administration issued the "electric vehicle charging facilities standard system project table (20 15 version)" of the relevant standards;

(9) The construction shall comply with the relevant laws, regulations and standards, and the Administrative Measures for the Construction and Operation of Electric Vehicle Charging Infrastructure in Chongqing (Chongqing [2017]1264).

Application material

(a) a copy of the business license of the charging operation enterprise and the filing documents of the charging infrastructure construction;

(two) a copy of the charging infrastructure equipment procurement contract and VAT invoice;

(3) Application Form for Chongqing Charging Infrastructure Construction Grant Fund;

(4) enterprise commitment letter;

(5) Information such as the account opening bank and bank account number of the charging operation enterprise;

(6) To apply for subsidies for the construction of special DC charging infrastructure that mainly serves buses, taxis, network cars, time-sharing cars, logistics cars and sanitation cars, the charging operation enterprise shall also provide relevant materials such as certification documents of contracted sites;

(7) Other relevant materials and explanations.

The above materials must be stamped with the fresh seal of the charging operation enterprise. The charging operation enterprise shall also prepare the project completion acceptance report of the charging infrastructure put into use, proof materials such as electricity payment vouchers, operation management system, operation and maintenance records, proof of operation capability and other related materials for on-site inspection.

Refer to the above contents: Dianjiang People's Government-Matters related to subsidies for electric vehicle charging infrastructure construction (charging piles)

⑵ How to apply for enterprise standard filing for electric vehicle charging piles?

According to the regulations, you can file a declaration online or in the lobby.

(3) Which department does the national new energy facility charging pile construction need to apply for approval?

First of all, we should give the consent form to the installation site, usually the consent form signed by the property. If you want to declare electricity consumption, you need to submit an application to the electric power, and some areas need the consent of the fire department for installation.

(4) How to report the installation of electric vehicle charging piles in the community to the power supply bureau?

According to the introduction of charging piles for household electric vehicles published by the Power Supply Bureau, consult the business of application materials for self-use charging facilities.

5] Sample of application report for access catalogue of professional charging facility operators

It is illegal to operate the communication business for the second time. Please be careful.

[6] Where can I apply for a charging pile?

If you are a customer within the service scope of Guangdong Power Grid Corporation, the information required for installation business is as follows:

1, identification of the head of household;

2, electricity address property certificate;

3. If an agent is entrusted, the identity certificate and power of attorney of the agent shall be provided;

4. The bank shall submit relevant payment materials for electricity deduction.

5. For projects that occupy public places in residential areas, such as residential parking lots, it is also necessary to provide a consent for the construction of charging infrastructure issued by the owners' committee or the property.

6. If only the parking space is rented, provide the parking space owner's consent materials, the owner's identification materials, the electricity bill guarantee and the customer's statement.

Customer statements include:

(1) declare that I legally rent the house;

(2) Declare that the electricity charges generated by the house shall be borne by the lessee himself;

(3) A statement that if the power supply enterprise can't contact the lessee, it agrees that the owner of the house or the original house leasing enterprise will go through the relevant cancellation or renaming transfer procedures at the power supply enterprise.

Note: If the civil air defense parking space is installed, the property owner will issue the property right certificate or the customer will provide the use certificate of the civil air defense parking space.

The required materials shall be provided with the original and 1 copy, which shall be verified by the customer to be consistent with the original and signed, and the customers of enterprises and institutions shall sign the copy and affix their official seals. When handling business, resident customers need to sign the Power Consumption Business Sheet for confirmation, and customers of enterprises and institutions must affix their official seals to the Power Consumption Business Sheet.

There are data differences in different cities. Please consult the staff for details.

Treatment method:

Wechat follows the public platform "China Southern Power Grid 95598" > My Power Consumption > Business Handling > Power Application > After selecting the new installation business type to be handled, fill in the basic information and upload relevant materials according to the prompts > check "I have read and agreed to endorse the contract, and confirm that the submitted materials are true and valid" and submit them.

After completing the installation application, the power supply department will arrange the staff to make an appointment with you for on-site service. After completing the on-site investigation and collecting the information, you can install the electricity meter and send electricity for you.

I hope ours can help you.

1. What are the requirements for applying for the qualification of charging pile operation?

Apply for charging pile operation qualification:

1. It has the ability to sign an operation and management agreement for cooperative station building with large real estate enterprises, commercial chain organizations, roadside parking management units designated by the Traffic Management Bureau and other management units with parking spaces (the investor is responsible for charging stations and management, and the organization is responsible for providing venues and ensuring safety, and the fees and value-added benefits are shared by both parties).

2. Have the ability to establish joint ventures with local branches of large powerful enterprises (PetroChina, Sinopec, funds, etc.). ).

3. Obtain the qualification of joint venture with local departments of State Grid.

4. Contact relevant government departments (Science and Technology Commission, Association for Science and Technology, Urban Construction, Urban Management, Electric Vehicle Leading Group, Economic Commission, Development and Reform Commission, etc.). ) and carry out joint ventures or apply for funding (disguised policy support).

5. The construction, operation, service, maintenance and management of charging facilities meet the relevant technical standards, design specifications, construction standards and management requirements of the state and this Municipality.

6. Charging facilities enterprises connect social public charging facilities to the data information service platform of municipal public charging facilities.

(7) Extended reading for filing application for charging facilities construction.

Construction conditions and standards for charging piles:

1. Enterprises building public charging facilities in parking lots of residential quarters shall obtain the consent of more than two thirds of the owners or owners' congress.

2. Individuals install special charging facilities in their own parking garages and parking spaces, and all communities and units install special charging facilities in existing parking spaces. There is no construction agreement, only according to relevant requirements.

3. There shall be no less than 5 charging piles for public charging facilities with independent land occupation, the distance between piles shall not be greater than10m, and the total power shall not be less than 100 kW.

4. The charging equipment of charging facilities shall meet the national standards or industry standards such as interface, security and communication protocols. Due to innovation, technological progress and other factors, there is no corresponding national standard or industry standard, or the provisions are unclear, which can be temporarily implemented according to enterprise standards.

How to apply for the construction of a car charging station?

The following steps need to be followed:

Step 1: Confirm the charging conditions.

Before building a car charging station, it is necessary to confirm whether there are charging conditions, mainly to see whether there are fixed parking spaces, and the property must agree to the application for installing charging piles.

(8) Extended reading for filing application for charging facilities construction:

Automobile charging station is similar to automobile gas station, and it is a kind of "electrified" equipment. It is an efficient charger, which can quickly charge mobile phones, electric cars and electric cars.

The development of electric vehicle charging stations in China is inevitable, and seizing the initiative is also the way for enterprises to win. Under the current circumstances, although the country strongly advocates and enterprises are eager to move, it is not easy for electric vehicles to enter the homes of ordinary people in a short period of time.

National policies can give (car purchase compensation, on the road, etc.). ), but the network of electric vehicle charging stations can not be built in a short time. The main reason is that the rapid charging of electric vehicles requires instant and powerful electricity, which can not be satisfied by the conventional power grid. It is necessary to build a special charging network, which involves the transformation of the entire national power grid. The transformation of the state grid is not a trivial matter, and it costs a lot. From discussion, project establishment to networking, it can't be achieved overnight.

At present, a better way to solve the problem of fast charging is to change the power station and replace the long charging process by changing the battery for the car.

A car needs two batteries. When one battery runs out, it will automatically switch to another battery. At this time, you can go to the power station to replace the used battery and install a fully charged battery. If the charging station has a considerable number of spare batteries, the replaced batteries will be uniformly charged and maintained by the power station.

The advantage of this method is that it is fast, and users can go on the road after replacing the battery, which is faster than refueling. With this method, coupled with auxiliary means such as charging piles in parking lots, I believe the popularity of electric vehicles is just around the corner.

What are the procedures for building a new charging pile station?

Procedures: copy of ID card, proof of parking space ownership (which can be issued by the property), and instructions that the property agrees to install to the staff. In addition, we should pay attention to the following aspects:

About the property: contact the property company to determine the charging pile installation policy in the community. At present, for the installation of charging piles, the general rule is to require parking spaces with their own property rights. In addition, some properties are not suitable for installing charging piles because they were built earlier. If the installation of charging piles requires additional technical equipment investment, it is necessary to communicate with the property in advance.

About parking spaces: Check your parking spaces. There will be many power distribution rooms in the community, so the owner should choose the one closest to the parking space, which can save a lot of money when installing. In addition, some communities have installed charging piles and can learn from their neighbors. There are some precautions that you won't understand unless you are "experienced". In short, it is necessary to determine the shortest route for the installation of charging piles.

On-the-spot investigation: On-the-spot investigation, the engineers of the power company will inform the charging pile company of a time, when the property electrician, the charging pile company, the power company and the owner will all go to the site to determine the final construction plan.

About installation: after the construction scheme is determined, it is time for installation and construction. According to the situation of each community, the location of the garage is different and the construction time is different. Some will only take 2 hours to complete, while others may take a whole day to complete the construction. 、

About acceptance: after the construction is completed, the charging pile company will go to the power company for filing, and the power company will go to the site for acceptance. If it is qualified, it will stamp the meter, and then the power company will make the corresponding electric card, which will be collected by the charging pile company and handed over to the owner, or the owner will go to the power supply equipment to collect it himself.

(9) Extended reading for filing application for charging facilities construction:

As the electric vehicle charging pile (plug) on the distribution side of the power grid, the particularity of its structure determines that the automatic communication system has the characteristics of many and scattered measuring points, wide coverage and short communication distance. And with the development of the city, the network topology needs flexible and extensible structure. Therefore, the following issues should be considered in the selection of the communication mode of electric vehicle charging piles (plugs):

(1) Reliability of communication-The communication system should stand the test of long-term harsh environment and strong electromagnetic interference or noise interference, and keep the communication smooth.

(2) Construction cost-On the premise of satisfying reliability, the construction cost and long-term use and maintenance cost are comprehensively considered.

(3) Two-way communication-not only can upload information, but also can release control quantity.

(4) Multi-service data transmission rate-With the continuous growth of terminal traffic in the future, the communication between the main station and the sub-station and the terminal requires higher and higher data transmission rate of multi-service.

(5) Flexibility and expansibility of communication-Because charging piles (plugs) have the characteristics of many control points, wide area and dispersion, standard communication protocols are needed. With the development of "ALLIP" network technology trend and the continuous growth of power operation business, IP-based business load should be considered, and it is required to be convenient for installation, debugging, operation and maintenance.

References:

Network: charging pile

⑽ How to apply for public charging piles and what procedures are needed?

How to apply for public charging piles requires customer identification materials; Customer identification materials; Proof of the property right of the electricity address; For projects that occupy public places in residential areas, such as parking lots, it is also necessary to provide a consent letter issued by the owners' Committee or the property to agree to build charging infrastructure. If the user only rents the parking space, he shall also provide the consent materials of the parking space owner.

The charging pile has the following functions:

A tanker similar to a gas station can be fixed on the ground or wall and installed in public buildings (public buildings, shopping malls, public parking lots, etc.). ) and residential parking lots or charging stations, and can charge all kinds of electric vehicles according to different voltage levels. The input end of the charging pile is directly connected to the AC power grid, and the output end is equipped with a charging plug to charge the electric vehicle.

Charging piles generally provide two charging methods: conventional charging and fast charging. People can use a specific charging card to swipe their cards on the man-machine interface provided by the charging pile and print the corresponding charging method, charging time and cost data. The charging pile display screen can display data such as charging amount, cost and charging time.

How to file the medical insurance card?

1. For the reimbursement process of urban medical insurance, first go to the public hospital designated by medical insurance → register at the medical insurance office of the hospital within three working days of hospitalization → open the hospitalization application form, hospitalization invoice, detailed list and medical records at the medical insurance office when leaving the hospital.

2. If it is trauma, you should also fill in the trauma form in the hospital medical insurance office and affix the official seal of the hospital where you live and the official seal of the insured unit, and write down everyone's information. The explanation or proof of the insured unit shall be submitted to the office on the second floor of the Social Labor and Social Security Bureau for reimbursement. The original of the above materials is required when the medical insurance for urban residents is reimbursed. If you need commercial insurance reimbursement, please copy all the above materials and affix the seal of the commercial insurance hospital.

3. If there is a new rural cooperative medical system, it cannot be reported at the same time as the urban residents' medical insurance, and both can only be reported in one place. Commercial insurance, first reported to the urban residents' medical insurance, and then reported to the commercial insurance; Those who apply for commercial insurance first will not be reimbursed for medical insurance for urban residents.

Second, the specific process of medical insurance reimbursement for different reasons is as follows

1. Sick hospitalization: Within three days of hospitalization, go to the hospital medical insurance office for medical insurance networking procedures with valid documents such as medical insurance card or ID card and household registration book, and go directly to the hospital medical insurance office for settlement procedures when leaving the hospital.

2. Hospitalization for work-related injuries: Within three days of hospitalization, with valid certificates such as medical insurance card, ID card and household registration book, go to the hospital medical insurance office for medical insurance networking procedures. After investigation by the inspection department of the municipal (district) medical insurance office, those who meet the conditions of medical insurance reimbursement will go through the settlement formalities directly at the hospital medical insurance office when they leave the hospital; If the investigation is unclear or disagrees, after discharge, bring all documents such as medical records, invoices, statements, and copies of my CCB passbook to the Municipal Medical Insurance Office for investigation, and then submit them to the urban residents' medical insurance management department for reimbursement.

3. Outpatient accidental injury: After the treatment, bring all documents such as outpatient medical records, invoices and copies of my CCB passbook to the municipal medical insurance office for investigation, and then submit them to the urban residents' medical insurance management department for reimbursement.

Three:

Medical insurance refers to social medical insurance. Social medical insurance is a social insurance system established by the state and society according to certain laws and regulations to provide basic medical needs for workers within the scope of protection. The basic medical insurance fund consists of overall funds and individual accounts. The basic medical insurance premiums paid by individual employees are all included in individual accounts; The basic medical insurance premium paid by the employer is divided into two parts, one part is included in the personal account, and the other part is used to establish the overall fund.

20 16 65438+ 10/2 the State Council issued "opinions on integrating the basic medical insurance system for urban and rural residents" to promote the integration of medical insurance for urban residents and the new rural cooperative medical system, and gradually establish a unified national medical insurance system for urban and rural residents.

On February 20th, 2065438+0616, Ministry of Human Resources and Social Security held a video conference on the nationwide networking of basic medical insurance and direct settlement of medical treatment in different places, and signed letters of responsibility with the first batch of 22 provinces including Beijing, which applied for nationwide networking of basic medical insurance and direct settlement of medical treatment in different places, marking the formal implementation stage of direct settlement of medical treatment in different places.

Is the information publicity of enterprise annual report filing time or articles of association?

The information disclosure and filing time of an enterprise's annual report is not a filing charter. The information disclosure of the annual report of the enterprise is in a time year, and the enterprise information is publicized once a year after filing. In other words, the annual report information of an enterprise refers to the annual business activities of the enterprise, which is publicized in the national enterprise credit information publicity system, instead of enterprise registration and no articles of association for the record. Therefore, the information disclosure and filing time of enterprise annual report is not the filing charter.

How to register a company contact?

The enterprise liaison officer registers in the national enterprise information publicity system, opens the website, then clicks the enterprise information declaration, and then clicks the enterprise liaison officer registration.

To change the industrial and commercial liaison and mobile phone number, you need to re-register the liaison in the industrial and commercial registration window, directly covering the previous filing information, and then change it to the new liaison information.

The filing liaison shall submit the following materials:

1, record form of corporate information publicity liaison;

2. Power of attorney of the entrusted agent;

3. A copy of the business license (except for the newly established registration).

The specific process is as follows:

1. The enterprise logs into the local enterprise credit information publicity system, fills in the Record Form for Online Liaison of Enterprise Information Publicity in the "Enterprise Annual Report System" window, and submits the printed record form to the legal representative (person in charge) of the enterprise for signature and official seal.

2, the enterprise to the registration authority to submit the "enterprise information publicity contact record form", after the registration authority and the system input content check, on the spot to be put on record, and in the enterprise annual report system to confirm the completion of the record.

3. The enterprise liaison officer receives the password through the recorded mobile phone number and logs in the information publicity system to submit it to the industrial and commercial authorities.

What needs to be done next after the project is put on record?

The next step is planning and handling planning conditions, land pre-examination, and then conducting survey and design bidding, handling land planning permits, signing transfer contracts, and issuing land certificates! Make project planning permit, annual plan and work permit!