Project handover acceptance generally refers to the preliminary acceptance evaluation that the construction unit organizes the construction unit and supervision unit to check the implementation of the construction contract after the project is completed, and evaluate whether the project quality meets the technical standards and design requirements, whether it can be handed over to the next stage of construction or whether it meets the completion acceptance conditions.
The certificate of completion acceptance refers to the certificate signed by all members of the project acceptance committee or team after listening to the report, inspecting the site and reviewing the completion data. , and confirm that the whole project conforms to the approved construction content, project quality requirements, production capacity and economic benefits.
The contents of the completion acceptance certificate include:
(1) project overview (project name, project location, project approval unit, construction unit, main design unit, main construction unit, construction scale, project content, total investment, quantity of equipment and materials, construction progress, etc.). );
(two) the evaluation and opinions of the acceptance committee on the construction project;
(3) Opinions on handling matters not covered in the project;
(4) Signature of all members.
The certificate of completion acceptance shall be stored in the engineering technical file with all the completion acceptance data and reported to the competent department for the record.