The supervision diary is a very important supervision information, and the project supervision team must record it seriously, in detail, truthfully and in a timely manner. Before recording, the construction status and supervision work status of the day should be summarized and organized to ensure that the writing is clear, the layout is neat, organized, and the content is comprehensive. So, how to write the supervision work log? Let’s take a look below!
1. Construction activities
1. Construction parts and content: work on key lines, work on important parts or nodes, and other work that the project supervision team deems necessary to record.
2. Dynamics of workers, materials and machines
Workers: the number of workers of the main types of work on site (for example: steel workers, carpenters, masonry workers, scaffold workers, etc.), mainly managed by the project department The availability of personnel (project managers, construction workers, quality personnel, safety personnel, etc.).
Materials: The entry and exit of the main materials (including components) on the day.
Machinery: refers to the number of main mechanical equipment on the construction site and its operation status (whether there is a fault, the time to troubleshoot the fault, etc.), and the entry and exit of the main mechanical equipment.
2. Supervision activities
1. Inspection: time or number of inspections, and important situations during the inspection are selectively recorded according to the actual situation;
2. Acceptance : The part, content, results and acceptance person of the acceptance;
3. Witness: the content, time and witness of the witness;
4. Side station: content, part, side station Number of person and side station record;
5. Parallel inspection: location, content, inspector and parallel inspection record number;
6. Engineering measurement: Complete the measurement of engineering quantities , Measurement of changed contact content (required);
7. Review and approval status: Review and approval status of relevant plans, inspection batches (sub-items, processes, etc.), raw materials, schedule plans, etc. (Just record the number of the relevant review and approval form)
3. Existing problems and solutions
Throughout the day, through a series of supervision work, the quality and progress of the project were improved. What problems were found in investment, investment, etc., and how the supervision team dealt with these problems.,:: Detailed records should be kept of the results of the handling. Some major quality and safety accidents should be handled according to prescribed procedures, and relevant information should be recorded, saved, and organized in accordance with regulations. The records in the diary should be concise and comprehensive.
4. Others
1. Supervision instructions (supervision notices, memorandums, rectification notices, change notices, etc.);
2. Meetings and meeting minutes ;
3. Correspondence status;
4. Safety work status;
5. Reasonable suggestions;
6. Construction The inspection status of the leading departments of all parties or the construction administrative department;
5. Duty record
The signature of the supervisor on duty that day.