Sample of construction unit start application report
The start of work report must be signed and stamped by the construction, supervision and construction unit to be valid. The following is a sample application report for the start of construction unit brought to you by the application website for your reference.
Part 1: Sample of construction unit application report for commencement of work
XXX Logistics Park Development Headquarters:
Our company was on Yiping Road on December 8, 20XXX The Hongwei Village section has obtained the right to use the land for construction. Due to the issue of land certificate for the land, the work has not been able to proceed normally. Now the construction project site is basically available. In order to speed up the construction of the project, we have specially reported to the headquarters. Submit an application and request that the construction (foundation treatment) of the 2#~5# shopping mall project of Jindong Logistics Park (Phase I) be started first, and then go through the relevant construction application procedures. Please support the park headquarters.
Another note: The demolition work of the ceramsite sand factory has been going on for nearly three years, which has seriously hindered the implementation of the project. We request the headquarters to coordinate and deal with it.
Hereby apply!
XXX Real Estate Investment Co., Ltd.
XXX Xinjinshang Real Estate Development Co., Ltd.
May 16, 20XXX Part 2: Sample of application report for construction unit to start construction
xxx Development Office:
Herein, for the project (bidding section) undertaken by our unit, the construction machinery and other equipment have arrived at the project site. The department has been established, the construction management personnel and workers have been in place, and the conditions for starting construction are met. We are now applying to start construction, and we look forward to your approval.
xxxx Engineering Co., Ltd.
Part 3 of 2020: Sample application report for construction unit to start work
To the project supervision unit:
In view that the construction organization design of the unit project applied for in this application has been completed, construction equipment has been basically mobilized and brought to the site, personnel and construction organization are in place, and the conditions for starting construction are already in place. Apply for the start of construction of the unit's projects in order to prepare for construction and promote the early start of the first batch of branch (sub-project) projects.
Project Manager:
Construction Unit:
Application Date: Year, Month, Day
Extended Reading
Unit What are the contents of the project commencement application report?
1. All contents in the project commencement application report should be filled in truthfully, completely and accurately.
2. For branch (or sub-division) projects contracted by the construction unit, a separate start-up report should be filled out.
3. Conditions that must be met before the unit project can start:
(1) Construction organization design or construction plan approval;
(2) Construction drawings have been reviewed together;
(3) The site, three links and one level, and temporary facilities meet the construction requirements;
(4) The main materials, construction machinery and equipment have been implemented;
( 5) The construction permit has been applied for;
(6) The project baseline, elevation, etc. have been reviewed.
4. The construction commencement report must be signed and stamped by the construction, supervision and construction units before it becomes valid. ;