1. Safety construction measures
1.1 All construction activities must have safety construction measures, and disclosure shall be made before construction. Without measures or disclosure, it is forbidden to arrange construction.
1.2 the safety construction measures for general projects must be reviewed and approved by the technical director of the project, and then implemented after the technical personnel of the team disclose.
1.3 the safety construction measures for important temporary facilities, important construction procedures, special operations, seasonal construction and multi-job crossover operations shall be reviewed by the construction technology and safety supervision departments, approved by the company's chief engineer, and implemented after the technical personnel of the project department or team technicians disclose.
1.4 the safety measures and schemes for major lifting and transportation operations, special high-altitude operations, live-line operations and other dangerous operation projects must be reviewed by the construction technology, machinery management department and safety supervision department, approved by the company's chief engineer, and implemented after the technical personnel of the project department or shift technicians disclose.
1.5 when compiling safety construction measures, engineers and technicians must clearly point out the hazards, main hazards and possible hazards and pollution of the construction, and take technical measures to eliminate the hazards and reduce environmental pollution, which mainly means:
1.5.1 Take technical measures to eliminate the hazards that may be brought to the construction personnel according to the structural characteristics of the project.
1.5.2 technically control the unsafe factors that may be brought to the construction personnel by the machinery and tools selected for construction.
1.5.3 according to the use characteristics of the special materials that are harmful to human health or explosive and flammable, they should be protected from industrial hygiene and technical measures;
1.5.4 in view of the danger that the construction site and the surrounding environment may bring to the construction personnel or others, as well as the transportation of materials and equipment, technical measures shall be taken to control and eliminate the danger.
1.5.5 The safety construction measures approved and signed by the technical director or chief engineer must be strictly implemented. Without the approval of the measure approver, no one has the right to change it.
1.5.6 the person-in-charge shall be severely punished for the construction without measures or without disclosure, and the behavior of not seriously implementing measures or changing measures without authorization. Those who cause serious consequences shall be given administrative sanctions until criminal responsibility is investigated.
1.5.7 for repeated construction of the same construction project, the technician should re-submit the safety construction measures and conduct safety disclosure again.
2. Work ticket for safe construction
2.1 All construction activities of the power grid project must have a work ticket for safe construction, and all construction personnel participating in the construction shall be disclosed and signed for approval before construction. Construction is strictly prohibited without measures and disclosure.
2.2 when the construction team leader arranges work tasks, he should assign people who are familiar with the construction process and know the site conditions as the construction leader and safety guardian of the work tasks according to the actual situation on site, and determine the construction personnel of the operation group.
2.3 the construction team leader is responsible for filling in the operation tickets of each operation group, and selecting and supplementing the matters needing attention on the operation tickets.
2.4 generally, the construction team leader is responsible for issuing the operation ticket. In special circumstances, the construction team leader may designate the vice captain, technician or other management personnel of his team to review and issue it.
2.5 technicians and safety officers of the construction team shall review the operation tickets of each operation group before issuing the operation tickets, supplement and improve the precautions in the operation tickets, and sign for confirmation.
2.6 after receiving the construction task and the operation ticket, the construction director of the operation group shall supplement and improve the matters needing attention in the operation ticket according to the work task and the actual situation on site, and be responsible for the correctness of the supplementary items.
2.7 before the start of construction, the construction director of the operation group must read out the operation ticket to the construction personnel, and carry out the "three checks" and "three checks". After the construction personnel understand and master the contents of the operation ticket, they will sign their names in the "sign-in column for on-site disclosure personnel" in the operation ticket (note: "three checks": refers to handing in tasks, handing in safety, handing in technology and "three checks": refers to checking clothes and checking.
2.8 the construction director can only be responsible for one job at the same working time; When a day's work involves multiple tasks successively, the same person in charge of construction may be responsible for it, but the operation tickets of corresponding processes should be used in the order of work development.
2.9 if the main work content, work place and construction personnel listed in the operation ticket remain unchanged, it can be used continuously for up to five days, and it can be signed by the construction personnel of "three deliveries" and "three inspections" once; When the operation ticket expires, or the main construction content does not conform to the working procedure of the operation ticket, or the working place changes, the operation ticket will end accordingly.
2.1 any of the following situations when using the operation ticket shall be punished as violation of regulations: there is no operation ticket on the construction site; The examination and issuance are not in conformity with the regulations, and the signatures of relevant personnel are not uniform; The column of safety precautions is not selected according to the actual situation on site and marked with "tick"; There is no supplementary safety measures after the site situation changes; The person in charge of the construction did not read the operation ticket before the start of construction; Failing to carry out "three exchanges" and "three inspections" for the construction personnel, and failing to personally sign the operation ticket by the construction personnel.
2.11 the operation ticket should be properly kept during use, and the integrity of the operation ticket should be maintained.
2.12 during the construction of special projects, blank tickets (blank operation tickets) can be used, and the construction team leader will fill in the safety precautions according to the requirements of operation tickets, and strictly follow the above provisions.
for more information about the engineering/service/procurement bidding, and to improve the winning rate, you can click on the bottom of official website Customer Service for free consultation:/#/? source=bdzd