The Chinese name of the issuer is Jiang Weixin, Minister of Housing and Urban-Rural Development, issued on June 2009 10.
catalogue
1 relevant regulations
2 Submission of documents
3 record the results
4 filing procedures
Editor of relevant laws and regulations
Article 49 of the Regulations on Quality Management of Construction Projects stipulates that the construction unit shall, within/0/5 days from the date of completion and acceptance of the construction project, report the completion and acceptance report of the construction project and the approval documents or permission documents of the planning, public security, fire protection and environmental protection departments to the construction administrative department or other relevant departments for the record.
Article 4 of the Administrative Measures for the Filing of Completion Acceptance of Housing Construction and Municipal Infrastructure Projects (promulgated by Order No.78 of the Ministry of Construction on April 4, 2000, and revised by Order No.2 of the Ministry of Housing and Urban-Rural Development on June 65438+1October 9, 2009) stipulates that the construction unit shall1from the date when the project is completed and accepted.
Submit a file for editing
(1) project completion acceptance record;
(2) Project completion acceptance report. The completion acceptance report shall include the date of construction application, the construction permit number, the review opinions of construction drawing and design documents, the quality qualification documents signed by the units of survey, design, construction and project supervision, the original completion acceptance documents signed by the acceptance personnel, the relevant quality inspection and functional test data of municipal infrastructure, and the relevant materials deemed necessary by the filing authority;
(3) Approval documents or permission documents that shall be issued by the planning and environmental protection departments according to laws and administrative regulations;
(four) the certificate issued by the housing and urban-rural construction department that the special construction projects such as large-scale crowded places have passed the inspection according to law;
(5) the project quality guarantee signed by the construction unit;
(6) Other documents required by laws and regulations.
(7) residential quality guarantee and residential instructions.
Record score editing
After receiving the filing documents for completion acceptance submitted by the construction unit and verifying that the documents are complete, the filing organ shall sign the receipt of the documents on the Record Form for Project Completion Acceptance.
Project completion acceptance record form in duplicate, one kept by the construction unit and one kept by the filing authority.
Archiver editor
1. The completion acceptance can only be carried out after the self-inspection of the construction unit is qualified and meets the requirements of the Interim Provisions on Completion Acceptance of Housing Construction Projects and Municipal Infrastructure Projects.
2. After the completion of the project, the construction unit shall submit the project completion report to the construction unit, apply for completion acceptance, and be signed by the chief supervision engineer.
3. For the project that meets the requirements of completion acceptance, the construction unit is responsible for organizing an expert group composed of survey, design and supervision units to implement acceptance.
4. The construction unit must notify the engineering quality supervision institution responsible for supervising the project in writing 7 working days before the project completion acceptance.
5. Within 15 working days from the date of project completion acceptance, the construction unit shall submit the completion acceptance report in time and file it with the construction administrative department (and filing authority) of the local people's government at or above the county level where the project is located.
6. The project quality supervision institution shall submit the project quality supervision report to the filing authority within 5 working days from the date of completion and acceptance.
7. Urban construction archives management department shall conduct pre-acceptance of engineering archives according to the requirements of national laws and regulations, and sign the acceptance opinions.
8. After the filing authority reviews the completion acceptance filing documents, it shall sign the acceptance filing opinions and sign the completion acceptance filing form. The project completion acceptance record form is in duplicate, one kept by the construction unit and the other by the filing authority.