Current location - Quotes Website - Signature design - Example of steps for installing lightweight partition board
Example of steps for installing lightweight partition board
There are many partition materials. Including ordinary concrete materials and lightweight partition boards similar to those introduced below, are all materials and products that can be referenced. In addition, the price distribution of the product needs to be considered before buying. For example, the price distribution of lightweight partition board in the market is relatively broad, and consumers and friends can consider it with reference to the actual situation if they are interested.

First, the installation process of lightweight partition board

1, the structural surface, ground and floor are cleaned, and the line is drawn step by step, leaving the position of doors and windows.

2. Install from the side of the main structure plane. If there are doors and windows, install them from both sides of the doors and windows, leaving the last process partition board in the middle for installation, cutting it as wide as possible and installing it in the last position.

3, plumbing electrical equipment should be pay-off, before installing partition board, drilling adhesive embedded parts or switch socket; When it is necessary to cut the wire slot horizontally, the user should cut the slot and bury the wire by himself, and then smooth the wire with filler and ink it.

4. Working temperature:-10 degrees Celsius can be installed.

5, plate seam processing.

Second, the light partition board installation points

1, check the geometric size of the partition, which should meet the standard requirements.

2. According to the floor plan, fix the 40×50×90L iron pieces in the position to be fixed in advance.

3. Install from one side according to the layout. If there are door and window openings on the partition board, install them from the door and window openings to both sides. Aim at the chalk line, pry it as far as possible at the bottom with a crowbar, brace the upper end tightly, seal the edge of the board, plug the bottom with a wooden wedge and reinforce it.

4, when installation, check the flatness, verticality and other related inspection items at any time.

5, water and electricity buried pipe laying should be synchronized with the partition board installation, partition board surface need to open holes, should be drilled before installation, holes shall not be greater than 80 mm x 80 mm; The water heating hanger shall not exceed 80 kg, and the hanger exceeding 80 kg must be installed on the fixed embedded parts of the partition board.

6, electrical circuit switch, socket, etc. , around the application of filler.

7. After the partition board is installed, the bonding material must be dried before the next working procedure can be carried out, and the decoration can be carried out within 10- 15 days from the date of normal installation.

8, installed partition board surface can not have peeling, corner, empty drum and cracks, calculated according to the plane of each wall, to achieve intermediate plastering.

Three. Requirements for installation components of lightweight partition board

1, the top and bottom of the beam are fixed with U-shaped iron pieces, the U-shaped iron pieces are fixed at the bottom of the beam with nails, the upper ends are reinforced with wooden wedges and fixed with L-shaped iron pieces.

2. Hanging design: The hanging distance is not less than 300m, and the single point bearing capacity is not more than 80 kg, so the embedded parts need to be opened first.

3. Electrical design: the electrical circuit can be designed as a hidden wire, and the circuit can be laid through the hose through the hole of the partition; It can also be used as an open wire design and applied to walls, open sockets and their corresponding configurations.

4. Moisture-proof and waterproof: Moisture-proof and waterproof should be considered in decoration design. When designing accessories such as pool, water tank and basin along the wall, the wall should be painted with waterproof paint or tiled.

5, wall decoration: can be scraped white, sprayed porcelain, tiles and other decorative materials for decoration. During the decoration of the next working procedure, the partition wall shall be cleaned first, wetted with water, and decorated according to the conventional construction technology.

The above is about the price, purchase scheme and suggestions of lightweight partition board. It can be seen that a suitable lightweight partition board is often close to the people, and the options we can choose in the purchase process are also relatively rich. For example, Bian Xiao analyzed a representative one today, and further gave appropriate and reliable scheme suggestions and operation instructions, which I believe can maximize the value of lightweight partition board as much as possible.