Design change system of blue prints.the design?
The design change system of the blue prints.the design is very important. The details of the system are ultimately implemented according to various actual conditions, and only by in-depth understanding can we do better. Zhong Da Consulting Company lists the design change system of blue prints.the design as follows.

A, before the implementation of the project construction, the blue prints.the design of design drawings must be carried out, organized by the company according to the classification, specifically by the leaders in charge of the organization, the head of the project department and related technical personnel, project supervision, design units and interested parties to consult familiar drawings, understand the problems existing in the drawings, and put forward opinions on the blue prints.the design.

Second, the blue prints.the design should be recorded. The competent leader and the project department should organize the blue prints.the design. The design unit should solve the problems raised by the drawings in time, make detailed records and write them into official documents (the design unit will modify the drawings separately when necessary). The representatives and technical leaders of the supervision (construction) unit, design unit and construction unit shall sign and seal for approval and be included in the project file.

Three, in the process of construction, whether the design changes or construction orders put forward by the construction unit, should fill in the design change contact list, with the consent of the design unit and supervision, technical director and manager of the project department, before subsequent implementation.

4. If the contents of the design change have a great impact on the construction scale, investment, technology, quality and safety, it must be approved by the company and reported to the relevant competent department for approval.

Five, all design change information, including design change contact list, written records needed to modify drawings, into the project file.