Contractor (Party B):
According to the Civil Code of People's Republic of China (PRC) and other relevant laws and regulations, combined with the specific conditions of this project, both parties sign this contract for mutual compliance.
Article 1: Project
1. 1 Project name: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
1.2 Project location: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
1.3 scope of contract: according to _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
1) hydropower pipeline project connected with pump house and fire control center.
2) Fire hydrant system: including the indoor and outdoor fire hydrant system of the whole commercial and residential building.
3) Automatic sprinkler system: including the automatic sprinkler system of the whole commercial and residential building.
4) Automatic alarm and linkage control system: including the automatic alarm linkage control system of the whole commercial and residential building and the equipment supplemented by the fire control center.
5) Fire-fighting broadcasting and telephone system equipment and control circuits; Fire broadcast doubles as background music.
6) Ventilation, smoke control system equipment and control circuit of the whole commercial and residential building, and each equipment directly obtains power from the corresponding dual power converter.
7) The firefighting control loop related to the firefighting elevator system shall be required by the firefighting construction unit for professional cooperation of elevators.
8) Configuration of mobile fire extinguishing equipment.
9) Fan, fire shutter equipment and control circuit; The rear part of the dual power converter is completely completed by the fire fighting construction unit.
10) cut off the non-fire power supply line.
1 1) fire pool water level alarm system, circuit, etc.
12) monitoring and feedback system for fire fighting equipment.
13) Design and construction of gas fire extinguishing.
The above fire protection design drawings shall be submitted by Party B to _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
The materials, equipment and facilities involved in the above 1~ 13 project are all purchased, supplied, transported and installed by Party B, and all expenses are included in the contract price.
1.4 contract mode:
The contracting method is lump-sum contracting, that is, Party B must contract construction and expenses, contracted projects, contracted materials, contracted design, contracted duration, contracted quality, contracted safety and civilized construction, contracted coordination fees, contracted commissioning, contracted acceptance, contracted construction and installation, contracted profits and taxes, etc. Without the consent of Party A, the project shall not be subcontracted. It belongs to turnkey project.
Article 2: Project cost (lump sum price): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
2. 1 The total contract price of this project is (RMB): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
In words: RMB _ _ _ _ _ _ _ (RMB _ _ _ _ _ _ _ _ _ _ _).
2.2 Projects beyond the contract scope must be reported to Party A for confirmation before construction. After the construction, the project supervision company and Party A shall sign and seal to confirm the quantities, and settle the accounts according to the valuation. If the total increase of project cost is within _ _ _ _ _ _ _ _ _ _
Article 3: Construction Period
3. 1 Party B shall start construction from the effective date of this contract. Party A shall complete the construction progress before _ _ _ _ _ _ _ _ or the site fails to meet the construction conditions for Party B to enter the site. The construction period shall be determined by both parties through consultation.
3.2 The actual total duration of this contract shall be from the date when both parties sign the contract, and Party B shall formally start to work until the project is completed and accepted by both parties and the fire department.
Article 4: Project Quality Standards and Warranty Period
4. 1 According to the current national construction acceptance standards, provincial and municipal acceptance standards and project quality, the project quality standards are above the qualified level, and Party B guarantees that the project will be put into use as scheduled and pass the quality supervision and fire control acceptance.
4.2 The project warranty shall be implemented according to the relevant regulations of the Ministry of Construction, and the warranty period shall be two years from the date of formal approval of the acceptance report of the relevant government departments.
Article 5: Supply of Materials and Equipment
5. 1 All materials required for the project shall be purchased by Party B and supplied to the construction site; Finished products and materials shall be provided by Party B to Party A and the supervisor. After the sample is approved, Party B shall purchase and supply it to the construction site (except the materials and equipment provided by Party A).
5.2 All materials and equipment shall have factory certificates and production licenses, and shall be inspected in strict accordance with the regulations and requirements of relevant state departments, meeting the safety and quality standards stipulated by the state.
5.3 During the construction process, the engineering design changes due to Party A's reasons, and the materials and equipment purchased by Party B are not applicable. After Party A gives Party B proper compensation, Party B shall dispose of the unsuitable materials and equipment by itself.
5.4 The materials and equipment shall adopt the brand or similar products promised in the bidding documents (the brand of the products adopted shall be confirmed by Party A in writing).
Article 6: Payment of Project Price
6. 1 When the project progress reaches _ _ _%, Party A shall pay _ _ _% of the total contract price as the project progress payment;
6.2 When the project progress reaches _ _ _%, Party A shall pay _ _ _% of the total contract price as the project progress payment;
6.3 When the project progress reaches _ _ _%, Party A shall pay _ _ _% of the total contract price as the project progress payment;
6.4 After the project is completed and accepted by Party A and the supervisor, and the fire control system is fully opened, _ _% of the total amount shall be paid as the project progress payment;
6.5 After the project passes the fire inspection, Party A shall pay the project payment to _ _ _% of the contract settlement price within 10 days after Party B submits the complete completion drawings and settlement data to Party A for review;
6.6 The remaining _ _ _ _% shall be used as the quality deposit, which shall be paid within 10 days after the expiration of the warranty period, provided that Party B has not breached the contract.
6.7 Party B must submit a payment application report to Party A before each payment, and Party A shall complete the review within 65,438+00 working days from the date of receiving the payment application report from Party B, and pay Party B according to the above provisions. If Party A disagrees with the payment application report submitted by Party B, it shall notify Party B in writing within 65,438+00 working days from the date of receiving the report, and make payment after negotiation between both parties.
6.8 When Party A pays Party B, Party B shall provide Party A with a legal and valid invoice equal to the amount paid by Party A, otherwise, Party A has the right to refuse to pay.
Article 7: On-site visa and settlement
7. 1 on-site visa
7. 1. 1 When the items in the contract list are increased or decreased or visa items outside the contract list occur due to design changes or Party A's reasons, Party B shall organize Party A and the supervision company to accept and submit a visa application within _ _ _ days after the visa items are completed (Party A must be informed of the acceptance of concealed items before concealment).
7. 1.2 The materials that Party B should submit when applying for a visa include: the project contact sheet (such as the project contact sheet initiated by Party B, which must be signed and sealed by Party A and the supervisor) and the construction site visa sheet (which must have the quantities, unit price and total price). The quantity of work shall be accompanied by the calculation process, the list valuation unit price analysis table, the quota valuation unit price book), the original documents of on-site acceptance measurement (signed by Party A's engineering personnel, Party B and the supervisor) and photos, engineering design drawings and information on the blue prints.the design, the written reasons for the visa, and the single project acceptance sheet corresponding to this visa; On-site signing outside the contract