Current location - Quotes Website - Signature design - Whose name does the construction unit sign on the construction survey and pile delivery form?
Whose name does the construction unit sign on the construction survey and pile delivery form?
The construction unit shall sign the names of the following personnel on the construction survey and pile delivery sheet:

1. Project manager or construction manager of the construction unit: As the leader of the construction unit, he is responsible for the whole construction process of the project and needs to sign the legality, accuracy and reliability of the construction survey pile submission form.

2. Surveyor or engineering technician of the construction unit: As a professional in construction survey, you need to be familiar with measuring instruments and technologies, and be responsible for actual measurement, calculation and inspection to ensure the accuracy and completeness of the construction survey pile submission form.

3. Engineering supervision engineer of the supervision unit: As the supervisor of the construction unit, it is necessary to review and supervise the process and results of the construction survey to ensure that the construction survey conforms to the norms and standards and ensure the safety of the construction project.

4. Engineering designer of design unit: As the main responsible party of architectural design lofting, the design unit needs to check and review the construction survey pile submission form, and provide necessary technical support and guidance to ensure the legal feasibility of construction survey.