Current location - Quotes Website - Signature design - Factory maintenance labor construction contract template
Factory maintenance labor construction contract template

Factory Maintenance Labor Construction Contract Sample 1

Contractor (hereinafter referred to as Party A):

Constructor (hereinafter referred to as Party B):

< p>Party A and B, based on the principles of equality, voluntariness and consensus through consultation, have reached the following agreement on matters related to Party B's contracting of Party A's painting and decoration project (hereinafter referred to as the project):

1. Project address :

2. Project content:

3. Entrustment method: Party B provides materials and Party B pays for the labor.

4. Project duration:

1. Construction start date: (calculated from the start of work by Party B’s workers).

2. Completion date: (based on the date of acceptance according to the specified acceptance standards), except for natural disasters and force majeure.

5. Total project cost: (RMB) per square meter: ______ yuan.

VI. Rights and obligations of Party A:

1. Party B is responsible for purchasing construction materials by itself, and the materials purchased should comply with relevant national standards.

2. Party B is responsible for keeping the materials. Party B will be responsible for compensation for losses caused by improper storage.

3. During construction, if Party A needs to change or add construction projects, it should promptly and truthfully notify Party B. Both parties should sign a project change form and negotiate the cost.

7. Rights and obligations of Party B:

1. Party B’s construction personnel must strictly follow the construction procedures.

2. Party B must take protective measures for Party A’s other items.

3. Timely and proactively report the supervision situation and construction progress to Party A.

4. Party B must complete the project on time. If the construction period is delayed due to force majeure factors, the solution should be negotiated with Party A.

8. Payment method:

Party A shall pay the project payment within __ days after the project is completed and accepted. If the project is changed, Party A shall pay Party B the price agreed upon by both parties.

9. Contract validity: There are ___ copies of this contract, and each party holds __ copies. This contract will take effect after being signed and sealed by both parties. This contract will have the same legal effect after being supplemented.

Party A: Party B:

Signing date: Signing date:

Factory Maintenance and Construction Contract Sample 2

Contracting party: (below (hereinafter referred to as Party A)

Contractor: (hereinafter referred to as Party B)

1. In accordance with the "People's Republic of China and Civil Code", "Construction Project Quality Management Regulations" and other relevant laws , regulations, and following the principles of equality, voluntariness, fairness, and good faith, Party A entrusts Party B to carry out maintenance projects for the steel structure factory buildings such as the first workshop, the second workshop, and the third workshop of ___ Food Co., Ltd., and strictly in accordance with A The party requires fabrication, installation and anti-corrosion. Based on the specific circumstances of this project, Party A and Party B signed this contract through *** agreement negotiation. The specific contents are as follows:

2. Project location and content

1. Project location:

2. Project content:

(1 ) Dismantling, rust removal, anti-corrosion and fabrication of roof panels in the gas tower parts of workshops 1, 2 and 3.

(2) Removal of damaged and rotten parts of the wall, anti-corrosion and fabrication of wall panels.

(3) Manufacturing and security of nylon screens.

3. Project Cost

(1) The gas floor part and wall part of the first, second and third workshops

①The removal of the stained steel tiles is 3.00 yuan /M2.

② Maintenance of partial rust removal of steel structures (calculated based on the area of ??color steel tiles) 3.50 yuan/M2 (including scaffolding, if part of the anti-corrosion is not replaced, this unit price will apply)

③ Anti-corrosion (calculated based on tile area) 5.00 yuan/M2 (including scaffolding) If part of the anti-corrosion is not replaced, this unit price will apply.

④ Newly made purlins (C120 or 140) cost 18.00 yuan or 22.00 yuan/M.

⑤The upper color steel tiles on the roof (type 90, thickness 0.45MM, made of Baosteel plate or honest plate) are 30.00 yuan/M2 (single layer price).

⑥Inner layer UV.PVC anti-corrosion board (thickness 1.8MM) 48.00 yuan/M2 (single layer price).

⑦Hardware accessories used for roof panels and wall panels (calculated based on tile area) 3.00 yuan/M2.

(2) Nylon screen window (40 mesh) 20.00 yuan/M2 (including labor cost).

The above project quantities shall be settled according to the actual recipient.

IV. Payment method:

1. After the sporadic projects in the above examples are completed and accepted, 95% of the total contract amount will be paid within 10 days, and the remaining 5% will be used as a quality deposit. Payment must be made within 15 days two years after the completion of the project.

2. Party B is responsible for submitting completion data to Party A. If Party A requires a construction and installation invoice, it will be calculated as 5% of the total cost, and Party A is responsible for organizing acceptance.

5. Project duration:

Enter the site for construction according to Party A’s requirements, but Party A must meet the construction conditions. The construction period is 30 working days. In case of rain or force majeure, the construction period will be postponed.

6. Quality standards

The project shall be accepted according to Party A’s requirements.

7. The quality warranty period is two years. If quality problems occur during the warranty period, they will be dealt with within 24 hours of notification from the receiving party.

8. Rights and Obligations of Party A and Party B

1. Party A is responsible for the protection of the construction site's leveling equipment, meeting construction conditions such as maintenance, and sending professionals to supervise the site and provide Party B's projects free of charge. Use water and electricity.

2. Party B’s on-site managers and construction workers will be responsible for their own food and accommodation.

3. Party B is responsible for performing maintenance according to the project quantities confirmed by both parties to ensure that the one-time acceptance is passed.

9. Safety Responsibility

1. Party B organizes on-site construction by itself, and Party B must be responsible for the safety of workers on and off work and on-site work safety.

2. Party B must ensure safety and quality; if a safety accident occurs, Party B must bear the full amount and Party A will not bear any responsibility.

10. Liability for breach of contract

After the contract takes effect, Party A and Party B shall perform their respective rights and responsibilities in accordance with the contents of the contract. In the event of a breach of contract, the breaching party shall bear full responsibility.

11. Other Agreements

1. If there are other unsettled matters or agreed matters, Party A and Party B can supplement them in writing. The supplementary contract or agreement will have the same legal effect as this contract. In the event of a dispute, either party may file a lawsuit in the local people's court.

2. This contract will take effect immediately after being signed and sealed by Party A and Party B, and will automatically terminate upon completion of performance.

3. This contract is made in triplicate, with Party A holding two copies and Party B holding one copy.

Contractor: Contractor:

Contract signing date: