Article 2. The assessment of relevant management personnel should follow the principles of openness, fairness and impartiality, and reward and punish each work area in accordance with these regulations in the standardized management of safety and quality.
Article 3. Violation of laws and regulations on production safety; Quality management laws and regulations, etc. Depending on the seriousness of the case and the violation of the criminal law, it shall be handed over to the judicial department for punishment according to law.
Article 4. For all the problems existing in the inspection, each work area shall, in addition to punishing the relevant responsible persons and units, immediately rectify the inspection problems and report the rectification results to the Safety and Quality Department of the project department for future reference.
Article 5. All units and individuals have the right to defend the rewards and punishments of the Safety and Quality Department. Those who refuse to accept rewards and punishments have the right to appeal to superior leaders.
Management bar, as shown below:
1, safety management
1. 1 Newcomers go to work without a college degree and pass the examination (subject to the academic registration certificate and examination paper). 5 people or more, the corresponding work area will be fined 2000 yuan, and the person in charge of the personnel training organization department (room) will be fined 200 yuan/time, and it is required to rectify immediately. During the rectification period, if the existing problems are not rectified in place, the director of the work area will be fined 500 yuan; If the leader of the work area forcibly arranges it, it will be fined 1000 yuan.
1.2 electricians, welders, scaffolders, drivers of motor vehicles on the construction site, storekeepers of explosives warehouses, blasters and other special operations personnel are employed without certificates. Each person will be punished by 200 yuan/person-time for the director of the work area, and 2000 yuan for the work area. If there are too many people, they will be punished according to the seriousness of the case.
1.3 No special construction scheme and special safety technical disclosure were made for the installation and demolition project, and the disclosure was not signed (subject to the written scheme). The chief civil engineer was punished 100 times, and 200 yuan was punished in the work area.
1.4 tower crane and movable formwork are installed or erected and put into use without going through the formalities of acceptance (including stage acceptance) (subject to the acceptance visa). The chief engineer of machinery in the work area punished 200 yuan, and the work area fined 500 yuan.
1.5 Insufficient safety study times or hours per month, signature or fraud, and insufficient safety activities before class (all are subject to records). 200 yuan was fined for the work area.
1.6 Not equipped with full-time quality assurance personnel (excluding part-time jobs) according to the specified attendance ratio, and the workers produced at the site without construction management personnel. 200 yuan was fined for the work area.
1.7 Failing to rectify the hidden danger rectification notice put forward by superior inspectors on schedule or failing to report it to relevant personnel for review after rectification. 200 yuan will be fined in the work area (double times, cumulative punishment).
1.8 Various safety production management systems were not posted. Work area fine 100 yuan.
1.9 safety management data does not use the prescribed form. Fine 100 yuan (according to the number of missing tables)
1. 10 fails to participate in weekly safety activities or the team fails to organize safety activities without any reason, and 200 yuan will be punished by the work area safety and quality department.
1. 1 1 Recruiting child labor or arranging minors under 18 to engage in prohibited labor as stipulated by laws and regulations, the director of the work area shall be fined 500 yuan/person.
1. 12 violates the safety and quality management instructions issued by the owner, the supervisor and the project management department. Give the work area director a fine of 200- 1000 yuan.
2, tunnel construction safety
2. The civilized construction management of1tunnel is not in place, and the suspension of pipelines and cables does not meet the specification requirements; There is water and silt on the road, and the ditch is not smooth; Materials, equipment, machines and tools are not hung with responsibility cards, and they are placed in confusion. Fines 200 yuan to the work area.
2.2 If the tunnel construction spacing exceeds the standard and does not meet the requirements stipulated by the Ministry of Railways, the work area will be fined 3000 yuan/time, and the tunnel face construction will be ordered to stop.
2.3 The advance geological forecast is discontinuous; If the monitoring and measurement are not serious, the frequency is not enough, and the points are insufficient, 500 yuan will be fined for each item found.
2.4 The mobile substation in the tunnel is not equipped with safety fence as required; Not equipped with fire fighting equipment; No safety warning sign is set. A place was fined 300 yuan.
2.5 For the working face with mud outburst and water inrush danger, the advanced geological forecast or the "explore before digging" system is not implemented to explore the water; There is a danger of gas outburst, and no outburst prevention measures are taken to predict and forecast, and advanced exploration holes are drilled. Each item will be fined 2000 yuan to the work area. Construction, the responsibility of the relevant personnel shall be investigated.
2.6 The position and size of embedded parts in the tunnel do not meet the design requirements. Fines found 1000 yuan.
2.7 In the process of tunnel excavation, excavation shall be carried out according to the design contour line. For the phenomenon of over-excavation and under-excavation, which do not meet the requirements of design drawings, the work area shall be fined 1000 ~ 2000 yuan according to the area, and the work area shall be reworked. Temporary support does not meet the requirements of the construction organization, and the work area is fined 1000 yuan for empty roof and empty help.
2.8 Tunnel lining must meet the requirements of design drawings. After the lining is completed, the concrete surface should be dense, flat and even in color. If there are missing ribs, honeycomb, holes, looseness, pits and contour deformation, a fine of1000-3,000 yuan will be imposed. If the lining thickness can't meet the design requirements, a fine of 1000 yuan shall be found and reworked. The quality of concrete should meet the requirements of construction technology: the processes of mixing, transportation, pouring, vibrating, demoulding and curing of concrete meet the quality requirements, and the fines for non-compliance are1000 ~ 3,000 yuan; If the concrete mixing process is not strictly controlled or the production and maintenance of various concrete specimens are not standardized, a fine of 500 ~1000 will be imposed; If the mixture ratio is not adjusted after material replacement, a fine of 500 ~ 2000 yuan will be imposed.
3, mechanical safety
3. 1 Work area will be fined 100 yuan in any of the following circumstances.
3. 1.65438+
3. 1.2 After the concrete mixer hopper rises, there is no safety hook during non-operation;
3. 1.3 Circular saw (sawmill) has no tail blade or panel, or uses rubber blade switch as power switch at will, and uses reverse switch as control switch;
3. 1.4 Safety operation procedures for hoisting machine, concrete mixer, mortar machine, saw machine and reinforcing bar machine not hanging.
3.2 The tower crane shall be punished by 300 yuan in the work area under any of the following circumstances.
3.2. 1 No torque, superelevation, amplitude variation, travel limiter or insensitivity; The walking limiter has no contact device;
3.2.2 There is no special person to command or command personnel or drivers to work without a license.
3.2.3 After the tower crane is installed, it will be put into use without experience. (subject to the acceptance certificate) 200 yuan will be punished in the work area.
4. Electrical safety
4. 1 The distance between the project under construction or temporary facilities and the adjacent high-voltage lines is less than the specified safety requirements and there are no protective measures; Each place will be fined 1000 yuan for the work area.
4.2 Don't use three-phase five-wire power supply; Give the work area a punishment, 200 yuan.
4.3 The live parts of electrical equipment or facilities are not shielded as required; Give the work area a fine of 100 yuan each time.
4.4 Electrical equipment is not connected to zero (grounding) protection according to regulations, or copper wire is used as safety gold wire without inspection; 50 yuan/minute for each fine.
4.5 The circuits used by hand-held power tools, submersible pumps, mobile electrical equipment and migrant workers' dormitories are not equipped with leakage protection switches as required; 50 yuan will be fined for each work area.
4.6 The distribution box and switch box have no rainproof measures, which violates the provisions of just one brake, the iron box has no zero (grounding) protection, and the electric box lies on the ground; Give the work area a fine of 50 yuan/Department.
4.7 The insulation of welding machine power cord, welding cable and electrode holder is damaged, and the primary and secondary terminals of welding machine are not shielded; Give the work area a fine of 30 yuan/Department.
4.8 The erection and installation of electrical lines and lamps are not in conformity with the specifications (including migrant workers' dormitory sheds); Give the work area a fine of 50 yuan/Department.
4.9 There is no three-level leakage protection, or mismatch or failure (one level is fined for one level), and safe voltage is not used for working hand lamps or dangerous places; Give the work area a fine of 100 yuan/place.
4. 10 electric box has no door, no lock and no sundries in the box; (Spare items are also counted as sundries) Work area fine 100 yuan/place.
5, scaffolding engineering
5. 1 scaffold is not higher than the construction surface (point)1.2m; The work area will be fined per 10 linear meter 100 yuan.
5.2 Scaffolding has no erection scheme or has not been approved, and the site has not gone through the formalities of approval and change after the scheme is changed; Give the work area a fine of 1000 yuan.
5.3 The erection of external scaffolding is not in conformity with the regulations (for example, the anchorage with the building is not firm, the vertical pole is too small, the cross bar spacing is too large, and the flat bridge is unsafe, etc.). ), or not built according to the approved erection plan; Each floor will be fined 100 yuan.
5.4 Oblique baffles are not set according to regulations or scheme requirements (for example, bamboo, wood and steel plates are replaced by fiber cloth or irregular safety net for baffles); Every fine 100 yuan.
5.5 The connection of steel pipe members need not be connected by fasteners; Every fine 100 yuan.
5.6 The use of bamboo poles and the connection of bamboo scaffolding bars do not meet the requirements of the Operating Rules for Safety Technology of Construction and Installation Engineering; Each joint will be fined for the work area 10 yuan.
6, three treasures, four, five limb protection
6. 1 There are no safety protection facilities at the elevator entrance, stairs, access openings, reserved holes and stairs; Give the work area a fine of 100 yuan/place.
6.2 No guardrail higher than 1m is set at the edge where the falling height exceeds 2m; Give the work area a fine of 100 yuan/place.
6.3 When crossing up and down, there is no isolation protection facilities; Give the work area a fine of 100 yuan/place.
6.4 Construction personnel (operators and managers) do not wear personal protective equipment (including safety helmet, safety belt, work clothes, work shoes, insulating shoes, protective masks, etc.). ) as required. If one person is found to have failed to provide personal protective equipment for the construction personnel on site, 500 yuan will be punished/person-time, and the assistant manager on site will punish 300 yuan/person-time. For violations found in the major inspection, the work area will be punished 10 times.
7, drilling, digging pile engineering
7. 1 If the pile hole depth exceeds 5m and there are no following safety facilities, the work area will be fined 300 yuan/item.
7. 1. 1 mechanical ventilation device;
7. 1.2 semicircular flat protective steel plate (net) for preventing falling objects from hurting people;
7. 1.3 Operators go up and down stairs;
7. 1.4 safe voltage of 12 volt is not used for well lighting;
7. 1.5 measures and equipment for detecting oxygen deficiency and toxic gases.
7.2 There is no anti-scarring cover plate at the hanging pile hole; Work area fine 100 yuan.
7.3 The retaining wall of the hole ring in the first section shall not exceed15 cm above the ground of the site; Work area fine 100 yuan.
7.4 Bucket hook has no anti-skid device; Work area fine 100 yuan.
7.5 There is no construction scheme or the construction scheme is not approved in the construction of digging pile; Give the work area a fine of 1000 yuan.
8, initiating explosive device management
In case of any of the following circumstances, the responsible work area shall be fined 5000 ~ 10000 yuan after investigation.
8. 1 initiating explosive device management; Explosives and detonators are not packaged and transported separately; Explosives and detonators on the job site in the cave are littered or unsupervised; Residual explosives and detonators are not returned to the warehouse in time or the system of receiving and returning is not implemented; The work area is not equipped with warehouse keeper as required; Foreigners entered the library without registration.
8.2 The system of "one shot, three inspections" was not strictly implemented during shooting; The blaster did not carry the detonator with him or give it to others for safekeeping.
8.3 Charge or explosive shield smokes.
8.4 There is a phenomenon of charging while drilling in tunnel construction. If the fine is doubled for many times and the fine is invalid for many times, it is suggested to replace the deputy director of the work area.
9. Others
9. 1 acetylene generator or acetylene bottle has no backfire prevention safety device; Give the work area a fine of 200 yuan/each.
9.2 Where all kinds of gas cylinders are exposed to the sun or the distance from the fire source is less than10m, and the distance between oxygen and acetylene is less than 5m, liquefied gas cylinders shall be used instead of acetylene cylinders; Give the work area a fine of 200 yuan/each.
9.3 The construction site fails to set up safety signs reasonably according to regulations (such as preventing electric shock, mechanical injury, falling from a height, falling objects from hurting people, etc.). ); Give the work area a fine of 50 yuan/each.
9.4 The site civilization construction lacks five certificates and one picture, and 300 yuan is fined for one brand less.
9.5 If one person dies or the economic loss exceeds 65,438+10,000 yuan, the director of the work area will be fined 40,000 yuan, and the secretary, deputy manager, safety director, chief engineer of machinery, chief engineer of civil engineering and chairman of the trade union will be fined 3000 yuan. At the same time accept the punishment of the joint-stock company.
The above reward and punishment system for tunnel construction safety and quality shall be collected and sorted by Zhong Da Consulting Company.