Article 1 Summary of Personal Annual Work of Engineering Department
Time flies, fleeting, we have gone through 20__ years of ups and
Article 1 Summary of Personal Annual Work of Engineering Department
Time flies, fleeting, we have gone through 20__ years of ups and downs. This year, under the leadership of the company's project leaders and with the joint efforts of colleagues from all departments, the Huang Tiao Water Diversion Project in Pingyuan New District has successfully passed through one difficulty after another, and Qi Xin, the project departments, worked together to overcome the difficulties. The whole project has achieved an extremely valuable stage victory, laying a good foundation for the next stage of work in the coming year. The annual work is summarized as follows:
First, diligent and pragmatic, pay close attention to on-site production work.
The main work completed this year is earthwork, with an excavation volume of1800,000 cubic meters and 290,000 cubic meters of filling and micro-topography piling. The construction site is divided into four areas, I, II, III and IV * *, and the operation is carried out in two stages. The whole earthwork was completed by three subcontractors. Our main work is the subcontractor's construction management, on-site quality inspection, and coordination and communication of multi-party relations.
1. Count the number of subcontracted construction machinery every day and record the work site. Since the start of construction, the site has changed every day, and the daily work of our department has detailed and true records. And infer the work progress from the work efficiency for a period of time, and make a feasible work progress plan.
2. Implement and appropriately optimize the construction scheme at the construction site. To transport the huge amount of earthwork outside the lake area, the transportation channel is the premise, so the construction of temporary roads is a preparatory work that must be strictly completed. Temporary roads should be wide enough to carry earth-moving vehicles and large mechanical equipment. Because most of the original landforms on the site are fish ponds and the soil is soft, a lot of brick slag needs to be replaced. Brick slag was purchased from outside, and 12000 cubic meters of brick slag needed for earthwork transportation of the whole temporary road was completed by all members of the engineering department on duty overnight in turn, which lasted for nearly one month, and then mechanical leveling and compaction were dispatched. Temporary roads 1900 meters are built in the whole project, which provides a reliable guarantee for on-site earthwork transportation. The working position and sequence of subcontracted machinery, as well as the formulation of the entry and exit routes of earth-moving vehicles, will be formulated with the participation of on-site construction personnel, and will be changed and optimized in time when construction conditions change. When the West Lake revetment was started, nearly 200,000 cubic meters of water in areas I and II could not be discharged in time due to heavy rain and groundwater infiltration, which directly affected the revetment excavation. After the implementation of the drainage scheme, our department has carried out a month-long follow-up observation of the water level, which provided accurate data basis for the later progress formulation.
3. Inspect and supervise the construction of subcontractors. Design and construction drawings are the basis for testing the site construction effect. The elevation of each part of the lake bottom and the position of detailed structures such as the lake shore are clearly written on the drawings, but deviations will inevitably occur in actual construction. At present, the quality of earthwork in all aspects has reached the acceptance standard of supervision, which is the result of thousands of times of elevation and coordinate checking in our department, which not only effectively avoids rework, but also ensures the progress and quality of the project.
4, safety is no small matter. With a huge construction site, more than 30 mechanical construction operations and more than 80 earthwork car running back and forth, any detail problem may turn into a safety accident. As the construction personnel in charge of the site, the string of safety awareness is always tight. Once potential safety hazards are found on the site, take photos and samples immediately, notify the subordinate subcontractors to set up safety warning signs, and order them to make rectification on time. The safety awareness deeply rooted in people's hearts ensured that no major safety accidents occurred in the whole project.
Second, it is rigorous and meticulous, which provides a strong basis for the confirmation of engineering quantity.
Field construction is closely related to the economic benefits of the project. When earthwork is subcontracted, the determination of transportation distance and the amount of earthwork in the dump directly affect the overall cost. Each settlement of earthwork volume is calculated by our staff using total station to complete all excavation parts in turn, and then on electronic drawings. Our staff also use levelers and tape measures to measure large and small garbage dumps. All rigorous and meticulous survey work ensures the objectivity and impartiality of the data and is a reliable basis for earthwork settlement.
In addition to earthwork settlement, other expenses on site should not be underestimated. For example, mechanical measures, due to the long time span of settlement of these expenses and scattered measures, our department has carried out classified statistics on the measures to ensure that it is well documented when checking with subcontractors. Brick slag is also a very big expense. When all the bricks are delivered to the site, our staff will confirm the quantity, and then sign the original and deputy sheets to ensure that the quantity of bricks is true and reliable.
The confirmation of all engineering quantities has been strictly notarized by our department, which not only ensures the economic benefits of the project department, but also creates value for customers.
Third, be reasonable and properly sort out the working relationship between all parties.
As on-site construction personnel, it is particularly important to handle the relationship with all parties. In the daily inspection work of the supervisor, the staff of our company actively prepare to accompany the work, deal with the facts in the inspection process, be humble, accept opinions with an open mind, solve problems in time, and ensure a harmonious relationship with the supervisor.
We also attach importance to the relationship between subordinate subcontractors. In the face of subcontracting, we are arrogant, fair and just, urging them to ensure the quality of the project and standardizing their behavior and style. * * * We will continue to work together to advance the project.
There are still some villagers who have not moved away. With the gradual progress of construction, crops and trees planted by villagers will be destroyed, and many temporary houses and appendages in the lake area need to be demolished. Although Party A has coordinated these compensation issues before, in the field work, it will still encounter unreasonable obstruction from some villagers, and even cause some work stoppages. As on-site management personnel, we were tepid, patiently explained to the villagers, and sought coordination and consultation from all parties, so that the contradictions were resolved in a timely and effective manner. Up to now, 63 temporary houses have been successfully demolished, ensuring the steady progress of construction.
Fourth, be proactive and constantly improve your working ability.
The members of the engineering department are mostly young people, and their work experience is not senior enough. The field experience needs to be further accumulated and enriched. However, this group of young people make full use of their energetic and strong learning ability to make up for these shortcomings, "recharge" in their spare time, constantly sum up in their work, enhance the tacit understanding of teamwork and improve the combat capability of the team.
5. Calm reflection and pave the way for next year's work.
Although many good achievements have been made in engineering, there are still some defects and deficiencies. The rainstorm in August seriously affected the progress of the construction period. Although the lost construction period was barely made up in the later progress plan, the lack of foresight made us pay the price.
Many times, the engineering department is like a sharp knife on the battlefield, always standing at the forefront of the scene. No matter how hard the environment is, they are brave enough to show their swords, willing to pay, and silently dedicate their youth and sweat. I believe that with the passage of time, our engineering department will be able to play a more powerful role, win the overall victory of the whole project in the next 20__ years, and write the most brilliant music of our engineering department.
Article 2 The personal annual work summary of the Engineering Department
20__ year is coming, review the work of the department in the past year, and make the following summary report:
I. Progress
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ d1# ~ d10 # building, and the acceptance of the main structure will be completed in late May. Won the title of city high-quality structure. Pile foundation construction of building D 1 1 ~ D 16 # started in early April, capped in late August, opened for the second time on _ _ _ September, and the main structure was accepted in late June, thus obtaining the city's high-quality structure. At present, indoor interior wall painting has been completed, and external wall insulation has been completely pasted. Since the temperature in June and February of 5438 was always below zero, the real stone paint on the external wall could not be constructed, so the dismantling time of the external wall scaffolding was delayed accordingly.
_ _ Company began to excavate the high-rise building 1 1 # ~ 14 # and the basement area of Phase I in July. Due to the poor organization of construction and excavation teams in rainy season, the progress is slow. Under the repeated urging of the company leaders, the excavation of various buildings was completed at the end of 10. The basement should be completely capped around the end of 65438+February. Four buildings were capped many times before the Spring Festival in 20__. Except for 14# building, the main structures of the four high-rise buildings are all constructed above 10 floor.
The 1 ~ 3 # building built by _ _ company started construction in August. After careful construction by the construction unit, the main structure should be over 10 by the end of the year, and the other two buildings can be capped.
Second, the quality control
Since the start of construction, the engineering department has been strictly controlling the quality and taking the project quality control as the top priority of project management. So far, the construction quality of the whole project is satisfactory. It is understood that the inspection teams of provincial, municipal and county-level construction departments have conducted many quality inspections, which have been affirmed by the inspection teams. However, there is still a big problem in the waterproof quality of the roof of D 1 # ~ D 10 # building, which leads to leakage. It has had a great impact on the sales of penthouses. In the process of roof waterproofing construction, engineers found problems in the construction technology through on-site inspection, and repeatedly asked for rectification and adjustment of the construction method. However, the construction team went its own way, resulting in leakage every time the roof construction was completed. Company leaders attach great importance to it, and since the first special meeting was held on July _ _, several special meetings have been held before and after. After changing the maintenance team, the roof waterproof maintenance has been basically and effectively controlled. Judging from the occurrence of this incident, it poses a great challenge to the daily quality management of the engineering department in the future. "Quality first" is not only a slogan, but also should be implemented in daily work.
Third, the site safety courtesy construction management
_ _ The residential area has a large building area and covers a large area. The completed building is side by side with the main building, and the level is outstanding. The earthwork in the basement is excavated in a large area, which leads to a mess in the construction site. The general contractor did not improve the general layout of the site, piled materials and placed construction machines and tools at will. Company leaders have put forward opinions many times and demanded rectification. For this work, the engineering department and the joint supervision department have conducted special inspections for many times to urge rectification within a time limit. However, in order to grab the construction period, the construction unit perfunctory the questions raised by the inspection. In the future work, the engineering department should continue to pay attention to this work to ensure that management is in place and create a good construction site environment.
Fourth, the management of supervision department
_ _ supervision company is a supervision company in this county. Although the supervision company has sent a group of supervision teams with strong work potential, there is still a gap in our company's requirements for quality, safety and schedule control. The engineering department should spend a lot of energy to help the supervision company complete the company that should have been completed by the supervision company. Accordingly, the labor intensity of employees in the engineering department has also increased. But in order to effectively control the project quality and other aspects of management. The contribution of the engineering department is also taken for granted. There have been no major quality and safety accidents in many aspects such as engineering quality this year. Received oral praise from the county quality supervision department.
Verb (abbreviation of verb) engineering visa
The company has established the examination and approval system of engineering visa process, and implemented the seven-level examination and approval of the general manager of supervision engineer. For visas that should not be paid, resolutely return them, and strictly review the number of visas that have been confirmed to be paid to prevent unreasonable expenses. The examination and approval of the project payment is also strictly controlled according to the project contract.
External coordination of intransitive verbs
External coordination plays a great role in the smooth development of the project. With the help of the company's leaders, the engineering department actively established good relations with county and city functional departments, competent units, urban management departments, environmental monitoring, greening, water supply, power supply and other departments by using good contacts and a series of measures to ensure that the project was less disturbed by the outside world.
Seven. Internal management of engineering department
Effective division of labor has been carried out for employees in this department, so that employees in this department not only have a clear division of labor, but also unite and cooperate to help each other. Regularly organize department employees to learn advanced theoretical knowledge and improve their work skills. And organize the ideological education of loyalty to the company, dedication to the cause, unity to colleagues and work efficiency, so that the overall management level and business potential of the engineering department have been improved.
Eight. Procedural status
According to the company's organization, all construction procedures are also the focus of the engineering department. For all procedures, including planning permission, quality supervision, safety supervision, construction permission, archives, civil air defense office, environmental protection bureau, seismological bureau, fire brigade, power supply, water supply and other departments, we have done our homework attentively, and we are not afraid of difficulties in getting in, ugly face and difficult to say. We have used the accumulated network resources for many years to take the initiative to run more errands and follow up, so that the promotion work will not stop or delay in our department, ensuring the smooth completion of the procedures.
In the future work, we should strictly control the quality and progress, pay attention to planned and targeted quantitative management, and clearly understand the shortcomings in management. Really take the company's affairs as your own and show good professionalism. Strict work style and high professional level, be an honest and excellent employee and excellent management team, and contribute wisdom and talent to the future of _ _.
Article 3 the engineering department personal annual work summary
In a blink of an eye, 20__ years have passed, and now I will make a summary report on the work of the engineering department in the past year from the following aspects.
First, schedule control
According to the project schedule requirements formulated by the company at the beginning of the year, the main project should be completed by the end of 10. By the end of the year, the main project has been completed, and the masonry project has been completed 80%, which is later than the original construction period 1 and 5 months. The main reasons for the delay are as follows:
1. We underestimated the difficulty of the project in advance, and the contract period was too tight. The fixed duration of this project should be 720 days, but we shortened it to 350 days. This construction period can only be completed as planned under ideal conditions. However, due to the difficulty of this project, any unexpected situation may cause the delay of the construction period and may have a chain reaction.
2. We underestimated the actual strength of the construction unit in advance (including financial strength and management strength). Both construction units belong to the contract responsibility system. The construction unit collects the management fee from the contractor, and the contractor is responsible for the capital investment of the project and the allocation of management personnel. The construction unit does not give any financial support and personnel support to the contractor, and it also lacks necessary management support. There is a phenomenon of escrow by package. The main reason that restricts the construction period lies in the capital and management of the construction unit. Lack of financial strength often leads to the shortage of materials and equipment, the phenomenon of waiting for materials at the construction site and the loss of construction personnel. The serious shortage of labor force has caused serious delay in the progress of the project. In management, on the one hand, the responsibility and quality of managers can not meet the due requirements; On the other hand, due to too many subcontracting levels in the labor service layer and too fine grouping of work classes, it is impossible to form a flow process, which makes it difficult to allocate project managers; At the same time, due to the subcontracting of the labor service layer and too many management levels, the management intention of the upper management personnel, especially the project manager, cannot be implemented in time and effectively in the team. On the other hand, migrant workers at the moment are also difficult to manage, often because of some minor problems and managers. This is the main reason for the delay in the construction period.
3. Self-management problems: Although the engineering department, especially the department manager, has taken a series of careful measures to delay the construction period of the construction unit, it is not strong enough and lacks effective management measures and emergency measures to deal with some problems, especially the serious shortage of personnel and untimely supply of materials in the construction unit, which is also one of the factors leading to the delay of the construction period. All of us, especially department managers, need to learn project management knowledge, master more good management experience and methods, and further improve their management level, so as to live up to the trust of leaders and make greater contributions to the development of real estate.
In view of the above problems, with the strong support and help of the general manager's office, all employees in our engineering department have taken a series of measures in terms of funds and achieved good results. In the construction process in the second half of the year, not only the momentum of further delay in the construction period was curbed, but also the delayed construction period was gradually reduced.
Second, the quality control
Since the start of construction, the engineering department has always adhered to the principle of quality first and strictly controlled the quality. So far, the construction quality is satisfactory, although some quality landslides have been solved in time before, which has continued the overall momentum of high-quality projects and laid a solid foundation for creating a cup. At present, after many inspections by the municipal quality inspection station and the provincial station, although some problems have been raised, the overall quality of our project has been affirmed. Judging from the current situation, it is not a big problem for our project to pass the provincial quality main structure acceptance.
Third, cost control.
Cost control, mainly from the following aspects.
1, as far as possible to reduce the unnecessary cost input in the drawings, such as the construction of civil air defense basement. In order to save costs, we decided to carry out the construction on the building plane according to the drawings of _ _ design institute, but the structure was carried out according to the drawings of _ _ design institute, which is expected to save the company nearly one million yuan; Without increasing the cost, we also increased some parking spaces for sale through technical transformation, which increased the sales revenue. At the same time, the installation specialty also saved nearly one million yuan for the company by putting forward some reasonable schemes, and was praised and rewarded by the company.
2. For some technical changes in the construction process, we will promptly make changes that have little impact on the investment cost or reduce the cost. For changes that increase the cost but remain unchanged, we will organize technical analysis and choose the most economical and feasible change plan. At the same time, the examination and approval system for drawing changes shall be strictly implemented, and all changes shall be approved by the general manager's office before implementation.
3. In terms of engineering visas, we have re-established the examination and approval system for engineering visas, and implemented seven levels of examination and approval for supervision engineers, directors, competent engineers, engineering managers, budget engineers, finance managers and general managers' offices to ensure that visas that should not be paid are resolutely returned, and those that do occur and should be paid are strictly reviewed to prevent unreasonable expenses.
Fourth, site safety and civilized construction
As the goal of this project is a provincial civilized construction site, we have paid enough attention to the safe and civilized construction on site. Due to the limited conditions in the early stage, the civilized construction on site could not be done well. In the later period, we made great efforts to grasp the civilized construction on site and achieved good results. At present, after many inspections at provincial and municipal security checkpoints, it is expected to pass the acceptance of provincial civilized construction sites in the near future.
V. Management of Supervision Company
Generally speaking, there are some problems in the management of supervision companies, mainly due to the lack of excellent technology and failure to strictly follow the contract requirements, which leads to the low overall quality of supervision personnel. Finally, our engineering department had to spend a lot of energy to help the supervision company complete the work that should have been completed by the supervision company. Although with our joint efforts, this work has basically been successfully completed, the labor intensity of the comrades in the engineering department has increased accordingly. But on the other hand, we should also realize why the overall quality of the personnel sent to the construction site by the supervision unit is low. The reason is that the cost of supervision is too low. If the cost of supervision is low, the wages of dispatched supervisors will be very low (800~ 1200 yuan/month), and the quality of supervisors with low wages will inevitably be low.
External coordination of intransitive verbs
For an engineering project, external coordination has a great relationship with the smooth development of the project. In this regard, with the help of the leaders, we have taken a series of measures to maintain good relations with the two quality inspection stations, law enforcement departments and other units to ensure that the project is as little as possible disturbed by the outside world.
Seven. inner management
First of all, according to the needs of the work, adjust the staffing of the engineering department in time to replenish fresh blood and enhance the overall strength. In order to improve the management level and technical potential of all personnel in the engineering department, this year the engineering department organized relevant personnel to participate in the study and examination of registered supervision engineers, and also participated in the management study organized by the company's administrative personnel department; On the other hand, it also organized two visits to the construction site of the brother unit, and organized civil engineers to participate in the online lecture on "Analysis of Cracks in Concrete Basement Wall and Preventive Measures"; In addition, it is also required to strengthen everyone's study of specifications in order to improve the overall management level and business potential of the engineering department.
VIII. Reflection and Suggestions
1, in the future project operation, try to make a reasonable time limit plan to avoid adding too many variables to the company in the actual project operation process and affecting the company's overall plan. At the same time, as the advance of the construction period will bring us greater benefits (including saved management expenses and promotion of sales value), and the construction unit also needs cost input to speed up the construction period, in order to encourage the construction unit to take measures to speed up the construction period as much as possible, the construction unit that speeds up the construction period can be given generous rewards to improve its subjective desire to shorten the construction period.
2. When selecting the construction unit for future projects, it is necessary to study how to evaluate the real strength of the construction unit more accurately and how to fundamentally put an end to all forms of affiliation and subcontracting. We believe that we should first make strict regulations on such issues during contract negotiation, and at the same time, the contract price should not be too low, because the management cost of a good construction project department must be high, and it is impossible to find a really good project department at a low price. The indirect benefits created by a good project department are far greater than the part of the project cost that we give him more. So is the choice of supervision company. It is impossible for a powerful supervision company to recognize the low cost of supervision. In order to better manage the site, we suggest that the supervision cost should not be deliberately lowered in the bidding process of the supervision company in the future, so as to ensure the overall quality of the supervision team and good supervision quality.
3. Because the profits of real estate companies come from the difference between sales and investment, the key to the cost control of construction and installation is the design link. We suggest that in the design process of future projects, on the one hand, we should choose a design company with strong strength, especially a strong sense of responsibility, and at the same time, before the construction drawing is formally drawn, we should find a design institute or a high-level structural engineer to carefully examine the drawings, and pay the labor fee according to the necessary proportion for the expenses saved after their examination. In this way, the cost can be controlled more effectively and the unnecessary cost expenditure can be controlled to a minimum.
To sum up, the engineering department, especially the department manager, has an unshirkable responsibility for the serious delay in the construction period of this project, and the management of project quality and site management needs to be further improved. But on the whole, our site management can reach a higher level in the same industry in terms of engineering quality, and all employees in the engineering department can be conscientious and responsible, and work overtime for the smooth development of the project without complaint. Sacrificing one's rest time and truly taking the company's affairs as one's own, it embodies the master's thoughts, shows good professionalism, rigorous work style and high professional level, and also shows the elegance of KONE employees in integrity. They are a group of excellent employees, an excellent team and a team that can win the battle.
Summing up the experience and lessons of previous work, in the future project management process, we will continue to strengthen on-site construction management, on the one hand, to ensure the high-quality completion of the work target of Shangcheng International Project next year, on the other hand, to further strengthen the improvement of the overall quality of internal personnel. And organize all engineering staff to further improve the management level and professional technical level of all staff through visiting and studying, CD-ROM learning, online lectures, self-study of standard terms, etc., so as to raise the overall level of our team to a new level and complete the group company. Our goal is: "I am proud to be a _ _ person, and let _ _ be proud to have me".