Summary of Project Manager Fan Wen's 2020 Personal Work (1) 20xx years have passed and 20xx years are coming soon. I will make the following report on my work in 20xx.
A, the project quality completion
Xx community is the key construction project of the company in xx years. After I was approved as the project manager by the company, I immediately started the establishment of the project department. First of all, according to the work requirements of xx, we will transfer personnel from the company to establish a quality management system, project management objectives and post responsibility system for management personnel. The quality goal of xx community is to create a "community without common quality problems", so the company has introduced many preventive measures and implementation methods.
In order to ensure the realization of the overall goal, I organized the management personnel of the project department to formulate the quality prevention measures of the project department according to their own practical experience and combined with the engineering characteristics. After the project starts, we strictly control the construction quality, starting from the foundation and step by step. Template engineering focuses on the control of structural size and support firmness to ensure the accuracy of design size and visual quality. Reinforcement engineering focuses on controlling the binding quality, especially the spacing and position of reinforcement objects.
In the process of construction, I demand that the contents of the company's preventive measures be resolutely implemented, adhere to the model to guide the way, and organize management personnel to visit and study other projects under construction in the project department, so as to foster strengths and avoid weaknesses and improve the quality awareness of the project department personnel. Concrete engineering focuses on controlling the pouring and curing of concrete. Standard pouring and timely maintenance are the fundamental ways to ensure the quality of concrete. During the whole main construction period, we earnestly implemented it. So far, no concrete cracks have been found. After careful control of the project, the whole main project construction meets the design requirements, and the main quality is good, which has been rewarded by xx Real Estate and achieved the expected quality goal.
Second, the project production and schedule control
After the construction of xx Community started, I organized the construction schedule network plan and labor force plan according to the company's requirements. According to the requirements of construction progress, we signed quality, progress and safety control agreements with various construction teams. Specific requirements are put forward for its specific progress and production content. In the production process, according to the actual situation, I made a monthly plan and a weekly plan to control and manage the whole project production. At the beginning of the construction, because the project started late, the labor force was insufficient. In this regard, the project department convened personnel in many ways, and through hard work, the construction requirements were basically guaranteed. In the construction process, considering the large amount of concrete pouring, I adopted the method of on-site pouring and using commercial concrete, which improved the construction progress.
After the subcontracting team entered the construction site, the construction deployment was adjusted in time according to the requirements of xx real estate, which created the construction conditions for the subcontracting unit. By the end of 20xx, the whole project has completed the main works, 40% of the external decoration works and 30% of the internal decoration works. From the whole project progress, there is a lag compared with the original planned construction period. To this end, I took the time to organize the masonry and backfill construction of the lower room during the backfilling and project shutdown in winter. The workload of spring construction in 20xx was reduced, and the smooth delivery of the whole project was ensured.
Three. Safety and equipment management
In the process of construction preparation, I organized the project department to plan and arrange the construction operation area of the whole site according to the goal of provincial civilized construction site. According to the characteristics of the project, make the equipment demand plan and organize the installation. In the process of construction, I insist on safety management as the focus of daily management, and put the safety of employees in the first place. Frame engineering, supporting system and boundary protection are the key points of safety management. To this end, I have strengthened management from the following aspects:
1. Strengthen safety technical disclosure. Strengthen the safety awareness of employees through three-level safety education when entering the site and special safety disclosure when taking up the post.
2. Strengthen safety inspection and patrol, find problems in time, rectify them in time, and put an end to potential safety hazards. Strengthen the safety protection of buildings. At the same time, all the equipment on site is managed by special personnel.
After the equipment comes into play, the project department will conduct unified inspection and acceptance after it is qualified. In the process of construction, the equipment should be repaired, maintained and inspected regularly, and the potential safety hazards should be repaired and replaced in time. During the whole construction period. No major safety accidents occurred, and the general safety accidents were controlled within 65438 0.5 ‰, which ensured the life safety of employees and achieved the expected safety production target requirements.
Four, materials, cost reduction and labor cost management
In terms of material management, according to the construction budget, I organized the construction material demand plan. At the same time, in view of the large number of rental materials outside this project. I have organized various teams and groups to make material use plans and return plans. During the whole construction period, all kinds of engineering materials and instruments were returned in time, and there was no backlog. In the use of materials, I ask everyone to adhere to the quota acquisition system. According to the construction budget, arrange the project manager to count the construction content and quantity of each team in time, and make a comparative analysis with the budget in time to control the material use and labor cost distribution of each subdivisional work. The machines and materials used by each team are required to be collected by each team. The worn materials are allocated according to the budget, and each floor is counted. If waste is found, it will be corrected in time. The turnover materials shall be returned by each team after use, and the teams shall be responsible for compensation for the insufficient quantity.
Five, the shortcomings of the work throughout the year
1. project quality: during the main construction period, the project quality is strictly controlled and relatively good. However, in the construction of infilled wall, due to the relaxation of thought, the concrete pouring of constructional column is not ideal, and there are many water leaks and slurry leaks. This is a lesson for me, reminding myself that the later quality management needs to be further strengthened.
2. Construction progress: Generally speaking, the progress basically meets the requirements of xx. However, compared with other project departments, the progress is slow. We also need to further strengthen the schedule management, sum up the shortcomings, strengthen the human organization, and make up for the shortcomings of the previous construction.
Work plan of intransitive verbs in 2020
In the new year, I will work hard from the following points.
1. Continue to pay special attention to xx project management.
The work of xx project in 20xx is interior and exterior decoration engineering and outdoor engineering. Time is tight and the task is heavy. Considering the requirements of the total construction period, I will continue to pay special attention to the control of construction production progress, actively organize human input, and ensure that the project is completed on schedule and the whole community is delivered on schedule.
2. Strengthen business knowledge learning and continuously improve management level.
With the progress of the times and the application of new technologies, it is necessary to re-educate professional technical knowledge. So in the new year, I plan to strengthen the study of professional knowledge first. Although the foundation is weak and the study is very hard, I believe that as long as I work hard, I will certainly have results. On the other hand, we should actively learn from the advanced points of others, foster strengths and avoid weaknesses, further improve our ideological understanding and broaden our horizons.
3. Further improve the construction management.
In the 20xx years' work, although some achievements have been made in the projects I am responsible for, there are still many shortcomings that need to be summarized and improved. Only by summing up the past well can we serve the future better. In the new year, I will pay more attention to three aspects of management: first, people management. People are the organizers and executors of management, and project managers cannot relax. Only when all the managers cooperate closely and perform their duties, can all aspects of the construction be interlocked and the overall work be orderly. The second is the management of things. That is, material management. In 20xx, I will continue to do a good job in the quota acquisition system in project management, and further refine it, and make a comparative analysis with the project budget on a regular basis to find out the shortcomings and formulate countermeasures. The third is the management of law. That is, the research and management of construction methods. On the basis of the company's preventive measures, combined with the actual characteristics of the project, optimization and improvement were carried out to form a set of effective construction methods to guide the construction and workers' operation.
In short, in the new year, I will further improve myself, research and improve project management methods, and make contributions to the development of the company.
Summary of Project Manager Fan Wen's 2020 Personal Work (II) The intense, busy, rich and unforgettable 20xx has passed, and the 20xx full of expectations has arrived. Looking back on the work of the past year, there are both joy of harvest and insufficient reflection. At the beginning of this new year, it is necessary to calm down and review, sort out and summarize the life, work and study of the past year, and refine the experience and lessons, so as to lay the foundation for the new year to complete this year's tasks better and faster. Now I will report my annual summary to the leaders as follows, and encourage my colleagues.
First, harvest
Speaking of harvest, please allow me to review with you today the xx project site a year ago: soho decoration was completed, the secondary structure of the South Tower was completed by painting the North Tower for small apartments, 60% of the painting was completed by quasi-A, the central business entity started construction, and the hotel was completed to 0.00. Today, one year later: sohox successfully delivered the house on X; Small apartment x month x day smooth delivery; Quasi-a decoration is completed; The image of the central business facade is basically completed except for the 8# building; The curtain wall of the hotel model room is being closed, which is expected to be closed before the Spring Festival. At present, the state is basically in line with expectations except that there is a big lag outside the 8# building. There were no major quality accidents and safety accidents in the whole year, especially the installation quality of small-sized residential buildings has made great progress on the basis of building 2. 10, observed by xx quality supervision station in the city's participating units, and won honor and credibility for xx project and xx brand.
To say that the most influential or symbolic event of xx project in 20xx is the delivery of xx pieces, two delivery nodes were successfully completed this year:
No.30 soho office building 1.x delivery.
2. Deliver the small apartment on X month and X day.
These two events were vividly compared to two of the three fortresses at the mobilization meeting of the engineering department in early 20xx, and their difficulty was predicted and prepared. After the careful organization of all the participants in the project and the concerted efforts of Qixin Qi Xin, it was finally successfully solved. This embodies the hardships and efforts of xx people. These two deliveries of X-special soho, as the first delivery of the commercial complex project, are of great significance. First, it is the inspection and assessment of the hard work of all the staff of this project in the past three years; Secondly, as the first delivery of commercial complex, it provides us with the experience and foundation of continuous summary and continuous improvement; Thirdly, the smooth delivery of the house provides guarantee and support for the brand promotion and publicity of the project brand group.
Of course, I clearly understand that these achievements are not my personal achievements, but the achievements of all participants in the project, especially the results of sincere cooperation, reasonable division of labor, overall management, giving full play to the role of project management carrier and hard work. Here, on behalf of the project department, please allow me to express my heartfelt thanks to several comrades for their unremitting efforts in the past three years. They are: enthusiastic and responsible XX; Steady and inclusive xx; XX full of enthusiasm and vitality; Hard-working ox xx; Dedicated, cautious, pragmatic and low-key XX; Hard-working and individual team leader, Manager X, please allow me to say thank you in my own name, brothers. Without your efforts, there would be no xx today.
Second, growth.
If the above achievements belong to everyone and are the result of the efforts of all my colleagues in the project, then growth is more a reflection of my personal psychological state. Growth is not only a result, but also a state, constantly learning and improving mental outlook and state.
Let's start with reading. My daughter and I studied the Amethyst and Disciples Rules together. I am familiar with the Art of War, and even try to recite her. Studying Zeng Guofan is, in short, a book. Challenge the self-limit, take part in the xx Marathon on xx, xx, XX, 20xx, complete the men's half-way 2 1 km, and score 1 hour 56 points. I also attended a social reading club and listened to inspirational radio programs on my way off work, which seems to have little to do with my work, but it reflects my mental state of longing for learning, progress and growth. I even attended xx's speech at my own expense this year, and really realized what Mr. X said to help more people realize their dreams, and my dream is the realm of realization.
When I first heard this sentence, I thought it was a big talk or a slogan. Through continuous learning and understanding, I realized the truth of life, and I really understood the practical significance of helping more people grow up. Therefore, I constantly practice this concept in my work, helping, driving and influencing colleagues around me while making personal progress and growth. I believe that only when everyone makes progress and makes achievements can our team work make achievements. This is my philosophy of life, and it is also the direction of my constant efforts.
If the above is personal study, an experience in the last x months is an exercise for me. Last year 10, the company assigned me to be in charge of the overall work of the project. This experience is so great for my exercise, influence and harvest that it even exceeds the sum of the gains at other times of the year, so I can't help but mention it. First of all, I thank the organization for its trust in me, which provided me with a platform and opportunity to exercise myself, show myself and improve myself. During the period, I experienced the acceptance and delivery of soho office buildings; Late decoration, curtain wall and installation of small apartment compete for construction period and acceptance; Decoration, installation and large-scale development of quasi-A office building; Interpolation construction of central business insulation, curtain wall, civil engineering and installation; The main building of the hotel.
To this end, I have devoted great energy to the management deployment, coordination and cooperation of the whole project. Especially during the time when 10 grabbed the construction period for small apartments, I can't remember how many nights I stayed at the construction site until eleven o'clock. I haven't even said a word to my daughter for a week, even though I go home every night. When I got home at night, my daughter was already asleep. When I went to work in the morning, I left home, and my daughter still didn't wake up. During this period, I deeply realized the responsibility, pressure and motivation as a project manager. And from it, I have learned a lot of life truths: I have deeply realized that I have less gains and losses and more responsibilities; Complain less and do more practical things; The practical significance of complaining less and being grateful more has gradually deepened and strengthened the understanding and understanding of the corporate culture of Greenland. Through three months' hard work and dedication, I have gained great exercise and improvement, and won everyone's recognition to some extent.
This experience has brought me too many gains and positive effects. Please allow me to express my sincere thanks to the leaders and colleagues who care about and support me. Thank you for your concern and love for me. I will take this as the driving force, continue to work hard with higher enthusiasm, stronger sense of responsibility and greater efforts, and make greater contributions to our green space cause.
Third, the shortage.
Although we have gained a lot in 20xx, we have gained a lot, but we also have many shortcomings.
First, although this year's tasks have been basically completed, there is still a certain lag in different degrees, indicating that progress management still needs to work hard and continue to tap the potential. In particular, the civil construction progress of the 8# building is lagging behind, and no effective remedial measures have been found, resulting in the late construction period of the 8# building being too tight.
Second, the relationship between schedule and quality assurance has not been properly handled. The whole construction period of 20xx is very tight, especially the south tower of Building No.3, which will resume work after the Spring Festival1October 20th. It takes only half a year from painting, curtain wall construction to decoration completion, and it is very difficult to coordinate the management of cross-construction, multi-discipline and multi-job. In the process of catching up with the construction period, too much attention was paid to the progress, which caused some sacrifices in quality to a certain extent, which led to being used as a negative teaching material in the later delivery and acceptance process and criticized by the company leaders.
Third, the progress management is greatly influenced by the quality and cooperation of the construction unit. For example, the lack of effective management methods and measures in the second construction site and poor sense of responsibility in management cooperation led to the main construction period of Building 8 being nearly one year, which led to a very tight overall construction period of 20xx in the later period. As a project department, it is suggested to introduce the elimination of competition mechanism when determining the team in the future, and also to summarize and reflect on its own management. According to different units, different effective management methods and measures should be taken to minimize the negative impact of the quality of construction units.
Fourthly, the role of the project department as a carrier of project management needs to be strengthened and improved.
As the carrier of project management, engineering department should play a leading role in overall management and coordination, but there are still the following deficiencies in current management:
1. There are unreasonable overlapping processes in different blocks. 1# building skirt building decoration failed to learn from the failure case of building 2, because the skirt building decoration team entered the site late, which delayed the construction period of the whole project.
2. The lack of coordination, unity and foresightedness between disciplines leads to unnecessary rework in site construction. For example, in order to ensure that the construction of fire fighting and air conditioning pipes will not affect the construction of fine decoration, most of them have been completed before the decoration comes into play. At the beginning of the decoration, it was found that many places did not meet the decoration requirements, which would cause rework for the decoration effect.
3. The engineering department has integrated the resources between the contract department and the technical department, and the efforts of unified coordination are not enough, which needs to be strengthened. Especially in the decoration stage, when the progress is affected by the plan and expenses, the project cannot be effectively coordinated and solved at a high speed in the first time.
Fourth, plan
Look before you leap. For the smooth development of next year's work, combining the project with your own reality, the plan is as follows:
1. Take schedule management as the starting point, closely focus on the inverted plan of core delivery nodes, and plan ahead. Two core target nodes for next year: quasi-A on X, X and X and central commercial launch; The hotel was put into trial operation on X day, and its tension was by no means normal. Therefore, it is necessary to make full use of the time before the Spring Festival to make detailed arrangements and improve the 20xx plan, especially the reasonable overlap of work procedures, technical preparations and the intervention time of external supporting units, which should be accurately reflected in the annual plan and copied to relevant departments to ensure the implementation and execution of the annual plan.
2. The process of strengthening quality and safety management. It has been more than three years since XX, and no major quality and safety accidents have occurred in the project department, which is inseparable from the efforts of the project participants. The more in the last year, the more attention should be paid to safety work, to ensure the occurrence of zero casualty accidents, to write a wonderful chapter for the safety management of xx, and to ensure the construction quality to a new level on the basis of each delivery.
3. Strengthen the construction of project team, and strive to build a first-class project team with first-class personal quality and ability. While strengthening project team cooperation, we should pay attention to the study and improvement of individual quality and cultivate outstanding talents for the group's leap-forward development.
4. Strengthen communication and coordination between horizontal departments, especially with technical department and contract department, give full play to the carrier role and leading role of project management, make technology and contract better serve the project, minimize unnecessary internal friction, and promote faster and better development and construction of the project.
5. Continuously improve personal business ability and management level. Guided by the spirit of never being satisfied, constantly seeking change, never stopping, striving for first-class xx enterprise, and aiming at the personal three-year plan, we will continue to learn, improve and make progress, and make greater contributions to the development of the enterprise.
Project Manager Fan Wen's Personal Work Summary 2020 (III) I joined xx Group Real Estate Company on xx, xx, and worked as a project manager at the project site of xxXX Department Store on XX, XX, and it has been more than three months. During these three months' work, with the strong support and guidance of the group real estate company, the project department has overcome many difficulties and it is extremely difficult to get to today. At present, the site is in the piling stage, and 46% of the pile foundation construction tasks have been completed. Although the next construction task is extremely arduous, I still have confidence and ability to complete the construction period of each stage. Next, I will make the following report on my work in the past 20xx years and three months and my work plan for the next year:
First, the preliminary construction preparation stage
As an investment promotion project in xx county, the xxxx department store project can basically get government support and help as long as it is conducive to the construction progress. However, before the smooth start of construction, the following work must be completed.
1. Basement control sideline lofting.
2. Building alignment.
3. The planning department should conduct line inspection.
4. Submit the leveling points and coordinate control points provided by the surveying and mapping department to the general contractor.
5. Organize the construction drawing design disclosure of foundation pit support and the blue prints.the design twice.
6. Pile foundation construction drawing design disclosure and blue prints.the design.
7. The planning department shall provide the drawings of municipal pipelines around this project.
8. Assist to complete the expansion of temporary electricity consumption on the construction site.
9. Before construction, go through the quality supervision procedures at the quality and safety station.
Second, the construction stage
Before piling construction, the foundation pit earthwork has been dug to a depth of about two meters and five meters. Because there were no construction drawings at that time, most places were not excavated in place. Considering that there are enough working faces in the surrounding row of piles, it is necessary to cooperate with the earthwork excavation unit to dig out the remaining soil. For a long time, the earth excavation unit didn't cooperate with our work arrangement, kept antagonistic feelings with us, and even made trouble at the construction site, so the construction site work could not be carried out at the moment. Through our patient and meticulous communication, we learned the unit price of earthwork excavation in other local sites, and finally reached an agreement with the earthwork excavation unit through rewards.
After the foundation pit is excavated for 2.5m, it will have a great impact on the site piling. The concrete truck can't drive into the construction site at all, and the surface of the foundation pit is covered with silt. Once it rains, the bearing capacity of silt layer drops sharply, and piling construction is very difficult. The general contractor will use this as an excuse that there is no condition of three links and one leveling on the construction site, which leads to claims for expenses and time limit. We made a decisive decision and actively organized the local construction unit to backfill the pond slag in the site, which ensured the need of piling construction in the site.
The hardest part is actually in the beginning After three weeks at the site, the general contractor still hasn't arranged for the pile driver to enter the site. It is also true that the general contractor has not received the formal construction drawing of pile foundation provided by us, which is not convenient for organizing machinery to enter the site. However, after we provided the blueprint of pile foundation construction on X, the general contractor still failed to enter the pile frame. The general contractor encountered great difficulties in finding subcontractors, and found more than a dozen units back and forth, but they were unwilling to undertake this business. It was not until x, x, that several piles were successively entered. The trial pile construction of the podium and the tower began on X, and the trial pile construction of the podium was successful, but the tower ended in hole collapse after six days of trial drilling. The tower pile must enter the rock 1.5 meters, and the circulating drilling rig encounters pebbles with large particle size in the sandy pebble layer (the largest pebble collected on site is close to 40 cm), which is easy to block the pipe.
Later, with the consent of the design unit, the tower recycling hole-forming process was changed to impact hole-forming process, and the general contractor organized six impact hammer drills to enter the site on X day, and first tried holes on the north side of the tower, but the soil layer on the north side was about three meters of quicksand. When lifting the hammer, the heavy hammer, quicksand and casing are pulled up together, which makes it very difficult to form a hole. Considering not to delay the construction period of the tower pile foundation as much as possible, the pile test construction will be started on the south side of the tower, and the pile test will be started on X day, X month and X day to complete the first concrete pouring. However, due to the limited working face on the south side of the tower, only four piles can be placed for construction. At the same time, we have not given up our efforts on the north side of the tower. After consulting various experts, we put forward some suggestions, such as dewatering first, and then arranging piling construction. The general contractor has successively carried out well point dewatering, shallow tube well dewatering, grouting and other strengthening foundation construction technologies, but none of them have achieved the required results. Geological factors on the north side affect the construction of about 60 pile foundations, and together affect the construction of about 70 uplift piles in the surrounding pure basement. The next step will be deep well dewatering, and then piling construction will be arranged.
The podium pile foundation construction task has been completed, including 57 towers and 1 15 pure basement piles, with a total of 349 piles (46%).
Three. 20xx work plan arrangement
The progress of pile foundation construction is lagging behind, and the main work in the next stage is to arrange work around earthwork excavation to ensure that the basement floor pouring is completed before the flood season. Main work arrangements
1.20xx month x day comes into play and starts digging.
2. Piling (including retaining piles) will be completed before the end of 20xx 1, but the next stage of piling construction and foundation pit retaining construction will not affect earthwork excavation. 20xx Earth excavation will be completed before March 20th, and the basement will be started in early March of 20xx, and completed on April 15.
3.20xx The concrete structure below 0.000 shall be completed before the end of xx.
4.20xx Complete the concrete structure of the podium before the end of August.
The tower will be capped before the end of 5.20xx.
6. Electromechanical installation, curtain wall construction, secondary structure construction and fine decoration construction are carried out in the main structure construction.
Four, the current need to coordinate other work.
1. Provide a full set of construction drawings, and examine and approve the construction drawings.
2. Determination of subcontractors such as fire protection, HVAC, weak current, hardcover, curtain wall and elevator.
3. Determine the brand information provided by Party A and Party A. ..
In the new year, I will work hard from the following points.
1. Continue to do a good job in the project management of xxxx department store: the work of 20xx is the main structure, electromechanical installation, curtain wall engineering, fine decoration, etc. Time is tight and the task is heavy. Considering the requirements of the total project duration, I will continue to control the progress of the project to ensure that the project is completed and the whole project is delivered on schedule.
2. Strengthen business knowledge learning and continuously improve management level: With the progress of the times and the application of new technologies, we must learn professional technical knowledge and management knowledge to improve our management coordination ability. Continuously improve the professional skills of subordinate employees to ensure that the quality and progress of on-site construction are effectively controlled.
3. Further do a good job in site management: In the 20xx years' work, although some achievements have been made in the projects I am responsible for, there are still many shortcomings, which need to be further summarized and improved. Only by summing up the past well can we serve the future better. In the new year, I will pay more attention to three aspects of management:
The first is the management of people. People are the organizers and executors of management, and project managers cannot relax. Only when all the managers cooperate closely and perform their duties, can all aspects of the construction be interlocked and the overall work be orderly.
The second is the construction schedule management. Always track the site construction progress, find problems, and immediately communicate with the construction unit to ensure that the weekly, monthly and annual progress plans are completed on time.
The third is cost control management. Although the construction unit will not take the initiative to consider the project cost when settling accounts with the construction unit according to the quota, even the more cost investment, the better the construction unit will be. However, as the on-site management personnel of Party A, it should belong to the expenses borne by the construction party, and there will be no additional visas, and everything will be settled according to the quota.
In short, in the new year, I will further improve myself, research and improve project management methods, and make contributions to the development of the company.