1. Be responsible for the operation inspection, maintenance and repair, live detection, hidden trouble investigation, routine elimination of defects below 3m and line channel protection of distribution network equipment under its jurisdiction.
2. Patrol the distribution automation devices attached to the line, maintain the information data of the distribution equipment, evaluate the status, collect and report the status information of the line, accept new, modified and expanded projects, and be responsible for the data maintenance of the transportation inspection information system.
From this point of view, the inspection of distribution operation is still dangerous, but it is safer than substation operation.
Extended data
Engineering requirements for distribution operation inspection of power supply company
1. The construction unit shall carry the bid-winning notice, project management documents, technical measures of construction organization and construction drawings to the relevant departments of the company for the commencement permit, and sign and seal the project management documents.
2. Before the project construction, the relevant project management units shall conduct comprehensive safety technical measures training for the construction.
3. During the project construction, the construction unit shall earnestly implement various safety measures and issue relevant working tickets; For construction that does not involve power failure, the construction unit shall issue a line construction operation ticket, which will take effect after being approved by the operation unit. It is forbidden for the construction unit to operate without a license.
4. The project construction unit shall strictly follow the design and construction, and shall not arbitrarily change the design scheme. If it is necessary to make changes, the design and relevant management departments shall agree in advance, and the design unit shall issue design change procedures.
5. The project construction is carried out in strict accordance with the process and quality standards, and it is forbidden to cut corners. Relevant management departments of the project shall conduct irregular inspections during the construction of the project and fill in this management document.
6. After the project is completed, the project construction unit shall apply to the competent engineering department for acceptance, and the engineering management department shall organize and coordinate the relevant departments of the company to participate in the project acceptance.
7. The project acceptance shall be carried out in strict accordance with the items listed in the management documents of power distribution project, and the management documents shall be filled in by the acceptance person. The construction unit shall promptly deal with the problems found in the on-site inspection or acceptance according to the rectification opinions, and the inspectors or acceptance personnel shall closely follow up and review them to ensure the effectiveness of the acceptance.
8. After the project is accepted, the relevant departments of the company shall sign and seal the project management documents.
References:
Ningyang County People's Government-Ningyang County Power Supply Company State Grid Ningyang County Power Supply Company of Shandong Province Institutional Functions