What does the project commissioning in the construction contract mean?
The project debugging in the construction contract refers to the trial operation of the equipment, circuits, pipelines and other systems of the completed project to see whether they work normally and meet the design requirements. There are mainly single machine debugging, linkage debugging, no-load debugging and on-load debugging, which are different debugging methods according to different requirements.

Engineering debugging scope:

If both parties agree that trial operation is needed, it shall be organized, and the trial operation content shall be consistent with the installation scope contracted by the contractor.

1, single machine no-load test run, single machine no-load test run.

2, linkage no-load test run the whole set of equipment or multiple devices together for no-load test run.

3. Trial operation shall be carried out according to the normal working mode.

Extended data:

First, the project debugging process and matters needing attention

1. If both parties agree that trial operation is needed, the trial operation content shall be consistent with the installation scope contracted by the contractor.

2. Equipment installation works meet the conditions of single machine no-load trial operation. The contractor shall organize the trial run and notify the engineer in writing 48 hours before the trial run. The notice includes the content, time and place of trial operation. The contractor shall prepare the trial run record, and the employer shall provide necessary conditions for the trial run according to the requirements of the contractor. If the test run is qualified, the engineer will sign the test run record.

3. If the engineer can't attend the trial run on time, he must apply to the contractor for an extension in writing 24 hours before the trial run, and the extension shall not exceed 48 hours. If the engineer fails to put forward the extension request according to the above time and does not participate in the trial operation, the trial operation record shall be acknowledged.

4. The equipment installation works meet the no-load linkage test conditions. The Employer will organize the trial run and notify the Contractor in writing 48 hours before the trial run. The notice includes the contents, time, place and requirements of trial operation, and the contractor shall make good preparations as required. If the test run is qualified, both parties shall sign the test run record.

Second, the responsibilities of both parties.

1. If the commissioning fails to meet the acceptance requirements due to design reasons, the Employer shall require the design unit to modify the design, and the Contractor shall reinstall it according to the modified design. The Employer shall bear all expenses for design modification, dismantling and reinstallation and the additional contract price, and the construction period shall be postponed accordingly.

2. If the test run fails to meet the acceptance requirements due to equipment manufacturing, the buyer of the equipment shall be responsible for re-purchasing or repairing, and the contractor shall be responsible for dismantling and reinstalling. If the equipment is purchased by the contractor, the contractor shall bear the cost of repairing or re-purchasing, dismantling and re-installing, and the construction period shall not be postponed; If the equipment is purchased by the employer, the employer shall bear the above additional contract price, and the construction period shall be postponed accordingly.

3. If the test run fails to meet the acceptance requirements due to the contractor's construction, the contractor shall reinstall and test run according to the requirements of the engineer, and bear the expenses of reinstallation and test run, and the construction period will not be postponed.

4. Commissioning expenses shall be borne by the Employer, unless it has been included in the contract price or otherwise agreed in the special terms and conditions.

5. After the trial run, the engineer will not sign the test record. After 24 hours of trial operation, it is deemed that the engineer has approved the trial operation record, and the contractor can continue the construction or go through the completion formalities.

6. After the project is completed and accepted, it will be debugged by the Employer. If the Employer requires it to be carried out before the project completion acceptance or needs the cooperation of the Contractor, it shall be approved by the Contractor and a supplementary agreement shall be signed separately.