Current location - Quotes Website - Collection of slogans - Key points of safety production control in ready-mixed concrete mixing station?
Key points of safety production control in ready-mixed concrete mixing station?
In order to ensure the company's safe production, further enhance the safety awareness of all employees, and ensure the smooth progress of the company's production, the Safety Production Control Point is specially formulated, and all departments, teams and all employees must conscientiously implement it.

1. Key points of fleet safety control:

1. 1 Strictly control the speed, slowly respond to changes and ensure safety;

1.2 According to the characteristics of winter climate, there are many rainy, snowy and foggy days, and the roads are slippery and icy. Drivers should drive carefully, start slowly and stop slowly, and keep a safe driving distance;

1.3 Before starting and reversing, be sure to get off the vehicle and observe the surrounding obstacles to prevent accidents, especially when driving at night and reversing.

1.4 After completing the task every day, when parking, turn the water tank upside down, drain the water in the water tank, drain the water in the storage tank, start the water pump or open the air valve to drain the water in the road to prevent freezing accidents;

1.5 strictly implement the regulations on waiting temperature of vehicles in winter, and it is forbidden to open the tank before the engine temperature reaches the starting temperature;

1.6 when cleaning vehicles in winter, it is easy to freeze on the pedal, so pay attention to anti-skid when getting on and off to prevent falling accidents;

1.7 It is forbidden to add water to the mixing tank in winter construction. If it is really necessary to add water, it must be approved by technicians to prevent concrete quality accidents.

2, maintenance class safety control points:

2. 1 all employees firmly establish the idea of safety first, and must achieve "three noes" when carrying out maintenance operations, that is, do not hurt themselves, others or be hurt by others during the operation;

2.2 Before entering the mixer, you must cut off the power supply, lock the electrical cabinet, hang up warning signs, and give the key to the operator who enters the machine for safekeeping before entering the machine. It is forbidden to enter the machine with electricity.

2.3 When maintaining the belt conveyor, the power supply must be cut off, the power distribution cabinet should be locked, and the key should be kept by the maintenance personnel. When it is really necessary to check and adjust the operation, two people must be present during the operation and take preventive measures. Single operation is strictly prohibited;

2.4 when working high above the ground, you must fasten your seat belt, especially when working in the powder bin, otherwise you are not allowed to work;

2.5 The maintenance electrician shall check the circuit switches and distribution boxes of the company's on-site electrical facilities once a month, and make timely rectification when problems are found, and make records of inspection and rectification. It is forbidden to connect the power supply in the dormitory and office to prevent electric shock accidents.

3, concrete pumping construction safety control points (tow pump, car pump operators)

3. 1 Wear safety helmet when entering the construction site, and be alert to falling objects in the air at any time to prevent accidents;

3.2 The concrete pump truck and concrete towed pump must be supported on a solid ground, and the pump can only be supported after careful observation of the construction site and understanding of the solid ground. When supporting the pump, you need to pad the support legs. When supporting the pump near the pit and slope, leave enough safe distance.

3.3 When the concrete pump truck is pumping, the operators (drivers and pump workers) should always observe the changes of the ground of the sub-pump, and take decisive measures to stop the pumping operation if any abnormal situation is found. Before operation, immediately close the boom and pump again;

3.4 When the concrete pump truck enters the construction site, it is necessary to observe the wires and cables within the operation scope, understand the line voltage, and ensure whether the minimum safe distance is reached according to different voltages (Note: 0-lkv shall not be less than LM; L- 10kv is not less than 3m, l 10-220/kv is not less than 4m, 220-400kv is not less than 5m, and when the voltage is unknown, it is not less than 5m. -

3.5 Transfer the concrete towed pump, and the maximum speed of the concrete mixer driver towing the pump on the construction site shall not exceed 8 km/h;

3.6 The pumpman of the concrete tow pump must check the tire pressure of the tow pump, the distance between the safety pin of the leg and the ground of the guide wheel, wear the safety pin of the tow hook and fasten the safety wire rope after hanging it. Assist and direct the driver to arrive at the construction site safely.

4. Safety control points for receiving personnel in the parking lot:

4. 1 you must stand on the left side of the car and command from the position where the driver can observe. It is forbidden to direct a car behind or in front of it.

4.2 When getting on the bus to check the aggregate, it is necessary to wait for the skip to stop and the driver to leave the cab before getting on the bus for inspection. It is forbidden to ride on the pedal out of the parking lot.

4.3 When checking the material level of the powder bin, you must wear a safety helmet and be alert to falling objects in the air.

5, auxiliary cleaning mixing equipment safety control points:

5. 1 Clean the mixing host, cut off the power supply in advance before entering the host, lock the power distribution cabinet, and keep the key by the personnel entering the host. It is forbidden to enter the host when the host is charging;

5.2 When cleaning the unloading hopper of the main engine, choose a suitable wooden cross arm to enter the unloading hopper in advance, and the cleaning personnel must fasten their seat belts when entering the unloading hopper to prevent the pit from falling in the air;

5.3 When cleaning the pulley, the cleaning tools and operators used must conform to the general cleaning of pulley rotation. It is forbidden to use cleaning tools in the opposite direction to prevent injuries caused by improper operation.

6, the guard on duty safety control points:

6. 1 Strictly implement the visitor registration system, distribute the visitor list, and prohibit other personnel from entering the company site;

6.2 If the mixing station does not produce at night, the doorman should close the door and inspect the factory every hour to prevent public security cases such as theft.

7, the company personnel on duty safety control points:

7. 1 Be on duty at night, and check the working conditions of personnel in each position every 2 hours;

7.2 The personnel on duty should know about the production and safe operation, deal with the emergency in production in time, and ensure the smooth progress of production.

8, inspector safety control points:

8. 1 When climbing the car, going to the mixing workshop and going to the construction site, pay attention to anti-skid, and it is forbidden to jump off the car and wear high heels and flat shoes;

8.2 To the construction site, you must wear a hat.

9, loader safety control points:

9.65438+

9.2 When working in winter, clear the snow and ice on the vehicle in time, and pay attention to anti-skid when getting on and off the vehicle; Prevent people from falling off the car and causing accidents. Drain the water in the car when the temperature is below zero, and run for 1-2 minutes to ensure the water is drained.

10, canteen safety control point:

10. 1 Strictly implement the food management system, and clean the operation room once a day and once a week to ensure the hygiene of the canteen meets the requirements.

10.2 it is forbidden to purchase expired food, sell spoiled food and mix raw and cooked food with knives. Must be classified management and storage, check once a day. When problems are found, they should be rectified immediately.

10.3 canteen staff must be checked by the hospital or epidemic prevention department to meet the requirements, hold relevant certificates, and re-check at least once every six months. Do not meet the conditions, shall not be employed.

10.4 canteen staff should wear clean work clothes, working caps and masks when operating, the operating platform should be clean, and the canteen should be clean to prevent food poisoning.