How to write the supervision opinion on the application form for project payment
Legal analysis: 1. Just tick "Agree" and "Disagree" in the measurement payment application form. If you choose "Disagree", please write down a brief reason in the explanation below. This form is signed and dated by the chief supervision engineer;

2. Measurement and payment table and summary table of quantities. There is a column of "Chief Supervision Engineer" at the bottom of these two forms, and there is no need to sign opinions;

3. In the bill of quantities, there is a column entitled "Calculation Results of Professional Supervision Review", which shall be signed by the professional supervision engineer.

Legal basis: People's Republic of China (PRC) Construction Law.

Fourteenth professional and technical personnel engaged in construction activities shall obtain the corresponding professional qualification certificate according to law, and engage in construction activities within the scope permitted by the professional qualification certificate.

Thirty-second supervisors found that the engineering design does not meet the quality standards of construction projects or the quality requirements agreed in the contract, they should report to the construction unit and ask the design unit to correct it.

Article 35 If a project supervision unit fails to perform its supervision obligations as agreed in the entrusted supervision contract, or fails to inspect the project that should be supervised or inspected in accordance with the regulations, thus causing losses to the construction unit, it shall bear the corresponding liability for compensation.