Current location - Quotes Website - Personality signature - Does the construction unit need to sign and seal the examination and approval procedures for the special construction scheme of the building project? Where is the specific basis for this provision?
Does the construction unit need to sign and seal the examination and approval procedures for the special construction scheme of the building project? Where is the specific basis for this provision?
Need; Safety management measures based on dangerous partial projects.

According to Article 12 of the Measures for Safety Management of Divisional and Sectional Projects with Greater Danger, the construction unit shall revise and improve the special scheme according to the demonstration report, and can organize the implementation only after the technical director of the construction unit, the chief project supervision engineer and the project director of the construction unit sign it. The implementation of the general construction contract shall be signed by the technical director of the general construction contractor and the relevant professional contractors.

If the special scheme needs major revision after demonstration, the construction unit shall make revision according to the demonstration report, and reorganize the experts for demonstration. The construction unit shall organize the construction in strict accordance with the special plan, and shall not modify or adjust the special plan without authorization. Due to changes in design, structure, external environment and other factors, it is really necessary to modify the special plan, and the revised special plan shall be re-examined in accordance with the provisions of Article 8 of these Measures.

Extended data:

Relevant requirements for examination and approval of special construction scheme are as follows:

1. The design unit shall consider the needs of safe operation and protection in construction, indicate the key parts and links involved in construction safety in the design documents, and give guidance on preventing production safety accidents.

2, the project supervision unit in the process of supervision, found that there are hidden dangers of safety accidents, it shall require the construction unit to rectify; If the situation is serious, the construction unit shall be required to temporarily stop the construction and report to the construction unit in time. If the construction unit refuses to rectify or stop the construction, the project supervision unit shall report to the relevant competent department in time.

3, in the construction site installation, demolition of construction hoisting machinery and overall lifting scaffolding, templates and other jack-up erection facilities, must be borne by the unit with corresponding qualifications.

Shunde District People's Government-Measures for the Safety Management of Divisional and Sub-divisional Projects with Greater Danger