Construction Safety Responsibility Letter (1)
Party A: (hereinafter referred to as Party A) Party B: (hereinafter referred to as Party B)
According to relevant national safety regulations , combined with the actual situation of our company, conscientiously implement the "61" order and the policy of "safety first, prevention first" and the principle of "who is in charge, who is responsible" and "production must focus on safety", implement the safety responsibility system, and ensure that To ensure construction safety and prevent accidents, Party A and Party B must fulfill the following terms:
1. Party A will fully cooperate with the safety and security work of this project, and at the same time supervise and inspect Party B’s safety and security work, and conduct inspections Party B has the right to require Party B to make rectifications for violations, violations, and safety hazards discovered.
2. Party A shall notify Party B in writing of any problems discovered during the inspection as required by the company and keep them on file for future reference.
3. Party A has the right to punish Party B for the “three violations” in accordance with relevant management regulations.
4. Party A should promptly report the behavior of ignoring the safety management of the decoration project to the company for handling.
5. Party B must have a clear legal safety responsible person, who is responsible for the safety and public security of the construction project, and achieves "five simultaneous" construction and safety.
6. Before entering the construction site, Party B must handle registration and access permit procedures for construction workers, and designate a dedicated person to carry out inspections. No one without a permit is allowed to enter the construction site.
7. Party B must be responsible for providing safety education to construction personnel before taking up their posts, clarifying relevant safety regulations and work requirements, and consciously abiding by the safety management system.
8. Party B must have full-time or part-time security officers during the construction, who are specifically responsible for implementing safety and security precautions during the construction.
9. The flammable, explosive and dangerous goods used by Party B during construction must be limited and a designated person shall be designated to be responsible for safety management.
10. Party B’s use of fire, electricity, and welding during construction must be approved by Party B’s on-site person in charge, and the technical specifications and operating procedures for fire, electricity, and welding must be strictly implemented to ensure nothing goes wrong. (Oxygen bottles and acetylene bottles must not be turned upside down, and have shock-absorbing rings. The number used is strictly controlled. The distance between them should be greater than 5 meters, and the distance between open flames and acetylene bottles must be greater than 10 meters. There are dedicated personnel to eliminate flammable materials, and fire extinguishers are placed on site. Leave someone on duty and confirm that there are no problems before leaving)
11. Party B’s electricians and electric (gas) welders must have a valid "Special Industry Personnel Operation Certificate" issued by the labor department before they can operate at the construction site. Implement operations as required by the specification.
12. Party B must strictly carry out construction in accordance with the national industry safety construction regulations for construction and decoration, and resolutely put an end to the "three violations".
13. When Party B uses large-scale equipment during construction, it must fully consider the load-bearing and earthquake-proof capabilities of the floor, and it can only be used under the premise of ensuring safety. Illegal command and risky operations are strictly prohibited.
14. Party B must erect safety nets for dangerous holes during construction (passage entrances, elevator entrances, reserved entrances, stairwells, etc.), and must tie safety ropes when working at heights.
15. Smoking, using open flames, leaving construction workers behind, and using electric water heaters are strictly prohibited in the decoration area.
16. It is strictly forbidden to pile up large amounts of waste materials in the construction area for a long time and block evacuation channels. They must be removed once a day. In particular, empty bottles such as glass glue and paint must be properly disposed of.
17. Party B must strictly manage the construction site, and designate a dedicated person to be responsible for the safety management of construction site equipment, equipment, tools, and materials.
18. Party B must equip fire-extinguishing equipment that meets specifications and standards at the construction site to ensure the safety of the entire construction process.
19. If Party B neglects safety and security management or violates the provisions of the contract and causes accidents or cases, Party B shall bear full responsibility. Party B shall bear all the economic losses and political impacts caused to Party A.
20. This letter of responsibility will take effect from the date of signature and will expire after the project is accepted and accepted. It is made in duplicate, with the owner and the construction unit each holding one copy.
Party A: Party B:
Representative’s signature: ? Representative’s signature:
Project supervisor’s signature:
Year, month, day, year, month, day
Construction Safety Responsibility Letter (2)
In order to ensure fire safety during the construction process and prevent fires, in accordance with the "Fire Protection Law of the People's Republic of China" and the Ministry of Public Security's " "Regulations on Fire Safety Management of Agencies, Groups, Enterprises and Institutions", this responsibility letter is specially formulated and the construction unit and specific responsible person are identified as the person responsible for fire prevention in the construction area. Their responsibilities are as follows:
1. The construction department (or unit) is responsible for fire safety at the construction site. During construction, fire regulations and industry regulations must be strictly observed, illegal command and illegal operations are strictly prohibited, and violations of labor disciplines must be prevented. The security department of the construction unit is responsible for supervising and inspecting the fire prevention person in charge of the construction party to do a good job in fire safety work, and the construction party must cooperate seriously.
2. The equipment used in construction must comply with fire safety regulations, strict fire prevention measures are required, and illegal operations are prohibited. The power supply must be turned on with the assistance of the construction unit's electrician.
3. When using open flames at the construction site, approval procedures must be completed in advance, and operations can only be performed after approval. Electrical and gas welding workers must hold certificates to work. The fire site must be equipped with necessary fire-extinguishing equipment and have designated personnel to supervise and remove surrounding combustibles. After the fire is over, it must be carefully inspected and any remaining fires must be completely extinguished.
4. When using gasoline, paint stripper and other flammable items during construction, safety regulations must be followed. Flammable materials must be stored in a special warehouse and kept by designated personnel. Flammable and explosive materials must not be stored at the construction site.
5. Paint strippers and other flammable liquids are not allowed to be used on large areas during construction, and spray painting operations are not carried out on site as much as possible. If it is necessary to spray paint on site, good ventilation and measures to prevent open flames must be provided.
6. The use of flammable and explosive chemicals in construction should be limited and should be collected as needed; () It is prohibited to pack and season in the workplace; it is prohibited to use liquefied petroleum gas cylinders and acetylene at the construction site Generator etc.
7. If the project construction affects the function of the original fire-fighting facilities and fire-fighting equipment, it must be reported to the fire protection supervision agency for approval in advance and effective measures must be taken.
8. Construction materials and garbage shall not occupy fire-fighting facilities, occupy fire-fighting passages, or block evacuation passages such as corridors and stairs.
9. Provide fire safety education and escape and self-rescue skills training to all construction personnel of the unit, so that they can master and use the equipped fire protection facilities and equipment. Internally
10. Fire protection work during the construction process must be frequently inspected and summarized regularly, and at the same time accept inspection and supervision by the fire protection supervision agency.
11. In the event of a fire, we must actively organize firefighting, organize and guide the evacuation of people present, and obey the unified command of the on-site commander.
12. After the fire is extinguished, protect the fire scene and assist relevant departments in investigating the cause of the fire.
14. This letter of responsibility shall take effect from the date of signature until the project is completed and the construction unit leaves the site.
15. This Letter of Responsibility is made in duplicate, with each party holding one copy.
Construction unit: Construction unit:
Person in charge: Person in charge:
Year, month, day, year, month, day
Construction safety responsibility letter (3)
In order to implement the policy of "safety first, prevention first", clarify the safety responsibilities of both parties, effectively strengthen construction project management, and ensure the safety of people, power grids and equipment during construction, in accordance with relevant national laws regulations, both parties signed this agreement through consensus.
Article 1 Party A: Fuzhou City Passenger Terminal Operation Co., Ltd.
Article 2 Construction Project: Signing Time:
Article 3 Validity Period 20XX From June 20XX to June 20XX
Article 4 Safety Responsibilities of Party A
1. Party A has the obligation to assist Party B in safety production, fire prevention management and supervision and inspection.
Party A has the right to inspect and urge Party B to implement work regulations related to safety production, stop and correct Party B's behavior that does not comply with safe and civilized construction, and issue safety rectification notices until it is cleared from the site. If you fail to comply with the rectification three times, you will not be allowed to take on our company's business in the future.
2. Party A has the right to conduct random tests on Party B’s personnel involved in construction on safety technical knowledge and safety work procedures.
3. Party A shall not require Party B to carry out construction in violation of safety management regulations. Party A shall be responsible for accidents caused by Party A.
Article 4 Safety Responsibility of Party B
As the contractor of the project, Party B shall bear safety responsibility for personal injuries and equipment damage accidents that occur during the construction process. Party B shall earnestly fulfill the following safety responsibilities:
1. The relevant qualification certification materials required by Party B for the contracted project shall be true, legal and valid.
2. On-site construction should comply with national and local laws, regulations and rules on labor safety and labor employment to ensure the legality of its employment. Party B must, in accordance with relevant national regulations, provide personal insurance for construction workers and equip them with qualified labor protection supplies and safety equipment.
3. Materials entering the site need to be checked to see if they have a production certificate, and they should be verified by Party A’s on-site person in charge or supervision engineer before use.
4. During the construction period, Party B shall assign a full-time safety officer to serve as safety work contact and on-site safety management.
5. Party B must prepare safety construction measures for all construction activities, conduct comprehensive safety technical briefings to all construction personnel before construction, and implement them correctly and completely during the entire construction process. No measures or failure to explain is strictly prohibited. cloth? construction.
6. Before starting construction, Party B shall organize safety education for all construction personnel. Special operations personnel must have valid and qualified qualification certificates issued by relevant departments.
Before starting construction, Party B should go to Party A to apply for a temporary entry construction order. Construction workers entering the site should sign up for construction.
7. Party B should install temporary fences or warning signs in the construction area, and shall not carry out construction beyond the designated construction area, and prohibit unrelated personnel from entering the construction site.
8. Party B shall ensure daily production and daily cleaning during the construction process to ensure that the construction site is clean and tidy.
9. Do a good job in civilized and safe construction; if electricity and water are needed during the construction process, Party A should be contacted in advance, and no unauthorized connections are allowed; do a good job in temporary electricity use during construction; comply with specifications. Scaffolding is set up to ensure the safety of construction workers and passengers.
10. Establish a rectification responsibility system, take effective measures to immediately rectify potential quality and safety hazards discovered during inspections, and assign dedicated personnel to be responsible for monitoring to ensure quality and safety.
11. On-site construction sites must effectively strengthen safe and civilized production during the holidays. Once various unexpected accidents and emergencies occur, plans must be launched immediately, and timely reporting and proper handling must be carried out in accordance with relevant regulations?
Party B shall submit the accident investigation report of the accident investigation team and Party B’s accident handling opinions to Party A for record.
12. In the event of suspension of work for rectification in the following circumstances, Party B shall bear the liability for breach of contract due to the suspension of work:
(1) Personal injury or death accident;
(2) Occurrence of Accidents involving serious damage to construction machinery and main production equipment;
(3) Fire accidents in the site;
(4) Failure to listen to advice during illegal operations or risky operations;
(5) The construction site is dirty, messy, and poor, and cannot meet the requirements for safe and civilized construction;
(6) During the construction process, anyone who violates the relevant regulations of the project is ordered by the relevant management agency Suspended.
Article 5 Liability for breach of contract
1. If the other party or third party suffers personal injury, equipment damage and other property losses due to the responsibility of Party A or Party B, the responsible party shall bear the corresponding liability, and Compensate all losses caused by the other party or third party.
2. Party B has not set up one? Safety supervision personnel; failed to correctly and comprehensively implement safety technical measures and construction organization design; construction personnel did not understand the characteristics of this project and construction safety measures; the construction machinery, tools and safety protection supplies used in this project did not meet the construction needs , Party A has the right to require Party B to immediately stop work and make rectifications, and Party B will bear the consequences and losses caused thereby.
Article 6 Party A and Party B must strictly implement this agreement. The legal effect of this agreement is independent of the main contract.
Article 8 This agreement will come into effect after being signed and sealed by the legal representatives or authorized agents of both parties. Article 9 This agreement is made in four copies, with Party A and Party B each holding two copies. Article 10 This agreement is signed at Party A’s domicile.
Party A: Party B: Legal representative: Legal representative: Authorized agent: Authorized agent: Contact number: Contact number:
Date of signing: Year, month and day