fire control acceptance report on the completion of construction project
project name
acceptance date
Employer (seal):
Notes on completing the form:
1. This form is filled in by the construction unit when organizing fire control acceptance.
2. When the construction unit declares the fire control acceptance or filing of the construction project, it shall submit this form, and the construction unit must fill it out truthfully;
3. This form shall not be filled in with ballpoint pen or pencil, and the contents in the form shall not be altered;
4. The general layout of the building, the layout of the standard and non-standard floors should be attached with this form.
1. Basic information of the construction project
Contact person of the construction unit
Contact person of the project name * *
contact person of design unit
contact person of civil construction unit
contact person of construction unit
contact person of supervision unit
contact person of decoration unit
building area of building site
building. Category □ new construction □ reconstruction □ expansion □ interior decoration
fire permit (record) number
main functions
remarks
II. Acceptance of civil works and decoration works
Spot check and inspection of acceptance items
□ General items. Setting of building curtain wall: □ compliance □ non-compliance
□ master control project;
□ General project
General layout and spot check of layout:
Fire prevention distance: □ Compliance □ Non-compliance
□ Main control project;
□ General items. Fire lane: □ compliance □ non-compliance
□ master control project;
□ General items. Fire fighting surface: □ compliance □ non-compliance
□ master control project;
□ General items.
Plane and space layout: □ conformity □ non-conformity
□ master control project;
□ General items.
Fire-prevention and smoke-prevention zones and building structure spot check parts:
Fire-prevention and smoke-prevention zones: □ Conformance □ Non-conformance
□ Main control project;
□ General items. Firewall, partition wall and floor slab, deformation joints and expansion joints: □ compliance □ non-compliance
□ master control project;
□ General items. Elevator shaft, pipeline shaft and other vertical shafts: □ compliance □ non-compliance
□ master control project;
□ General items.
Fire doors and windows: □ compliance □ non-compliance
□ master control project;
□ General items. Fire shutter: □ compliance □ non-compliance
□ master control project;
□ General items
Safety evacuation and
Spot check of fire elevators:
Evacuation stairwells and stairs: □ Compliance □ Non-compliance
□ Main control items;
□ General items. Emergency exits, evacuation walkways and evacuation doors: □ compliance □ non-compliance
□ master control project;
□ General items. Shelter floor (room): □ conformity □ non-conformity
□ master control project;
□ General items. Fire elevator: □ compliance □ non-compliance
□ master control project;
□ General items.
Spot check parts of decoration project:
Ceiling, partition wall, wall and floor: □ Compliance □ Noncompliance
□ Main control project;
□ General items.
Remarks
III. Spot-check parts and inspection of fire water supply and fire extinguishing equipment
Spot-check parts of fire water source and outdoor hydrant water supply system:
Fire water source: □ natural □ municipal □ compliance □ non-compliance
□ General items. Outdoor fire hydrant water supply system: □ compliance □ non-compliance
□ master control project;
□ General items.
Spot checks of indoor hydrant water supply system, fire pump room and fire pump:
Indoor hydrant system: □ compliance □ non-compliance
□ master control project;
□ General items.
Fire pump house and fire pump: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Automatic sprinkler
Spot check of fire extinguishing system:
System form □ Wet □ Dry □ Pre-action
System setting □ Compliance □ Non-compliance
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Spot check of water spray fire extinguishing system:
System settings: □ Conformity □ Nonconformance
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Spot check of water curtain system:
System settings: □ Conformance □ Nonconformance
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Rain spray
Spot check of fire extinguishing system:
System setting: □ Conform □ Not Conform
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Spot check of foam fire extinguishing system:
System settings: □ Conformance □ Nonconformance
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Spot check of gas fire extinguishing system:
System settings: □ Conformance □ Nonconformance
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Spot check parts of other fire extinguishing systems:
System name:
System settings: □ Compliance □ Noncompliance
□ Main control project;
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Remarks
IV. Spot check of smoke prevention, smoke exhaust, ventilation and air conditioning
Spot check of natural smoke exhaust system:
Natural smoke exhaust system: □ Compliance □ Non-compliance □ Master control.
□ General items.
Mechanical smoke prevention
Spot check of smoke exhaust system setting:
Mechanical smoke prevention system: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
smoke exhaust system of the organization: □ compliance □ non-compliance
□ main control project;
□ General items.
Smoke prevention and exhaust
Spot check of system functions:
Mechanical smoke prevention system: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
smoke exhaust system of the organization: □ compliance □ non-compliance
□ main control project;
□ General items.
Spot check of ventilation and air conditioning:
Ventilation and air conditioning: □ compliance □ non-compliance
□ master control project;
□ General items.
Remarks
V. Spot checks of electrical
Fire-fighting power supply and its distribution spot checks:
Fire-fighting power supply: □ Compliance □ Non-compliance
□
□ General items.
Fire power distribution: □ compliance □ non-compliance
□ master control project;
□ General items.
Spot check of fire emergency lighting and evacuation signs:
Fire emergency lighting: □ compliance □ non-compliance
□ master control project;
□ General items.
evacuation indication sign: □ conformity □ non-conformity
□ master control project;
□ General items.
Spot check parts of power lines and
electrical devices:
Power lines: □ compliance □ non-compliance
□ master control project;
□ General items.
Electrical devices: □ compliance □ non-compliance
□ master control project;
□ General items.
Spot check of automatic fire alarm system:
System form: □ area alarm system □ centralized alarm system □ alarm system of control center
Detector type: □ ion smoke □ photoelectric smoke □ temperature sensing □ flame □ combustible gas □ line type □ other
□ General items.
System function: □ Compliance □ Non-compliance
□ Main control project;
□ General items.
Spot check of leakage fire alarm system:
Leakage fire alarm system: □ compliance □ non-compliance
□ master control project;
□ General items.
Remarks
VI. Configuration of building fire extinguishers
Spot check of acceptance items
Configuration of building fire extinguishers
Spot check:
Configuration type: □ Clear water □ABC dry powder □ Chemical foam □ Other.
□ General items.
Remarks
VII. Comprehensive conclusion of acceptance
After comprehensive evaluation, the fire control acceptance of this project is:
□ qualified. However, there are still the following general unqualified items:
□ unqualified. The following problems exist:
□ Main control project:
□ General project:
Civil works designed by the construction unit
Fire fighting works by the construction unit
Decoration by the construction unit
Supervision by the construction unit
.
signature of person in charge
signature of person in charge
signature of person in charge:
(seal)
signature of person in charge
. Title signature
standard floor plan
(with the official seal of the construction unit, design unit and construction unit)
non-standard floor plan
(with the official seal of the construction unit, design unit and construction unit)
I hope my answer can help you.