Who signed the sub-project quality acceptance record?
Signatories of quality acceptance records of subdivisional works: supervision engineer and project professional and technical person in charge of the construction unit. Note that the project professional and technical director of the construction unit and the project director of the construction unit are two people.

A, project quality acceptance procedures

1, the inspection lot and subdivisional work shall be jointly accepted by the supervision engineer (project technical director of the construction unit) and the project technical director of the construction unit.

2. The chief supervision engineer (the project leader of the construction unit) shall organize the project leader of the construction unit and the technical and quality leaders to inspect the divisional project. By the foundation and foundation, the main structure of the division of engineering survey, design units, project leaders and construction units, technical and quality leaders for acceptance.

3. After the company's project is completed, the construction unit shall organize relevant personnel to conduct acceptance evaluation and submit the project acceptance report to the construction unit.

4. After the construction unit receives the project acceptance report, the person in charge of the construction unit (project) shall organize the project (including subcontracting), and the person in charge of the design and supervision unit shall conduct the project acceptance for the company.

5. After the company's engineering quality is qualified, the construction unit shall submit the completion report and related documents to the construction administrative department for the record within the specified time (15 days).

Second, the component project quality inspection record filling method

Table Name Fill in the name, header, inspection lot location and sub-item of the acceptance sub-item project, and the inspection and evaluation results of the construction unit shall be filled in by the professional quality inspector of the construction unit. After the acceptance, the professional and technical person in charge of the construction unit puts forward the evaluation and signs it. On the basis of passing the acceptance, the supervision unit or the construction unit is entrusted to accept the sub-projects, which usually plays the role of summarizing and sorting out. It is a statistical table with no substantive acceptance content.

The professional supervision engineer of the supervision unit shall check each project item by item, and fill in "qualified or meeting the requirements" on the agreed project. If not, it should be checked after treatment, but it must be marked. Please indicate the opinions of acceptance and rejection. When you agree to the acceptance and sign for confirmation, if you don't agree to the acceptance, please point out the existing problems, make clear your opinions and the completion time.