The main body (or foundation) division project construction to a certain stage (such as several layers) for the next step of internal and external plastering process handover acceptance-the whole division project has not yet been completed.
However, the connection process of the next sub-project needs to be carried out in advance. Without intermediate handover acceptance, the next process will not be accepted after completion. The acceptance of the main structure refers to the acceptance of the sub-projects before the whole main sub-project is handed over to the next sub-project (decoration engineering division) after the construction is completed.
Extended data
The quality control data items of the accepted division (sub-division) project shall be determined according to the relevant contents of the unit (sub-unit) project quality control data verification record in GB 50300-2001+0 table G.0. 1-2, and shall be checked item by item according to the requirements of data verification. Can basically reflect the quality of the project, meet the requirements of ensuring structural safety and use function, and then pass the acceptance.
If all the projects are qualified, you can mark "/"in the inspection and evaluation column of the construction unit as qualified. And send it to the supervision unit or the construction unit for acceptance, and the chief supervision engineer of the supervision unit will organize the review. After meeting the requirements, endorse the "Agree to Accept" opinion in the acceptance opinion column. Some projects can be accepted by sub-division projects, and some projects can be accepted by division projects. Because the projects are different, there is no need for unification.
During the intermediate acceptance, the relevant personnel who participated in the project construction responsibility unit according to the list should sign in person to show their responsibility, so as to trace the quality responsibility. The survey unit can only sign and recognize the foundation division (sub-division) project, and the person in charge of the project personally signs and recognizes it; The design unit can only sign the foundation, main structure and important installation division (sub-division) project, and the project leader will personally sign it.
The general contract of the construction unit must be signed, and the project manager must personally sign. Subcontractors with subcontractors must also sign off on their subcontracted division (sub-division) projects, and the subcontracting project manager must sign off in person.
As the acceptance party, the supervision unit shall be personally signed and accepted by the chief supervision engineer. If the project is not entrusted to the supervision unit according to the regulations, the professional person in charge of the project of the construction unit may personally sign and accept it.
Baidu Encyclopedia-Intermediate Acceptance