Completion acceptance refers to a comprehensive acceptance of all engineering projects after the completion of the project. This is an important link to ensure whether the project meets the planning and design requirements and to inspect the quality of the construction equipment installation of the building. So, what are the general project completion acceptance materials? The following is an introduction to the project completion acceptance materials brought by Zhongda Consulting for reference.
Project completion acceptance materials generally include the following contents:
(1) Completion acceptance registration form (cover): The construction unit shall fill in the details before submitting the registration documents.
(2) Project Overview
1. The filing date: filled in by the filing department.
2. Completion acceptance date: consistent with the completion acceptance date in the "Completion Acceptance Certificate".
3. Construction project planning license (copy) (original submitted for verification)
4. Construction project construction license (copy) (original submitted for verification)
5. Construction drawing design review report.
(3) Unit Project Acceptance Notice
The official seal of the construction unit shall be stamped, signed by the project supervisor of the Municipal Construction Project Quality Supervision Station, and the acceptance of all parties participating in the construction shall be filled in in detail. Personnel list, including personnel from the construction (supervision) unit, construction unit, and survey and design unit.
(4) Unit Project Completion Acceptance Certificate
1. It shall be filled in by the construction unit and submitted to the construction unit, and shall be approved by each responsible entity (construction, supervision, survey, design, construction unit) After signing and stamping the official seal of the legal entity, submit it to the quality supervision station for review and approval, and then submit a copy to the filing department.
2. In the acceptance opinion column, the content that must be stated includes: whether the project has been completed in accordance with the design and contract requirements, whether the functions of each system have been operating normally and in compliance with relevant regulations; the construction process A concise explanation of whether the quality problems that have arisen during the project have been resolved, whether hidden dangers in structure and function have been found on site, whether the inspection personnel have unanimously agreed to the acceptance, and whether the engineering technical files and materials are complete.
(5) Rectification Notice
The written rectification record required to record the rectification issues ordered by the quality supervision station refers to whether there are other issues in the project that do not involve structural safety and main functions. General quality problems, have they been rectified?
(6) Rectification completion report
It is required to record the completion of rectification in detail, and it should be signed and stamped with the official seal by the construction party, and the supervisor should confirm the completion of rectification. If during the project acceptance process If there is no rectification content, the owner (supervisor) unit needs to sign and seal for confirmation.
(7) Project quality supervision evaluation report
1. After the supervision unit pre-accepts the project upon completion and the construction unit completes the rectifications, it shall be filled in by the chief supervision engineer.
2. Quality assessment opinion column:
(a) Whether the project supervision department has strictly followed the "Construction Project Supervision Specifications", supervision contract, supervision plan and supervision implementation rules for the The project was fully supervised.
(b) Whether the construction quality of the foundation and basic engineering meets the design and specification requirements;
(c) The main project (including grid, curtain wall, dry-hanging stone, underground structure, steel structure, etc.) Whether the construction quality meets the design and relevant specification requirements;
(d) Whether the construction quality of water, electricity, HVAC and other installation projects meets the design and specification requirements and whether it meets the functional requirements.
3. Clearly assess the quality level of the project: an internal letter of project completion acceptance issued by the quality station.
(8) Construction Project Quality Assessment Report
Notes on the assessment report:
1. After the supervision unit pre-accepts the project upon completion, the construction unit has completed the rectifications. To be filled in by the chief supervisory engineer.
2. Quality assessment opinion column:
(a) Whether the project supervision department has strictly followed the "Construction Project Supervision Specifications", supervision contract, supervision plan and supervision implementation rules for the The project was fully supervised.
(b) Whether the construction quality of the foundation and basic engineering meets the design and specification requirements;
(c) The main project (including grid, curtain wall, dry-hanging stone, underground structure, steel structure, etc.) Whether the construction quality meets the design and relevant specification requirements;
(e) Whether the construction quality of water, electricity, HVAC and other installation projects meets the design and specification requirements and whether it meets the functional requirements.
3. Clearly assess the quality level of the project.
Note: The form of this evaluation report is made by the supervision unit or construction unit, but the content of the report must contain the above precautions.
(9) Housing construction project quality warranty letter
1. It shall be signed by the construction unit and the construction unit after the project is completed and accepted.
2. Project warranty items column: In addition to the six warranty items, others should be added according to the design documents and contract agreements. If relevant national regulations require new items to be added, they should be completed.
3. Minimum warranty period column: all in Chinese capital letters, the minimum warranty period shall not be lower than the period stipulated by the state.
(10) "Residential Quality Guarantee" for commercial housing
The construction unit shall register and affix the official seal based on the actual sales situation and property management conditions.
Contact sheet for receiving construction project archives
Relevant quality inspection and functional test data for municipal engineering infrastructure
"XX City Housing Construction (Municipal Infrastructure ) "Opinion Letter on Passing the Completion Registration"
"XX City Housing Construction (Municipal Infrastructure Expression of Opinion on Passing the Completion Registration)"
(11) Relevant quality inspection and functional test information
Provide functional test reports issued by nationally certified testing departments.
(12) Other documents and information
1. Documents approved by the planning department usually require the project planning permit (copy), but the original must be provided for verification, and the copy plus the The official seal of the construction unit indicates where the originals are kept.
2. For the project construction license, provide a copy and submit the original for verification. The copy plus the official seal of the construction unit indicates where the original is stored.
3. Documents approved by the public security and fire protection department. If the design has fire protection requirements, the original document shall be provided, that is, the "Fire Protection Acceptance Letter of Construction Project".
4. The original document approved by the environmental protection department and designed with environmental protection requirements, namely the "Suzhou Construction Project Environmental Impact Report Form" issued by the Municipal Environmental Protection Bureau.
5. Construction drawing design document review report, the original shall be provided in accordance with relevant regulations.
6. Special acceptance letter for construction project archives, that is, the "Contact Form for Receiving Construction Project Archives" (original) provided by the Urban Construction Archives.