Steps to apply for a fire protection certificate:
1. The applicant shall issue an application report and obtain the "Public Security Entertainment Venue Fire Safety License Application Form" from the local public security fire supervision agency.
2. Fill out the "Public Entertainment Venue Fire Safety License Application Form", the reporting unit signs the opinion and stamps the official seal, and submit the completed application form and application report to the local public security fire supervision agency (Key units under the jurisdiction of the detachment shall be sent directly to the Fire Prevention Department of the detachment).
3. Within 7 days after the local public security fire supervision agency receives the report and "Declaration Form" from the applicant unit, it will send a staff officer in charge to conduct an on-site inspection and review according to the review content. Those who are qualified will be reviewed by each county (city) ) The city shall have the opinions signed by the staff in charge and submitted to the brigade leader for approval and stamped with the official seal. The license fee will be charged according to regulations, and then the brigade back office will be responsible for filling out and issuing the "Fire Safety License for Public Entertainment Places".
4. Within 10 days after receiving the (declaration form) and relevant information reviewed by the fire brigade of each district in the city, the fire prevention department of the detachment will send a staff officer in charge to conduct an investigation. If the review is qualified, he will sign the review opinion and report it to the fire prevention department The leader and detachment leader will review and approve, stamp the official seal, and collect the application fee according to regulations. Then the back office of the Fire Prevention Department will be responsible for filling in and issuing the "Fire Safety License for Public Entertainment Places"
Required application materials:
(1) The Fire Safety Approval Form for Cultural and Entertainment Places should be filled in;
(2) The "Construction Project Fire Safety Acceptance Letter" must be produced for any newly built place;
(3) Fire-fighting products such as evacuation signs and fire accident lighting should present the fire-fighting certificate of the product;
(4) When combustible decoration is subjected to flame-retardant treatment, the inspection report and fire-fighting product certificate must be presented;
(5) Places with building fire protection facilities must present a qualified "Building Fire Protection Facilities Inspection Report";
(6) Bathing places should present a boiler product inspection certificate;
p>
(7) The number of consumers allowed in singing and dancing entertainment venues shall not exceed the approved number.
Extended information:
Steps for fire protection acceptance
1. After the construction project is completed, the construction unit should submit an application for fire protection acceptance after the completion of the project to the public security fire protection agency. It can only be put into use after passing the test.
2. After the public security firefighting agency accepts the case, the specific person in charge of the acceptance inspection should check whether the information meets the requirements. If it does not meet the requirements, the applicant should be informed in time to make up for it, and the construction unit should be notified 1-2 days before acceptance. Make relevant preparations before acceptance.
3. According to the provisions of the fire protection project acceptance procedures, no less than two fire supervisors shall go to the site for acceptance. The fire supervisors participating in the acceptance shall wear standard police uniforms and the "Public Security Fire Supervision and Inspection Certificate" 》, the specific acceptance procedures are as follows:
(1) Each unit participating in the acceptance will introduce the situation. The construction unit introduces the project overview and self-inspection status, the design unit introduces the fire protection engineering design status, the construction unit introduces the project construction and debugging status, the supervision unit introduces the project supervision status, and the testing unit introduces the testing status.
(2) Group on-site inspection and acceptance. Acceptance personnel should inspect and test at the same time, and truthfully fill in the fire acceptance record form.
(3) Summarize the acceptance status. Each group reports on the acceptance status respectively. According to the "Guangdong Province Construction Project Fire Acceptance Assessment Rules (Trial)" formulated by the Corps, assessments are carried out according to sub-item, single item, and comprehensive procedures. The assessment conclusions are truthfully recorded in the acceptance record form, and Provide preliminary opinions to construction, construction, design and other units participating in the acceptance inspection, and promptly provide rectification opinions to the construction unit for those that do not meet the requirements of the specification.
4. When the construction, construction and design units participating in the acceptance inspection express opinions or raise questions, the participants in the acceptance inspection of the fire protection agency should give a reply. Those who cannot reply on the spot should give an explanation.
5. After the fire protection project has passed the acceptance or re-inspection, the acceptance personnel of each unit and the fire protection agency shall sign on the acceptance declaration form.
6. The project acceptance contractor should fill in the acceptance opinion letter in a timely manner, submit the approval form, and organize the acceptance files and send them to the leadership for approval.
7. The construction unit will go to the window and issue a receipt to retrieve the acceptance letter;
8. When the acceptance and reexamination fail, the construction unit should organize all relevant units to comply with the "Construction Project Fire Protection The problems raised in the "Acceptance Opinion Letter" will be rectified. After the rectification is completed, a re-inspection application will be made to the public case fire protection agency. The re-inspection procedures are the same as those for application for acceptance.
9. If the construction project fails to pass the acceptance inspection, the application materials will not be returned. When applying for re-inspection, the application information is the same as the normal application and acceptance information.
Reference: Baidu Encyclopedia-Fire Safety License