Three papers on the summary of project completion
Writing a project completion summary is actually a test of our self-working ability. Do you know how to write a project completion summary? The following are the reference materials of three selected articles "Project Completion Summary", which are shared with you for your reference. You are welcome to read them.

Selected model essays for project completion summary 1

? I. Overview of the Project

? 1, engineering geographical location and engineering structure form

? The 20xx small key county construction project in Shuyang County (1 bid) is located in Shizi Town, Shuyang County.

? 2. Relevant units, construction period and contract cost of the project.

? Owner: Office of Leading Group for Water Conservancy Construction Project

? Design unit: Jiangsu Zhanghe Civil Engineering Design Institute

? Supervision unit: Engineering Construction Consulting Co., Ltd.

? Construction unit: Xindadi Engineering Co., Ltd.

? Contract cost: 286,265,438+ten thousand yuan.

? The contract starts on February 28th, 20xx, and ends on June 7th, 20xx.

? Actual commencement date: 20xx February 28th Actual completion date: 20xx August 18.

? 3. Main technical and economic indicators:

? It is planned to renovate the channel 14, * * 13.224 kilometers, of which rectangular channels are 4.82 kilometers and 8.404 kilometers; U-grooved; Newly added pools 1 1, including 4 pools 1 100m3, 6 pools/300m3 and 500m3 pools1; There are 24 sluice wells, aqueducts 1 seat, 9 highway culverts and 8 flood discharge troughs on the canal. Irrigation pipe network 5km, field pipe network 12km. Earthwork excavation 1.52 million cubic meters; Earthwork backfill of 8,000 square meters; Concrete pouring is 0./kloc-0. 8 million square meters; Steel bar 46.85 t; Cement 400 t; Explosive150kg; ; Sand and gravel 2300 cubic meters; Masonry concrete brick 0300 square meters; The total investment of the project is 28,665,438+200,000 yuan.

? 4. Main construction contents:

? Planning and construction contents:

? Canal system works: channel reconstruction14km, * * *13.224km; Among them, the rectangular channel is 4.82km and the U-shaped channel is 8.404km. Regulation pond project: 1 1 newly built ponds, including 4 ponds of 1 100m3, 6 ponds of 300m3 and 500m3 ponds of1seat;

? Supporting buildings: 24 sluice wells, aqueduct 1 seat, 9 highway culverts and 8 flood discharge troughs on the canal; Pipe network engineering: 5km for irrigation pipe network and 12km for field pipe network.

? Complete the construction content:

? Drainage works: regulation works 13 (including U-shaped channels and rectangular channels of Paper Mill Bay and Leshan Channel), * * * *12.835km; ; (including: 4 rectangular channels, * * * * * 5.135km; ; With 1 1 U-shaped groove, * * * 7.700km);

? Regulation tank project: 6 new 300m3 regulation tanks, 2 200m3 regulation tanks and 2 100m3 regulation tanks;

? Supporting buildings: 30 new sluice wells, 1 modified aqueduct 1 seat, 9 highway culverts, and 5 flood discharge channels; Pipe network engineering: the irrigation pipe network is excavated and backfilled by 4.397km,12 km; Excavation and backfilling of on-site pipe network;

? 5. Mainly complete the engineering quantity.

? This project * * * completed earthwork excavation of 65438+6300 cubic meters; Earthwork backfill 0.94 million cubic meters; Concrete pouring 2400 square meters; Steel bar 50.26 t; Cement 400 t; Explosive150kg; ; 3000 cubic meters of sand and gravel; Masonry of 460,000 square meters of concrete bricks; The total investment of the completed project is 3,842,200 yuan.

? Second, the construction management

? 1, schedule management

? Since the construction started on February 28th, 20xx, it was successfully completed on August 28th, 20xx through careful organization of construction. In terms of schedule management, the project department has mainly done the following work:

? 1) Construction progress plan: Before the commencement of construction, the project department shall prepare the general construction progress plan. In the process of construction, the project department prepares monthly plans and weekly plans according to the total schedule, and formulates the construction period of key nodes of the project.

? 2) Scientifically increase investment in key equipment and turnover materials.

? At the early stage of the project, it was once influenced by the local people's boycott, which seriously delayed the construction period and the progress of the project was seriously behind schedule. In order to ensure the overall progress of the project, the relevant personnel of the project department cooperate with the owner's representative to do mass ideological work at various construction sites. After countless efforts around the clock, the situation of lagging progress was reversed, which laid a solid foundation for completing the whole project on schedule.

? 3) Implement scientific project plan management.

? In the process of engineering construction, according to the schedule, comprehensively track the progress of various projects, adhere to the weekly meeting system, analyze the progress, find out the reasons for the delay, take effective measures, and correct the deviation in time. According to the progress of the project, timely optimize and adjust the progress plan to ensure that the construction period of key nodes meets the requirements of the total construction period.

? 4) Ensure the quality and quantity to ensure the progress.

? Do a good job in quality control in the construction process, do a good job in quality planning and on-site construction personnel training before construction, improve the quality awareness of all staff, and ensure that rework does not occur; In the process of construction, strengthen on-site quality monitoring, and at the same time strengthen the arrival, re-inspection and acceptance of materials to avoid the phenomenon of shutdown caused by late or unqualified materials.

? 5) Safety guarantee progress.

? Manage safe and civilized construction with advanced, scientific and strict management methods, and really promote safety.

? 2. Quality management

? (1) Carefully compile the construction organization design and strictly implement it.

? After entering the site, the project department organizes key personnel to be familiar with design documents, drawings, relevant technical standards, specifications, procedures and contract documents, and participates in the blue prints.the design and design disclosure organized by the owner. According to the natural conditions and social and economic conditions of the site, a practical, scientific, economical, reasonable, practical and instructive construction organization design shall be prepared, submitted for approval according to relevant procedures (company, supervisor and owner), and strictly implemented after approval.

? ② A complete quality management system and quality assurance system have been established.

? Before construction, the project department compiled and established a perfect quality management system and quality assurance system according to ISO9002 quality management system. The project is equipped with strong technical and management forces and a clear division of labor. The quality management system and quality assurance system operated effectively in the construction process, and no quality accident occurred.

? (3) Establish the technical disclosure system before construction.

? Before each subdivisional work starts, the person in charge of individual technology shall make detailed technical disclosure to all construction personnel and operation teams, and make clear the design requirements, technical standards, geometric dimensions, main construction methods and matters needing attention of each subdivisional work, so that all construction personnel can fully understand the construction object, construction technology, construction drawings, quality standards and time limit requirements before the subdivisional work starts.

? (4) Strictly implement the process acceptance? Three inspections? manufacture

? That is, self-inspection, mutual inspection and special inspection. Those who fail in the previous procedure are not allowed to enter the next procedure, so as to ensure the quality of the project and strictly control the quality.

? ⑤ Carefully write the construction work instruction.

? For key and major sub-projects, the chief engineer of the project organized and compiled targeted and operable construction work instructions, and put forward more detailed process requirements to ensure the construction period and visual quality.

? ⑥ Establish and improve strict inspection and acceptance system for concealed works.

? All concealed engineering projects shall be self-checked step by step by the quality inspection engineer of the team and project department. Only after the self-inspection is qualified can it be reported to the supervision engineer for inspection and signed in time? Take cover engineering acceptance record? .

? ⑦ Adhere to the system of weekly production meeting and weekly quality meeting.

? Every Friday night at 6: 30, the project manager will organize a weekly production meeting and a weekly quality meeting to comment on last week's quality situation, quality rectification and problems heard in the weekly supervision meeting, and put forward the quality work priorities and quality rewards and punishments for next week, which has played a positive role in quality control.

? ⑧ Establish the system of hand-over and recheck the measurement and calculation data.

? All survey technical data must be rechecked by changing hands and finally submitted to the project chief engineer for approval;

? Construction site survey baseline, leveling points and related signs should be checked regularly.

? 3, materials and equipment management

? (1) Strictly implement the planned application system for material procurement, and purchase materials according to the system of our logistics company to ensure that qualified raw materials are used in this project.

? (2) Establish and improve strict acceptance system for raw materials, finished products and semi-finished products.

? The acceptance of raw materials, finished products and semi-finished products shall be organized by the personal technical supervisor; Participants include quality, technology, testing, materials departments and construction-related personnel. The acceptance contents include: whether the variety, specification and quantity of the incoming goods meet the procurement plan; B. Whether the supplier's product certificate or test report is complete; C on-site quality inspection of products, and fill in inspection and acceptance records; D. Take samples for entrusted test and fill in the entrusted test report.

? After receiving the goods according to the acceptance procedures, they should be kept in different categories, marked and the samples should be kept well. Quality inspection records and test reports shall be kept with the samples for future reference. Strict formulation and implementation of unqualified raw materials, finished products and semi-finished products management system.

? (3) When the reinforced brick is rammed, it is 50cm from the ground, and direct contact is strictly prohibited to cause corrosion; All kinds of semi-finished products are clearly marked.

? 4. Safe production

? Strictly enforced? Safety in production, prevention first? Basic policy: the project department shall set up full-time security officers and appoint a deputy manager to be responsible for safety work. Before the project starts, all construction personnel entering the site shall be given three-level safety education, and a safety agreement shall be signed. Workers with special types of work shall insist on holding relevant certificates. Since the project started on February 28th, 20xx last year, there has not been a casualty accident at the site.

? For subdivisional works with key working procedures, high risks and strong technology, the project department has compiled special construction schemes (including safety schemes), such as hoisting of underground continuous wall reinforcement cage, deep foundation pit excavation, bored piles, cast-in-place breast wall, on-site construction electricity and other subdivisional works, and timely reported them to the supervisor, the owner and relevant departments, and organized the scheme review and demonstration, and the construction can be organized only after approval;

? The project department is led by the person in charge of the project, and carries out routine safety inspection every month and week, which is organized by full-time security officers to play the role of inspection and control.

? Participate in the joint safety inspection of relevant units organized by the owner every month and week, and the inspection is recorded and rectified.

? 5, civilized construction

? Do a good job of civilized construction in strict accordance with the first-class site standard of the Measures for the Administration of Construction Site. One card and one picture? Three pictures and one table? If the plaque is complete, all kinds of publicity slogans, flags and safety warning signs are standardized.

? Third, the unit engineering quality inspection

? This project is divided into 1 unit project, 3 subprojects and 39 unit projects.

? According to the quality inspection standards of water conservancy projects, all 39 unit projects are excellent projects, with an excellent rate of 100%, and all three sub-projects are excellent projects, with an excellent rate of 100%, and the quality of unit projects is excellent.

? Four. Concluding remarks

? During the construction process, we received the guidance and strong support from the owner Badong County Water Conservancy Bureau, the designer Zhanghe Civil Engineering Design Institute of Hubei Province and the supervisor Hubei Chu Yuan Engineering Construction Consulting Co., Ltd., which enabled the project to be implemented smoothly and successfully completed the construction task according to the contract quality, progress and safety objectives. On behalf of the Project Department of 20xx Small Key County Construction Project in Badong County of Hubei Xindadi Engineering Co., Ltd. 1 Bid, I would like to express my heartfelt thanks to the owners, supervisors, design and quality supervision station leaders and relevant comrades who have supported and cared about Hubei Xindadi Engineering Co., Ltd.

? Please criticize and correct me from leaders and experts!

? Dida engineering co., ltd

Project completion summary Fan Wenxuan 2? I. Overview of the Project

? 1. Project name: Building 2 and Building 5 of resettlement house in the north area of He 'an Jiayuan has a construction area of 8,200 square meters. 20xx started on March 10 and was completed on April 30th, 20xx.

? 2. Designer: Hunan Shicheng Architectural Planning and Design Co., Ltd.

? 3. Survey unit: Hunan Construction Engineering Survey Institute.

? 4, supervision company:

? 5, the construction unit:

? 6. Structural design: This project is a six-story brick-concrete residence, with a structural safety grade of Grade II, a design service life of 50 years, a building seismic fortification grade of Grade VI, a foundation design grade of Grade C and a natural shallow foundation. Concrete strength: foundation cushion C 10, foundation C25, frame beam-column slab C30 and common beam-column slab C20. The strength grade of brick is M 10.0. M7.5 cement mortar below 0.000, one to three layers of M7.5 mixed mortar, and four to top layers of M5.0 mixed mortar. The quality grade of masonry is Grade B. ..

? Second, the main basis of construction:

? 1, construction drawings, design change documents and relevant instructions of the owner.

? 2, the current national laws and regulations and construction engineering quality acceptance specification.

? 3. The company's quality management system and the relevant quality system of the project department.

? 4, construction engineering data management procedures and other related documents.

? Three. Management methods and project management objectives:

? Our company has carefully prepared the construction implementation plan and managed it in the mode of engineering project department. In terms of safety management and civilized construction, we will vigorously promote standardized management, implement regular inspection and quantitative scoring, and combine the economic reward and punishment system to achieve the goal of civilized construction and safe production without accidents. Quality is the life of an enterprise. My project department's quality goal for this project is: qualified rate 100%, and strive for a successful acceptance. In order to achieve this goal, in the quality plan, the project department will control special processes and key processes, focusing on preventing quality problems in key processes; Adhere to the policy of putting prevention first, make plans to eliminate common quality defects, and put the work of eliminating common quality defects in an important position; Establish higher quality standards (internal control standards) for the main branch project and decoration branch project, and greatly improve the quality of sub-projects and the score of architectural perception. Detailed and easy-to-operate schemes have been formulated for the implementation of documents, product identification and traceability, inspection and testing, nonconforming product control, storage and protection, training and other elements.

? Management measures for safe and civilized construction: establish and improve the responsibility system for safe production, which should be adhered to by leaders at all levels and all project personnel? Safety first, prevention first? Principle: Strengthen safety awareness, organize regular safety inspections, conduct pre-shift safety activities every day, educate operators on safety awareness and discipline, and strengthen self-protection awareness. The safety officer and the team check each other, and rectify in time when problems are found. Due to the strict management and organization of construction according to 1999 version of "Safety Inspection Standard for Building Construction", all major and minor safety accidents have been eliminated and the established safety objectives have been achieved.

? Fourth, the project quality control

? In the project quality control, the project department adheres to the company's quality assurance system as the main line, takes the construction specifications and national quality standards as the criterion, speaks with actual data, and follows the following principles: adhere to quality first; Insist on controlling nuclear by people; Adhere to prevention first; Adhere to quality standards; Implement scientific, fair and law-abiding professional norms.

? 1, engineering quality grade of each division

? Serial number division engineering quality grade

? 1 Basic part is qualified

? 2. The master teacher is qualified

? 3 decoration division qualified

? 4 qualified roof division

? 7 water supply and drainage division qualified

? 8 Electrical division is qualified

? Unit project qualification rate 100%.

? 2. Quality control means before, during and after the event: Because the project quality itself has the following characteristics: many influencing factors, great quality fluctuation, great quality variation, hidden quality and great limitations in final inspection. Therefore, we should pay attention to pre-control and strict supervision in the process of engineering quality, nip in the bud and nip quality accidents in the bud. Based on the quality assurance system of the group company, the project department carries out specific quality control according to the requirements of construction process, inspection and test, nonconforming product control, correction and preventive measures.

? A. Control before construction: In the preliminary work, the project department pays attention to the preparation of construction technology;

? A. Pay special attention to the blue prints.the design and technical disclosure before construction.

? B, before the project department starts, the construction survey control network shall be re-surveyed, and the periodic verification and availability of inspection, measuring and test equipment shall be checked to ensure the accuracy of engineering survey and test.

? C, pay special attention to the preventive measures of common quality problems before construction: the project department organizes the construction team to learn the construction operation procedures before the project starts.

? B, control in the process of construction:

? A. Carry out on-site supervision and inspection: During the construction process, the management personnel of the project department will strengthen the supervision and inspection of the on-site station, find out the illegal operation and the phenomenon that does not meet the design requirements, construction drawings, construction specifications, procedures and quality standards in time, and promptly correct and strictly control the non-compliance with quality requirements.

? B, check the material certificate of the building materials entering the site, and witness the sampling together with the supervisor; Strictly control the concrete mixture ratio, material measurement, mixing quality and slump, and reserve test blocks;

? C, strengthen process inspection, process handover inspection and concealed engineering inspection. On the basis of self-inspection, the process handover inspection was also carried out. It is stipulated that concealed works must be checked and confirmed by the supervision unit before they can be concealed.

? D, timely according to the specification to do a good job of engineering and technical data.

? C, the construction of product control:

? A, unqualified products such as concrete columns and beams that have an impact on the main structure must be aborted and redone. B, enter the decoration stage, for unqualified parts, must rework, and after acceptance, can enter the next working procedure construction.

? Five, the project schedule control

? Since the start of construction, the construction has been organized in strict accordance with the progress plan in the construction organization design, and adjusted according to the actual construction situation in each stage. In the process of construction, make a monthly plan for daily control.

? The successful completion of this project can not be separated from the strong support of the leaders, owners, design institutes and supervision companies of quality supervision stations and resettlement offices in industrial parks. They not only strictly control the construction quality, but also give advice to the construction party in the spirit of serving the construction unit. With the joint efforts of all construction management personnel, the smooth completion of the project was ensured. Here, on behalf of Huaihua Changshun Construction Engineering Co., Ltd., I would like to express my sincere thanks to all the people and guests who participated in this project!

Project completion summary Fan Wenxuan 3? I. Project Overview Summary of Project Completion

? The student apartment and canteen project of Huainan No.2 Middle School is located in the campus of Huainan No.2 Middle School, with a construction area of about 5909m m. The construction unit of this project is: Huainan Mine No.2 Middle School; The design unit of this project is: Anhui Modern Architectural Design and Research Institute; The survey unit of this project is Huainan Coal Survey and Research Institute; Project supervision unit: Huainan Zhongcheng Supervision Consulting Co., Ltd.; The construction unit of this project is Huainan Education Jian 'an Company. This project is a six-story frame structure, and the foundation adopts concrete independent column foundation. The foundation cushion is C 15 concrete, the foundation cap is C25 concrete, the foundation beam to the third floor column is C30 concrete, the beam slab is C25 concrete, and the columns, beams and slabs above the third floor are C25 concrete. ? +/-0.00 solid clay brick and M5 cement mortar are used for masonry inside and outside. Above 0.00, M5 non-bearing clay hollow brick is used, and the inner wall is made of 180 thick aerated concrete block, all of which are built with M5 mixed mortar. The interior wall is painted with white latex paint, and the exterior wall tiles, stairs, corridors, floors and dados are all ceramic floor tiles. Roof insulation layer and SBS waterproof layer.

? 20xx started on April 8th and was completed on August 3rd1day. During the construction of this project, the project department will carefully construct and manage it in strict accordance with the relevant national standards and the relevant documents and design blueprints of quality, safety and civilized construction of relevant provincial and municipal departments.

? 3. The Project Department was established under the leadership and supervision of the construction unit and supervision unit? Three inspection teams? For structural engineering, strict inspection shall be carried out, and construction shall be carried out after acceptance and signature.

? Four, in terms of materials, the project department strictly, all finished and semi-finished materials entering the construction site, all by the supervision personnel to the scene for inspection and acceptance, and obtain the material factory certificate or quality guarantee, to ensure that the qualified rate of materials in 100%.

? Five, in terms of safe and civilized construction, the project department carries out safe and civilized education and safety technical disclosure for each team and type of work, and takes advantage of workers' commuting and rainy day breaks to conduct open-book examinations.

? In a word, the construction unit has made some achievements in foundation, main body and decoration. , but there are still some shortcomings. In the future, we will carefully construct and manage in strict accordance with the relevant construction specifications, laying a good foundation for the next step of engineering excellence. Under the leadership and supervision of the construction unit and supervision unit, we will make persistent efforts to strengthen management and achieve better results for future projects.