1. To apply for fire protection acceptance, the following materials should be provided:
(1) Construction project fire protection acceptance declaration form;
(2) Project completion acceptance report;< /p>
(3) Documents proving the quality of fire protection products;
(4) Documents proving that building components, building materials, and interior decoration materials with fire protection performance requirements meet national standards or industry standards. , factory certificate;
(5) Documents proving that fire protection facilities and electrical fire protection technology have passed the test;
(6) Legal identity certificates and qualification levels of construction, project supervision, and testing units Supporting documents;
(7) Other materials required by law.
2. Precautions for fire protection acceptance:
1. All requirements raised during fire protection audit should be met;
2. Automatic fire protection facilities have been tested and qualified, and Intact and effective;
3. Safe evacuation meets specification requirements;
4. Fire-fighting products are of qualified quality and quantity guaranteed;
5. Decoration materials meet specification requirements ;
6. The flammable and explosive settings meet the requirements;
3. Fire acceptance process:
1. After the construction project is completed, the construction unit shall report to The public security fire protection agency submits an application for fire protection acceptance after the project is completed, and it can only be put into use after passing the acceptance inspection.
2. After the public security firefighting agency accepts the case, the specific person in charge of the acceptance inspection should check whether the information meets the requirements. If it does not meet the requirements, the applicant should be informed in time to make up for it, and the construction unit should be notified 1-2 days before acceptance. Make relevant preparations before acceptance.
3. According to the provisions of the fire protection project acceptance procedures, no less than two fire supervisors shall go to the site for acceptance. The fire supervisors participating in the acceptance shall wear standard police uniforms and the "Public Security Fire Supervision and Inspection Certificate" 》, the specific acceptance procedures are as follows:
(1) Each unit participating in the acceptance will introduce the situation. The construction unit introduces the project overview and self-inspection status, the design unit introduces the fire protection engineering design status, the construction unit introduces the project construction and debugging status, the supervision unit introduces the project supervision status, and the testing unit introduces the testing status.
(2) Group on-site inspection and acceptance. Acceptance personnel should inspect and test at the same time, and truthfully fill in the fire acceptance record form.
(3) Summarize the acceptance status. Each group reports on the acceptance status respectively. According to the "Guangdong Province Construction Project Fire Acceptance Assessment Rules (Trial)" formulated by the Corps, assessments are carried out according to sub-item, single item, and comprehensive procedures. The assessment conclusions are truthfully recorded in the acceptance record form, and Provide preliminary opinions to construction, construction, design and other units participating in the acceptance inspection, and promptly provide rectification opinions to the construction unit for those that do not meet the requirements of the specification.
4. When the construction, construction and design units participating in the acceptance inspection express opinions or raise questions, the participants in the acceptance inspection of the fire protection agency should give a reply. Those who cannot reply on the spot should give an explanation.
5. After the fire protection project has passed the acceptance or re-inspection, the acceptance personnel of each unit and the fire protection agency shall sign on the acceptance declaration form.
6. The project acceptance contractor should fill in the acceptance opinion letter in a timely manner, submit the approval form, and organize the acceptance files and send them to the leadership for approval.
7. The construction unit will go to the window and issue a receipt to retrieve the acceptance letter;
8. When the acceptance and reexamination fail, the construction unit should organize all relevant units to comply with the "Construction Project Fire Protection The problems raised in the "Acceptance Opinion Letter" will be rectified. After the rectification is completed, a re-inspection application will be made to the public case fire protection agency. The re-inspection procedures are the same as those for application for acceptance.
9. If the construction project fails to pass the acceptance inspection, the application materials will not be returned. When applying for re-inspection, the application information is the same as the normal application and acceptance information.